2726-2728 N ALTA ST 90031
Certificate Information: 2726-2728 N ALTA ST 90031
- Application / Permit
- 19010-10000-05896
- Plan Check / Job No.
- B19LA09732
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Carport
- Work Description
- (N) Detached carport per city standard detail
- Permit Issued
- Issued on 1/30/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/13/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/13/2019 | APPLICANT |
| Green Plans Picked Up | 5/24/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/30/2019 | SHANGQIN XIE |
| Corrections Issued | 6/5/2019 | SHANGQIN XIE |
| Quality Review Completed | 6/24/2019 | KESETE HAREGOT |
| Building Plans Picked Up | 6/25/2019 | APPLICANT |
| Applicant returned to address corrections | 12/20/2019 | SHANGQIN XIE |
| Applicant returned to address corrections | 1/22/2020 | SHANGQIN XIE |
| Plan Check Approved | 1/30/2020 | SHANGQIN XIE |
| Issued | 1/30/2020 | LADBS |
| CofO in Progress | 8/2/2021 | SCOTT FINNILA |
| Permit Finaled | 8/13/2021 | DEROLD HAUFF |
| CofO Issued | 8/13/2021 | DEROLD HAUFF |
| Permit Finaled | 8/13/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| "D" conditions | Cleared | 1/22/2020 | SARAHI ORTEGA |
| "Q" conditions | Cleared | 1/22/2020 | SARAHI ORTEGA |
| Eng Process Fee Ord 176,300 | Cleared | 1/22/2020 | EMIL KYUPELYAN |
| Low Impact Development | Cleared | 1/22/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 1/22/2020 | EMIL KYUPELYAN |
| Grading Pre-Inspection | Cleared | 1/30/2020 | SHANGQIN XIE |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/16/2020 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2020 | Approved | OSVALDO PARAMO |
| Green Building Rough | 6/23/2020 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 7/27/2021 | Approved | SCOTT FINNILA |
| Final | 7/27/2021 | Partial Inspection | SCOTT FINNILA |
| Green Building Final | 7/27/2021 | Approved | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 7/27/2021 | SGSOV Approved | SCOTT FINNILA |
| Service/Power Release | 7/27/2021 | Partial Inspection | SCOTT FINNILA |
| Smoke Detectors | 7/27/2021 | Approved | SCOTT FINNILA |
| Final | 8/2/2021 | OK to Issue CofO | SCOTT FINNILA |