Piling/Pier/Caisson
|
2/8/2023
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Pre-Inspection
|
2/8/2023
|
Partial Inspection
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
2/27/2023
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
2/28/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Concrete
|
3/2/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Special/Order Compliance
|
3/2/2023
|
Approved
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
3/7/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Steel/Welding
|
3/31/2023
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Steel/Welding
|
4/10/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Steel/Welding
|
4/26/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Reinf. Concrete
|
4/28/2023
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Excavation/Setback/Form/Re-Bar
|
4/28/2023
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
4/28/2023
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
5/1/2023
|
Conditional Approval
|
GREGORY POMISH
|
|
Excavation/Setback/Form/Re-Bar
|
5/1/2023
|
Partial Approval
|
GREGORY POMISH
|
|
Deputy Reinf. Concrete
|
5/4/2023
|
Conditional Approval
|
GREGORY POMISH
|
|
Deputy Reinf. Concrete
|
5/5/2023
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Footing/Foundation/Slab
|
5/5/2023
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Concrete
|
5/8/2023
|
Approved
|
DAVID BURKHEAD
|
|
Excavation/Setback/Form/Re-Bar
|
5/8/2023
|
Partial Approval
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
5/9/2023
|
Partial Approval
|
DAVID BURKHEAD
|
|
Excavation/Setback/Form/Re-Bar
|
5/10/2023
|
Partial Approval
|
DAVID BURKHEAD
|
|
Green Building Rough
|
5/10/2023
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Verify Sprinkler Sign Off
|
5/10/2023
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Wood Frame
|
5/10/2023
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
5/15/2023
|
Approved
|
DAVID BURKHEAD
|
|
Excavation/Setback/Form/Re-Bar
|
5/15/2023
|
Partial Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
5/16/2023
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
5/16/2023
|
Partial Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
5/19/2023
|
Approved
|
DAVID BURKHEAD
|
|
Excavation/Setback/Form/Re-Bar
|
5/19/2023
|
Partial Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
5/22/2023
|
Conditional Approval
|
GREGORY POMISH
|
|
Green Building Rough
|
5/22/2023
|
Partial Inspection
|
GREGORY POMISH
|
|
Reinforced Concrete Frame
|
5/22/2023
|
Partial Approval
|
GREGORY POMISH
|
|
Verify Sprinkler Sign Off
|
5/22/2023
|
Partial Inspection
|
GREGORY POMISH
|
|
Deputy Reinf. Concrete
|
6/29/2023
|
Approved
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
6/29/2023
|
Partial Approval
|
DAVID BURKHEAD
|
|
Deputy Drilled-In Anchors
|
7/18/2023
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
7/24/2023
|
Approved
|
DAVID BURKHEAD
|
|
Excavation/Setback/Form/Re-Bar
|
7/24/2023
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
8/7/2023
|
Conditional Approval
|
LARRY ARNICK
|
|
Excavation/Setback/Form/Re-Bar
|
8/9/2023
|
Partial Approval
|
DAVID BURKHEAD
|
|
Deputy Drilled-In Anchors
|
8/10/2023
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Steel/Welding
|
8/23/2023
|
Conditional Approval
|
RONALD JIMENEZ
|
|
Footing/Foundation/Slab
|
8/23/2023
|
Partial Approval
|
RONALD JIMENEZ
|
|
Structural Steel Frame
|
8/23/2023
|
Partial Inspection
|
RONALD JIMENEZ
|
|
Deputy Steel/Welding
|
8/24/2023
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Steel/Welding
|
8/25/2023
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
8/30/2023
|
Partial Approval
|
TIMOTHY POWELL
|
|
Deputy Steel/Welding
|
9/7/2023
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Masonry
|
9/11/2023
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Masonry Wall/Backfill
|
9/12/2023
|
Partial Inspection
|
GREGORY POMISH
|
|
Deputy Steel/Welding
|
9/15/2023
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/25/2023
|
Partial Approval
|
DAVID BURKHEAD
|
|
Deputy Steel/Welding
|
9/26/2023
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Steel/Welding
|
10/5/2023
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Wood Construction
|
10/5/2023
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Reinf. Concrete
|
10/11/2023
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Excavation/Setback/Form/Re-Bar
|
10/11/2023
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Concrete
|
10/12/2023
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/19/2023
|
Partial Approval
|
GREGORY POMISH
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/24/2023
|
Partial Approval
|
DAVID BURKHEAD
|
|
Deputy Wood Construction
|
11/17/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Wood Construction
|
11/20/2023
|
Conditional Approval
|
GREGORY POMISH
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/20/2023
|
Partial Approval
|
GREGORY POMISH
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/11/2023
