2588 S BUNDY DR 90064

Certificate Information: 2588 S BUNDY DR 90064

Application / Permit
19010-10000-06031
Plan Check / Job No.
B19LA27088
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2-STORY 25'X25' ACCESSORY DWELLING UNIT WITH 2-CAR GARAGE
Permit Issued
Issued on 3/22/2021
Issuing Office
Current Status
CofO Issued on 2/26/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/23/2019 APPLICANT
Assigned to Plan Check Engineer 1/10/2020 MANUEL MONTUFAR
Corrections Issued 1/14/2020 AMIR DANAI
Quality Review Completed 1/24/2020 JASON HEALEY
Applicant returned to address corrections 9/22/2020 AMIR DANAI
Building Plans Picked Up 9/25/2020 APPLICANT
Green Plans Picked Up 10/22/2020 APPLICANT
Applicant returned to address corrections 12/28/2020 MANUEL MONTUFAR
Plan Check Approved 1/11/2021 MANUEL MONTUFAR
Issued 3/22/2021 APPLICANT
CofO in Progress 2/25/2022 KENNETH NAGLE
Permit Finaled 2/26/2022 DANIEL ORRANTE
CofO Issued 2/26/2022 DANIEL ORRANTE
Permit Finaled 2/26/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 9/15/2020 SAUL GARCIA
Eng Process Fee Ord 176,300 Cleared 9/15/2020 SAUL GARCIA
Sewer availability Cleared 9/15/2020 SAUL GARCIA
Construction near power lines Cleared 9/28/2020 OSCAR CASTRO
Construction within easement Cleared 9/28/2020 OSCAR CASTRO
Specific Plan Cleared 9/30/2020 PEDRO AYALA
Hydrant and Access approval Cleared 10/7/2020 KURT CORRAL
Low Impact Development Cleared 12/9/2020 MARTIN FRAGOSO
Green Code Cleared 12/10/2020 AARON COSTA
Roof/Waste drainage to street Cleared 12/11/2020 SAUL GARCIA

Contact Information

Contractor Williamson John Construction Inc; Lic. No.: 451421-B 8723 BLERIOT AVE      LOS ANGELES, CA 90045
Engineer Kim,, Taewon; Lic. No.: C80632 28000 S WESTERN AVE UNIT 209      SAN PEDRO, CA 90732

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 4/16/2021 Not Ready for Inspection EVAN COOPER
Excavation/Setback/Form/Re-Bar 4/16/2021 Corrections Issued EVAN COOPER
PLUMBING-Rough 4/16/2021 Not Ready for Inspection EVAN COOPER
Service/Power Release 4/16/2021 Approved EVAN COOPER
Underground Mechanical 4/16/2021 Not Ready for Inspection EVAN COOPER
Footing/Foundation/Slab 4/27/2021 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 5/11/2021 No Access for Inspection OGANES TARAKHCHYAN
Footing/Foundation/Slab 5/11/2021 Approved KENNETH NAGLE
Footing/Foundation/Slab 5/11/2021 No Access for Inspection OGANES TARAKHCHYAN
Special/Order Compliance 5/13/2021 Corrections Issued KENNETH NAGLE
Deputy Wood Construction 5/14/2021 Conditional Approval KEVIN SARGSYAN
ELECTRICAL-Rough 5/18/2021 Conditional Approval EVAN COOPER
PLUMBING-Rough 5/18/2021 Conditional Approval EVAN COOPER
Special/Order Compliance 5/18/2021 Corrections Issued EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 5/28/2021 Partial Approval OGANES TARAKHCHYAN
HVAC-Rough 5/28/2021 Approved OGANES TARAKHCHYAN
Wood Frame 5/28/2021 Partial Approval OGANES TARAKHCHYAN
Insulation 6/14/2021 Corrections Issued KEVIN SARGSYAN
Interior/Exterior Lathing 6/14/2021 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Rough 6/24/2021 Approved OGANES TARAKHCHYAN
HVAC-Rough 6/24/2021 Approved OGANES TARAKHCHYAN
Insulation 6/24/2021 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 6/24/2021 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Rough 6/24/2021 Approved OGANES TARAKHCHYAN
Drywall Nailing 7/6/2021 Approved DONALD GALLAGHER
Green Building Rough 7/6/2021 Approved DONALD GALLAGHER
ELECTRICAL-Final 8/23/2021 Corrections Issued EVAN COOPER
HVAC-Final 8/23/2021 Not Ready for Inspection EVAN COOPER
PLUMBING-Final 8/23/2021 Not Ready for Inspection EVAN COOPER
Sewer 8/27/2021 Approved EVAN COOPER
Underground Mechanical 8/27/2021 Approved EVAN COOPER
BUILDING-Rough-Frame 11/8/2021 Not Ready for Inspection JOHNNY MIRANDA
Final 11/8/2021 Not Ready for Inspection JOHNNY MIRANDA
Green Building Final 11/8/2021 Not Ready for Inspection JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 11/8/2021 SGSOV Not Ready JOHNNY MIRANDA
Smoke Detectors 11/8/2021 Not Ready for Inspection JOHNNY MIRANDA
Verify Sprinkler Sign Off 11/8/2021 Not Ready for Inspection JOHNNY MIRANDA
BUILDING-Rough-Frame 1/5/2022 Approved JOHNNY MIRANDA
Final 1/5/2022 Partial Approval JOHNNY MIRANDA
Green Building Final 1/5/2022 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 1/5/2022 SGSOV Approved JOHNNY MIRANDA
Smoke Detectors 1/5/2022 Approved JOHNNY MIRANDA
Verify Sprinkler Sign Off 1/5/2022 Approved JOHNNY MIRANDA