626 N WILTON PL 1-25 90004

Certificate Information: 626 N WILTON PL 1-25 90004

Application / Permit
19010-10000-05880
Plan Check / Job No.
B19LA26890
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 4-STORY 25-UNIT APARTMENT BUILDING WITH ONE LEVEL SUBTERRANEAN GARAGE
Permit Issued
Issued on 10/18/2022
Issuing Office
Metro
Current Status
CofO Issued on 5/18/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/20/2019 APPLICANT
Assigned to Plan Check Engineer 2/13/2020 SINA KHOSRAVI
Corrections Issued 3/2/2020 SINA KHOSRAVI
Quality Review Completed 3/7/2020 YOUNG KIM
Disabled Access Plans Picked Up 3/19/2020 APPLICANT
Applicant returned to address corrections 9/10/2020 GARO TELMI
Applicant returned to address corrections 10/14/2020 GARO TELMI
Applicant returned to address corrections 9/16/2021 SINA KHOSRAVI
Applicant returned to address corrections 9/22/2021 SINA KHOSRAVI
Applicant returned to address corrections 9/30/2021 SINA KHOSRAVI
Applicant returned to address corrections 10/7/2021 SINA KHOSRAVI
Green Plans Picked Up 10/20/2021 APPLICANT
Applicant returned to address corrections 11/4/2021 SINA KHOSRAVI
Building Plans Picked Up 11/5/2021 APPLICANT
Applicant returned to address corrections 8/10/2022 SINA KHOSRAVI
Plan Check Approved 8/26/2022 SINA KHOSRAVI
Issued 10/18/2022 APPLICANT
TCO Issued (Expire Date: 09-16-2026) 3/20/2026 ERNESTO CORRAL
CofO in Progress 5/12/2026 DAVID BURKHEAD
Permit Finaled 5/18/2026 RAFAEL ESPINOZA
CofO Issued 5/18/2026 RAFAEL ESPINOZA
Permit Finaled 5/18/2026 RAFAEL ESPINOZA

Permit Application Clearance Information

Address approval Cleared 7/29/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 7/29/2020 RENZ SORIANO
Hydrant and Access approval Cleared 9/25/2020 KURT CORRAL
Highway dedication Cleared 12/2/2020 JAMES MORALEZ
Construction near power lines Cleared 10/18/2021 RIDWAN HARDY
Green Code Cleared 10/19/2021 AARON COSTA
Sewer availability Cleared 10/22/2021 RENZ SORIANO
Building over 3-story or 36-ft Cleared 2/7/2022 CALOSHA APPROVED
Fire Marshall Fire Life Safety Cleared 3/22/2022 MENOA AGHAJANI
DAS Clearance Cleared 5/19/2022 SINA KHOSRAVI
Low Impact Development Cleared 6/16/2022 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 6/29/2022 WALLIE JONG
Hold Cleared 11/9/2022 MARIA VENDIVIL

Contact Information

Architect Tighe,, Patrick J; Lic. No.: C27987 5747 VENICE BLVD      LOS ANGELES, CA 90019
Contractor Lv Construction Llc; Lic. No.: 1043604-B 1768 MARY ROAD      ACTON, CA 93510
Engineer Irvine,, Jon Alan; Lic. No.: GE2891 145 N SIERRA MADRE BLVD STE 1      PASADENA, CA 91107
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007

