1409 N HAZELWOOD AVE 90041
Certificate Information: 1409 N HAZELWOOD AVE 90041
- Application / Permit
- 19010-10000-06062
- Plan Check / Job No.
- B19LA27116
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 1-STORY (24' X 32') ADU [2 BEDROOM , 1 BATHROOM] per AB 494, SB 229 and Ordinance 186,481. Provide one new open parking space.
- Permit Issued
- Issued on 8/2/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/10/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/23/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/7/2020 | JESSE JIMENEZ |
| Green Plans Picked Up | 1/8/2020 | APPLICANT |
| Corrections Issued | 1/22/2020 | JESSE JIMENEZ |
| Quality Review Completed | 1/26/2020 | YOUNG KIM |
| Applicant returned to address corrections | 8/31/2020 | JESSE JIMENEZ |
| Applicant returned to address corrections | 1/19/2022 | JESSE JIMENEZ |
| Building Plans Picked Up | 3/15/2022 | APPLICANT |
| Applicant returned to address corrections | 5/4/2022 | JESSE JIMENEZ |
| Plan Check Approved | 5/17/2022 | JESSE JIMENEZ |
| Issued | 8/2/2022 | APPLICANT |
| CofO in Progress | 6/20/2023 | JAVIER RAMOS SR |
| CofO in Progress | 6/20/2023 | JAVIER RAMOS SR |
| Permit Finaled | 7/10/2023 | DANIEL SANCHEZ |
| CofO Issued | 7/10/2023 | DANIEL SANCHEZ |
| Permit Finaled | 7/10/2023 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Address approval | Cleared | 3/6/2020 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 3/6/2020 | CELINA MORENO |
| Grading Pre-Inspection | Cleared | 3/6/2020 | PATRICK MISCHLICH |
| Green Code | Cleared | 3/6/2020 | DONALD CRICHLOW |
| Hydrant and Access approval | Cleared | 3/6/2020 | ROBERT DUFF |
| Miscellaneous | Cleared | 3/6/2020 | MINA GRAIS |
| Sewer availability | Cleared | 3/6/2020 | CELINA MORENO |
| Low Impact Development | Cleared | 7/30/2020 | SARAH YOUSSEF |
| GPI Written Notices | Cleared | 2/2/2021 | JESSE JIMENEZ |
| Roof/Waste drainage to street | Cleared | 9/16/2021 | THAN WIN |
| Miscellaneous | Cleared | 5/3/2022 | DANIEL SCHNEIDEREIT |
Contact Information
| Contractor | Rocka Builders Inc; Lic. No.: 1050219-B | 409 N PACIFIC COAST HWY #692 REDONDO BEACH, CA 90277 |
| Engineer | Cass,, James Edward; Lic. No.: S6385 | 828 CRESCENT DR MONROVIA, CA 91016 |
Inspector Information
| THOMAS WILLIS, (213) 252-3038 | Office Hours: 7:00-8:00 AM MON-FRI |
| JEFFREY CHRISTIAN, (213) 252-3038 | Office Hours: 7:00-8:00 AM MON-FRI |
| FERMIN RUBIO, (213) 252-3038 | Office Hours: 7:00-8:00 AM MON-FRI |
| JACOB SEGURA, (213) 252-3038 | Office Hours: 7:00-8:00 AM MON-FRI |
| CLAUDIO MORENO, (213) 252-3038 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK RUDE, (213) 252-3038 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/9/2022 | Corrections Issued | JAVIER RAMOS SR |
| Excavation/Setback/Form/Re-Bar | 10/18/2022 | No Access for Inspection | JAVIER RAMOS SR |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2022 | Not Ready for Inspection | JAVIER RAMOS SR |
| Sewer | 10/24/2022 | Not Ready for Inspection | JAVIER RAMOS SR |
| Footing/Foundation/Slab | 10/27/2022 | Approved | JAVIER RAMOS SR |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2022 | Partial Approval | JAVIER RAMOS SR |
| PLUMBING-Rough | 11/21/2022 | Not Ready for Inspection | JAVIER RAMOS SR |
| ELECTRICAL-Rough | 12/15/2022 | Partial Approval | JAVIER RAMOS SR |
| HVAC-Rough | 12/15/2022 | Not Ready for Inspection | JAVIER RAMOS SR |
| PLUMBING-Rough | 12/15/2022 | Approved | JAVIER RAMOS SR |
| Underground Mechanical | 12/15/2022 | Partial Approval | JAVIER RAMOS SR |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2022 | Approved | JAVIER RAMOS SR |
| Wood Frame | 12/19/2022 | Approved | JAVIER RAMOS SR |
| Insulation | 12/20/2022 | Approved | JAVIER RAMOS SR |
| Interior/Exterior Lathing | 12/20/2022 | Approved | JAVIER RAMOS SR |
| Drywall Nailing | 12/23/2022 | Approved | GORDON ZUBER |
| Interior/Exterior Lathing | 1/26/2023 | Approved | JAVIER RAMOS SR |
| Shower Pan | 1/26/2023 | Approved | JAVIER RAMOS SR |
| Floor/Roof Diaphrgm/Shear Wall | 2/8/2023 | Approved | JAVIER RAMOS SR |
| BUILDING-Rough-Frame | 5/8/2023 | Approved | JAVIER RAMOS SR |
| ELECTRICAL-Final | 5/8/2023 | Approved | JAVIER RAMOS SR |
| Final | 5/8/2023 | Not Ready for Inspection | JAVIER RAMOS SR |
| Green Building Final | 5/8/2023 | Approved | JAVIER RAMOS SR |
| Green Building Rough | 5/8/2023 | Approved | JAVIER RAMOS SR |
| HVAC-Final | 5/8/2023 | Not Ready for Inspection | JAVIER RAMOS SR |
| PLUMBING-Final | 5/8/2023 | Approved | JAVIER RAMOS SR |
| SGSOV-Seismic Gas S/O Valve | 5/8/2023 | SGSOV Approved | JAVIER RAMOS SR |
| Service/Power Release | 5/8/2023 | Not Required | JAVIER RAMOS SR |
| Smoke Detectors | 5/8/2023 | Approved | JAVIER RAMOS SR |
| Gas Test | 5/11/2023 | Approved | JAVIER RAMOS SR |
| HVAC-Final | 5/11/2023 | Partial Approval | JAVIER RAMOS SR |
| Final | 5/25/2023 | Not Ready for Inspection | JAVIER RAMOS SR |
| Final | 5/30/2023 | OK to Issue CofO | JAVIER RAMOS SR |
| HVAC-Final | 5/30/2023 | Approved | JAVIER RAMOS SR |
| PLUMBING-Final | 5/30/2023 | Approved | JAVIER RAMOS SR |