|
Partial Approval
|
GREGORY POMISH
|
|
Deputy Wood Construction
|
12/21/2023
|
Conditional Approval
|
GREGORY POMISH
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/21/2023
|
Partial Approval
|
GREGORY POMISH
|
|
Deputy Wood Construction
|
1/10/2024
|
No Access for Inspection
|
MICHAEL ROSENBERG
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/11/2024
|
Partial Approval
|
GREGORY POMISH
|
|
Deputy Wood Construction
|
1/16/2024
|
No Access for Inspection
|
MICHAEL ROSENBERG
|
|
Interior/Exterior Lathing
|
2/20/2024
|
Partial Inspection
|
TIMOTHY POWELL
|
|
Green Building Rough
|
2/21/2024
|
Not Ready for Inspection
|
TIMOTHY POWELL
|
|
Verify Sprinkler Sign Off
|
2/21/2024
|
Not Ready for Inspection
|
TIMOTHY POWELL
|
|
Wood Frame
|
2/21/2024
|
Partial Approval
|
TIMOTHY POWELL
|
|
Wood Frame
|
2/23/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Green Building Rough
|
2/28/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Verify Sprinkler Sign Off
|
2/28/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Wood Frame
|
2/28/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/4/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Deputy Wood Construction
|
3/11/2024
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/11/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Deputy Wood Construction
|
3/14/2024
|
No Access for Inspection
|
MICHAEL ROSENBERG
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/19/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Green Building Rough
|
3/26/2024
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Verify Sprinkler Sign Off
|
3/26/2024
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Wood Frame
|
3/26/2024
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Green Building Rough
|
4/10/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Verify Sprinkler Sign Off
|
4/10/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Wood Frame
|
4/10/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Insulation
|
4/16/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Green Building Rough
|
4/23/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Verify Sprinkler Sign Off
|
4/23/2024
|
Partial Inspection
|
DAVID BURKHEAD
|
|
Wood Frame
|
4/23/2024
|
Partial Inspection
|
DAVID BURKHEAD
|
|
Interior/Exterior Lathing
|
4/24/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Insulation
|
4/26/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Wood Frame
|
4/29/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/3/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/14/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Drywall Nailing
|
5/29/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Green Building Rough
|
5/29/2024
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/5/2024
|
Corrections Issued
|
JEFFREY FULTON
|
|
Drywall Nailing
|
6/10/2024
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/10/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Green Building Rough
|
6/10/2024
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Wood Frame
|
6/10/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Wood Frame
|
6/12/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Insulation
|
6/17/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
6/25/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Green Building Rough
|
6/25/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Drywall Nailing
|
7/10/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Green Building Rough
|
7/10/2024
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Green Building Rough
|
7/11/2024
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Verify Sprinkler Sign Off
|
7/11/2024
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Wood Frame
|
7/11/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Light Gage Steel Frame
|
7/12/2024
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Green Building Rough
|
7/15/2024
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Light Gage Steel Frame
|
7/15/2024
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Verify Sprinkler Sign Off
|
7/15/2024
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Insulation
|
7/18/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Insulation
|
7/22/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Wood Frame
|
7/22/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Light Gage Steel Frame
|
7/24/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Green Building Rough
|
7/26/2024
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Verify Sprinkler Sign Off
|
7/26/2024
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Wood Frame
|
7/26/2024
|
Corrections Issued
|
JEFFREY FULTON
|
|
Insulation
|
8/2/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Insulation
|
8/12/2024
|
Partial Approval
|
RAMAZANALI ALMASI
|
|
Interior/Exterior Lathing
|
8/19/2024
|
Partial Approval
|
LARRY ARNICK
|
|
Interior/Exterior Lathing
|
8/20/2024
|
Corrections Issued
|
LARRY ARNICK
