827 1/2 E 87TH PL 90002

Certificate Information: 827 1/2 E 87TH PL 90002

Application / Permit
19010-10000-05997
Plan Check / Job No.
B19LA27072
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW SINGLE-STORY 1000 SQFT ACCESSARY DWELLING UNIT WITH ATTACHED COVERED CAR PORT PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g
Permit Issued
Issued on 11/9/2020
Issuing Office
Metro
Current Status
CofO Issued on 5/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/23/2019 APPLICANT
Assigned to Plan Check Engineer 1/7/2020 RAHEL BEYENE
Green Plans Picked Up 1/8/2020 APPLICANT
Corrections Issued 1/15/2020 RAHEL BEYENE
Quality Review Completed 1/18/2020 STANLEY RAAP
Applicant returned to address corrections 4/15/2020 RAHEL BEYENE
Applicant returned to address corrections 9/8/2020 RAHEL BEYENE
Plan Check Approved 10/19/2020 RAHEL BEYENE
Issued 11/9/2020 APPLICANT
Building Plans Picked Up 11/9/2020 APPLICANT
CofO in Progress 5/1/2024 MICHAEL LEWIS
Permit Finaled 5/7/2024 DEROLD HAUFF
Permit Finaled 5/7/2024 DEROLD HAUFF
CofO Issued 5/7/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/7/2020 JEANIE LAM
Community Plan Implem. Overlay Cleared 2/7/2020 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 2/7/2020 JEANIE LAM
Hydrant and Access approval Cleared 2/7/2020 JOHN CONNEALLY
Permit Cleared 2/7/2020 JEANIE LAM
Sewer availability Cleared 2/7/2020 JEANIE LAM
Green Code Cleared 3/17/2020 DONALD CRICHLOW
Green Code Cleared 3/17/2020 DONALD CRICHLOW
Low Impact Development Cleared 8/12/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 9/25/2020 CECILIO NAVARRO

Contact Information

Contractor Owner-Builder       ,
Engineer Phan,, Phillip Trung Tri; Lic. No.: C76425 19221 E NORTHAM ST      WEST COVINA, CA 91792

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/11/2020 Partial Approval ALEJANDRO DE ARTOLA
Underground Mechanical 12/11/2020 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 12/17/2020 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 1/26/2021 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 2/5/2021 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 5/12/2021 Conditional Approval FREDDIE RIVERA
ELECTRICAL-Rough 5/12/2021 Approved FREDDIE RIVERA
Green Building Rough 5/12/2021 Approved FREDDIE RIVERA
HVAC-Rough 5/12/2021 Conditional Approval FREDDIE RIVERA
PLUMBING-Rough 5/12/2021 Approved FREDDIE RIVERA
Pre-Inspection 5/12/2021 Corrections Issued FREDDIE RIVERA
Verify Sprinkler Sign Off 5/12/2021 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 6/7/2021 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 6/7/2021 Corrections Issued ALEJANDRO DE ARTOLA
Insulation 6/14/2021 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 6/16/2021 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 6/16/2021 Approved ALEJANDRO DE ARTOLA
Shower Pan 6/16/2021 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 7/30/2021 Partial Approval ALEJANDRO DE ARTOLA
Shower Pan 7/30/2021 Approved ALEJANDRO DE ARTOLA
Final 4/5/2022 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 4/5/2022 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 4/5/2022 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 4/5/2022 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 4/5/2022 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 4/5/2022 SGSOV Not Ready ALEJANDRO DE ARTOLA
Service/Power Release 4/5/2022 Corrections Issued ALEJANDRO DE ARTOLA
Smoke Detectors 4/5/2022 Corrections Issued ALEJANDRO DE ARTOLA
Final 8/31/2023 Corrections Issued MICHAEL LEWIS
Gas Test 8/31/2023 Approved MICHAEL LEWIS
Green Building Final 8/31/2023 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 8/31/2023 SGSOV Not Ready MICHAEL LEWIS
Service/Power Release 8/31/2023 Partial Inspection MICHAEL LEWIS
Smoke Detectors 8/31/2023 Approved MICHAEL LEWIS
Final 9/7/2023 Corrections Issued MICHAEL LEWIS
HVAC-Final 9/7/2023 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 9/7/2023 SGSOV Approved MICHAEL LEWIS
Service/Power Release 9/7/2023 Approved MICHAEL LEWIS
Final 11/27/2023 Not Ready for Inspection JOSEPH MCGARRY
Final 4/30/2024 OK to Issue CofO MICHAEL LEWIS