511 W 105TH ST 90044

Certificate Information: 511 W 105TH ST 90044

Application / Permit
19010-10000-05905
Plan Check / Job No.
B19LA26957
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1200 SF DETACHED ADU DETTACHED PER WFPP AND ADU ORDINANCE 186481
Permit Issued
Issued on 11/16/2020
Issuing Office
Current Status
CofO Issued on 9/4/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/20/2019 APPLICANT
Assigned to Plan Check Engineer 1/10/2020 STARR CHEN
Corrections Issued 1/16/2020 STARR CHEN
Quality Review Completed 1/16/2020 JASON HEALEY
Building Plans Picked Up 1/17/2020 APPLICANT
Green Plans Picked Up 1/31/2020 APPLICANT
Applicant returned to address corrections 9/16/2020 STARR CHEN
Applicant returned to address corrections 10/21/2020 STARR CHEN
Applicant returned to address corrections 10/29/2020 STARR CHEN
Applicant returned to address corrections 11/13/2020 STARR CHEN
Plan Check Approved 11/13/2020 STARR CHEN
Issued 11/16/2020 APPLICANT
CofO in Progress 7/1/2021 EUGENE CASSIDY
Permit Finaled 9/4/2021 DEROLD HAUFF
CofO Issued 9/4/2021 DEROLD HAUFF
Permit Finaled 9/4/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/28/2020 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 1/31/2020 JEANETTE VONG
Sewer availability Cleared 1/31/2020 JEANETTE VONG
Low Impact Development Cleared 2/19/2020 SARAH YOUSSEF
Green Code Cleared 2/28/2020 STARR CHEN
Roof/Waste drainage to street Cleared 2/28/2020 JEANETTE VONG
Construction near power lines Cleared 8/22/2020 RIDWAN HARDY

Contact Information

Architect Garcia,, Hugo; Lic. No.: C33055 6429 DOS RIOS ROAD      DOWNEY, CA 90240
Contractor Owner-Builder       ,

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/17/2020 Partial Approval EUGENE CASSIDY
Underground Mechanical 12/17/2020 Conditional Approval EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 12/22/2020 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 1/15/2021 Corrections Issued EUGENE CASSIDY
BUILDING-Rough-Frame 1/20/2021 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Rough 1/20/2021 Not Ready for Inspection EUGENE CASSIDY
Green Building Rough 1/20/2021 Approved EUGENE CASSIDY
Rough-Elec/Plmb/HVAC 1/20/2021 Corrections Issued EUGENE CASSIDY
Verify Sprinkler Sign Off 1/20/2021 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 1/25/2021 Approved EUGENE CASSIDY
ELECTRICAL-Rough 1/25/2021 Approved EUGENE CASSIDY
HVAC-Rough 1/25/2021 Approved EUGENE CASSIDY
Interior/Exterior Lathing 1/25/2021 Approved EUGENE CASSIDY
PLUMBING-Rough 1/25/2021 Approved EUGENE CASSIDY
Insulation 1/28/2021 Approved EUGENE CASSIDY
Drywall Nailing 2/1/2021 Approved EUGENE CASSIDY
Gas Test 2/24/2021 Approved EUGENE CASSIDY
Sewer 2/24/2021 Approved EUGENE CASSIDY
Final 4/9/2021 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 4/9/2021 Approved EUGENE CASSIDY
Green Building Final 4/9/2021 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 4/9/2021 SGSOV Not Ready EUGENE CASSIDY
Service/Power Release 4/9/2021 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 4/9/2021 Not Ready for Inspection EUGENE CASSIDY
Final 4/15/2021 Corrections Issued EUGENE CASSIDY
Green Building Final 4/15/2021 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 4/15/2021 SGSOV Approved EUGENE CASSIDY
Service/Power Release 4/15/2021 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 4/15/2021 Approved EUGENE CASSIDY
Final 4/23/2021 Corrections Issued EUGENE CASSIDY
Service/Power Release 4/23/2021 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 6/30/2021 Approved EUGENE CASSIDY
Final 6/30/2021 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 6/30/2021 Approved EUGENE CASSIDY
PLUMBING-Final 6/30/2021 Approved EUGENE CASSIDY
Service/Power Release 6/30/2021 Approved EUGENE CASSIDY