|
|
Insulation
|
8/21/2024
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Insulation
|
8/23/2024
|
Partial Approval
|
LARRY ARNICK
|
|
Green Building Rough
|
8/26/2024
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Insulation
|
8/26/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Verify Sprinkler Sign Off
|
8/26/2024
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Wood Frame
|
8/26/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Insulation
|
8/27/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Wood Frame
|
8/27/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Green Building Rough
|
8/29/2024
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Verify Sprinkler Sign Off
|
8/29/2024
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Wood Frame
|
8/29/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Insulation
|
8/30/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Green Building Rough
|
9/3/2024
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Insulation
|
9/3/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Verify Sprinkler Sign Off
|
9/3/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Light Gage Steel Frame
|
9/4/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Wood Frame
|
9/4/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Green Building Rough
|
9/6/2024
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Verify Sprinkler Sign Off
|
9/6/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Wood Frame
|
9/6/2024
|
Partial Approval
|
DAVID BURKHEAD
|
|
Drywall Nailing
|
9/9/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
9/11/2024
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Insulation
|
9/11/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Verify Sprinkler Sign Off
|
9/11/2024
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Wood Frame
|
9/11/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Insulation
|
9/12/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Insulation
|
9/17/2024
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Insulation
|
9/18/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Drywall Nailing
|
9/20/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Green Building Rough
|
9/20/2024
|
Approved
|
JEFFREY FULTON
|
|
Drywall Nailing
|
9/26/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Drywall Nailing
|
10/1/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Insulation
|
10/1/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Light Gage Steel Frame
|
10/1/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Drywall Nailing
|
10/30/2024
|
Partial Inspection
|
JEFFREY FULTON
|
|
Light Gage Steel Frame
|
1/10/2025
|
Partial Inspection
|
JEFFREY FULTON
|
|
Masonry Wall/Backfill
|
1/10/2025
|
Partial Inspection
|
JEFFREY FULTON
|
|
Special/Order Compliance
|
4/2/2025
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Special/Order Compliance
|
4/7/2025
|
Partial Inspection
|
JEFFREY FULTON
|
|
Special/Order Compliance
|
10/29/2025
|
Partial Inspection
|
JEFFREY FULTON
|
|
Drywall Nailing
|
12/29/2025
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Final
|
12/29/2025
|
Partial Inspection
|
JEFFREY FULTON
|
|
Footing/Foundation/Slab
|
12/29/2025
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Green Building Final
|
12/29/2025
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Reinforced Concrete Frame
|
12/29/2025
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
SGSOV-Seismic Gas S/O Valve
|
12/29/2025
|
SGSOV Not Ready
|
JEFFREY FULTON
|
|
Smoke Detectors
|
12/29/2025
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Verify Sprinkler Sign Off
|
12/29/2025
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Wood Frame
|
12/29/2025
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Final
|
1/5/2026
|
Partial Inspection
|
JEFFREY FULTON
|
|
Pre-Inspection
|
1/8/2026
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Special/Order Compliance
|
1/8/2026
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Final
|
1/9/2026
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Drywall Nailing
|
3/6/2026
|
Approved
|
DAVID BURKHEAD
|
|
Final
|
3/6/2026
|
Partial Inspection
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
3/6/2026
|
Approved
|
DAVID BURKHEAD
|
|
Green Building Final
|
3/6/2026
|
Not Ready for Inspection
|
DAVID BURKHEAD
|
|
Reinforced Concrete Frame
|
3/6/2026
|
Conditional Approval
|
DAVID BURKHEAD
|
|
SGSOV-Seismic Gas S/O Valve
|
3/6/2026
|
SGSOV Approved
|
DAVID BURKHEAD
|
|
Smoke Detectors
|
3/6/2026
|
Approved
|
DAVID BURKHEAD
|
|
Verify Sprinkler Sign Off
|
3/6/2026
|
Approved
|
DAVID BURKHEAD
|
|
Wood Frame
|
3/6/2026
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Final
|
3/13/2026
|
Partial Approval
|
DAVID BURKHEAD
|
|
Green Building Final
|
3/13/2026
|
Approved
|
DAVID BURKHEAD
|
|
Reinforced Concrete Frame
|
3/13/2026
|
Approved
|
DAVID BURKHEAD
|
|
Wood Frame
|
3/13/2026
|
Approved
|
DAVID BURKHEAD
|
|
Final
|
5/12/2026
|
OK to Issue CofO
|
DAVID BURKHEAD
|