2588 S BUNDY DR 90064
Certificate Information: 2588 S BUNDY DR 90064
- Application / Permit
- 19010-10000-06031
- Plan Check / Job No.
- B19LA27088
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-STORY 25'X25' ACCESSORY DWELLING UNIT WITH 2-CAR GARAGE
- Permit Issued
- Issued on 3/22/2021
- Issuing Office
- Current Status
- CofO Issued on 2/26/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/23/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/10/2020 | MANUEL MONTUFAR |
| Corrections Issued | 1/14/2020 | AMIR DANAI |
| Quality Review Completed | 1/24/2020 | JASON HEALEY |
| Applicant returned to address corrections | 9/22/2020 | AMIR DANAI |
| Building Plans Picked Up | 9/25/2020 | APPLICANT |
| Green Plans Picked Up | 10/22/2020 | APPLICANT |
| Applicant returned to address corrections | 12/28/2020 | MANUEL MONTUFAR |
| Plan Check Approved | 1/11/2021 | MANUEL MONTUFAR |
| Issued | 3/22/2021 | APPLICANT |
| CofO in Progress | 2/25/2022 | KENNETH NAGLE |
| Permit Finaled | 2/26/2022 | DANIEL ORRANTE |
| CofO Issued | 2/26/2022 | DANIEL ORRANTE |
| Permit Finaled | 2/26/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 9/15/2020 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 9/15/2020 | SAUL GARCIA |
| Sewer availability | Cleared | 9/15/2020 | SAUL GARCIA |
| Construction near power lines | Cleared | 9/28/2020 | OSCAR CASTRO |
| Construction within easement | Cleared | 9/28/2020 | OSCAR CASTRO |
| Specific Plan | Cleared | 9/30/2020 | PEDRO AYALA |
| Hydrant and Access approval | Cleared | 10/7/2020 | KURT CORRAL |
| Low Impact Development | Cleared | 12/9/2020 | MARTIN FRAGOSO |
| Green Code | Cleared | 12/10/2020 | AARON COSTA |
| Roof/Waste drainage to street | Cleared | 12/11/2020 | SAUL GARCIA |
Contact Information
| Contractor | Williamson John Construction Inc; Lic. No.: 451421-B | 8723 BLERIOT AVE LOS ANGELES, CA 90045 |
| Engineer | Kim,, Taewon; Lic. No.: C80632 | 28000 S WESTERN AVE UNIT 209 SAN PEDRO, CA 90732 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 4/16/2021 | Not Ready for Inspection | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 4/16/2021 | Corrections Issued | EVAN COOPER |
| PLUMBING-Rough | 4/16/2021 | Not Ready for Inspection | EVAN COOPER |
| Service/Power Release | 4/16/2021 | Approved | EVAN COOPER |
| Underground Mechanical | 4/16/2021 | Not Ready for Inspection | EVAN COOPER |
| Footing/Foundation/Slab | 4/27/2021 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 5/11/2021 | No Access for Inspection | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 5/11/2021 | Approved | KENNETH NAGLE |
| Footing/Foundation/Slab | 5/11/2021 | No Access for Inspection | OGANES TARAKHCHYAN |
| Special/Order Compliance | 5/13/2021 | Corrections Issued | KENNETH NAGLE |
| Deputy Wood Construction | 5/14/2021 | Conditional Approval | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 5/18/2021 | Conditional Approval | EVAN COOPER |
| PLUMBING-Rough | 5/18/2021 | Conditional Approval | EVAN COOPER |
| Special/Order Compliance | 5/18/2021 | Corrections Issued | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2021 | Partial Approval | OGANES TARAKHCHYAN |
| HVAC-Rough | 5/28/2021 | Approved | OGANES TARAKHCHYAN |
| Wood Frame | 5/28/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Insulation | 6/14/2021 | Corrections Issued | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 6/14/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 6/24/2021 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 6/24/2021 | Approved | OGANES TARAKHCHYAN |
| Insulation | 6/24/2021 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 6/24/2021 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 6/24/2021 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 7/6/2021 | Approved | DONALD GALLAGHER |
| Green Building Rough | 7/6/2021 | Approved | DONALD GALLAGHER |
| ELECTRICAL-Final | 8/23/2021 | Corrections Issued | EVAN COOPER |
| HVAC-Final | 8/23/2021 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Final | 8/23/2021 | Not Ready for Inspection | EVAN COOPER |
| Sewer | 8/27/2021 | Approved | EVAN COOPER |
| Underground Mechanical | 8/27/2021 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 11/8/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Final | 11/8/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Green Building Final | 11/8/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 11/8/2021 | SGSOV Not Ready | JOHNNY MIRANDA |
| Smoke Detectors | 11/8/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Verify Sprinkler Sign Off | 11/8/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 1/5/2022 | Approved | JOHNNY MIRANDA |
| Final | 1/5/2022 | Partial Approval | JOHNNY MIRANDA |
| Green Building Final | 1/5/2022 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 1/5/2022 | SGSOV Approved | JOHNNY MIRANDA |
| Smoke Detectors | 1/5/2022 | Approved | JOHNNY MIRANDA |
| Verify Sprinkler Sign Off | 1/5/2022 | Approved | JOHNNY MIRANDA |