Inspector Information

DAVID BURKHEAD, (213) 482-7294 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 2/8/2023 Not Ready for Inspection DAVID BURKHEAD
Pre-Inspection 2/8/2023 Partial Inspection DAVID BURKHEAD
Deputy Reinf. Concrete 2/27/2023 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 2/28/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 3/2/2023 Conditional Approval MICHAEL ROSENBERG
Special/Order Compliance 3/2/2023 Approved DAVID BURKHEAD
Deputy Reinf. Concrete 3/7/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 3/31/2023 Conditional Approval DAVID BURKHEAD
Deputy Steel/Welding 4/10/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Steel/Welding 4/26/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 4/28/2023 Conditional Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 4/28/2023 Not Ready for Inspection DAVID BURKHEAD
Footing/Foundation/Slab 4/28/2023 Not Ready for Inspection DAVID BURKHEAD
Deputy Reinf. Concrete 5/1/2023 Conditional Approval GREGORY POMISH
Excavation/Setback/Form/Re-Bar 5/1/2023 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 5/4/2023 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 5/5/2023 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 5/5/2023 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Reinf. Concrete 5/8/2023 Approved DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 5/8/2023 Partial Approval DAVID BURKHEAD
Footing/Foundation/Slab 5/9/2023 Partial Approval DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 5/10/2023 Partial Approval DAVID BURKHEAD
Green Building Rough 5/10/2023 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 5/10/2023 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 5/10/2023 Not Ready for Inspection DAVID BURKHEAD
Deputy Reinf. Concrete 5/15/2023 Approved DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 5/15/2023 Partial Approval DAVID BURKHEAD
Deputy Reinf. Concrete 5/16/2023 Conditional Approval DAVID BURKHEAD
Footing/Foundation/Slab 5/16/2023 Partial Approval DAVID BURKHEAD
Deputy Reinf. Concrete 5/19/2023 Approved DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 5/19/2023 Partial Approval DAVID BURKHEAD
Deputy Reinf. Concrete 5/22/2023 Conditional Approval GREGORY POMISH
Green Building Rough 5/22/2023 Partial Inspection GREGORY POMISH
Reinforced Concrete Frame 5/22/2023 Partial Approval GREGORY POMISH
Verify Sprinkler Sign Off 5/22/2023 Partial Inspection GREGORY POMISH
Deputy Reinf. Concrete 6/29/2023 Approved DAVID BURKHEAD
Footing/Foundation/Slab 6/29/2023 Partial Approval DAVID BURKHEAD
Deputy Drilled-In Anchors 7/18/2023 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 7/24/2023 Approved DAVID BURKHEAD
Excavation/Setback/Form/Re-Bar 7/24/2023 Not Ready for Inspection DAVID BURKHEAD
Deputy Reinf. Concrete 8/7/2023 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 8/9/2023 Partial Approval DAVID BURKHEAD
Deputy Drilled-In Anchors 8/10/2023 Conditional Approval DAVID BURKHEAD
Deputy Steel/Welding 8/23/2023 Conditional Approval RONALD JIMENEZ
Footing/Foundation/Slab 8/23/2023 Partial Approval RONALD JIMENEZ
Structural Steel Frame 8/23/2023 Partial Inspection RONALD JIMENEZ
Deputy Steel/Welding 8/24/2023 Conditional Approval DAVID BURKHEAD
Deputy Steel/Welding 8/25/2023 Conditional Approval DAVID BURKHEAD
Footing/Foundation/Slab 8/30/2023 Partial Approval TIMOTHY POWELL
Deputy Steel/Welding 9/7/2023 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Masonry 9/11/2023 Conditional Approval DAVID BURKHEAD
Masonry Wall/Backfill 9/12/2023 Partial Inspection GREGORY POMISH
Deputy Steel/Welding 9/15/2023 Conditional Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 9/25/2023 Partial Approval DAVID BURKHEAD
Deputy Steel/Welding 9/26/2023 Conditional Approval DAVID BURKHEAD
Deputy Steel/Welding 10/5/2023 Conditional Approval DAVID BURKHEAD
Deputy Wood Construction 10/5/2023 Conditional Approval DAVID BURKHEAD
Deputy Reinf. Concrete 10/11/2023 Conditional Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 10/11/2023 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 10/12/2023 Conditional Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 10/19/2023 Partial Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 10/24/2023 Partial Approval DAVID BURKHEAD
Deputy Wood Construction 11/17/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Wood Construction 11/20/2023 Conditional Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 11/20/2023 Partial Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 12/11/2023 Partial Approval GREGORY POMISH
Deputy Wood Construction 12/21/2023 Conditional Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 12/21/2023 Partial Approval GREGORY POMISH
Deputy Wood Construction 1/10/2024 No Access for Inspection MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 1/11/2024 Partial Approval GREGORY POMISH
Deputy Wood Construction 1/16/2024 No Access for Inspection MICHAEL ROSENBERG
Interior/Exterior Lathing 2/20/2024 Partial Inspection TIMOTHY POWELL
Green Building Rough 2/21/2024 Not Ready for Inspection TIMOTHY POWELL
Verify Sprinkler Sign Off 2/21/2024 Not Ready for Inspection TIMOTHY POWELL
Wood Frame 2/21/2024 Partial Approval TIMOTHY POWELL
Wood Frame 2/23/2024 Partial Approval DAVID BURKHEAD
Green Building Rough 2/28/2024 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 2/28/2024 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 2/28/2024 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 3/4/2024 Not Ready for Inspection DAVID BURKHEAD
Deputy Wood Construction 3/11/2024 Conditional Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 3/11/2024 Partial Approval DAVID BURKHEAD
Deputy Wood Construction 3/14/2024 No Access for Inspection MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 3/19/2024 Partial Inspection JEFFREY FULTON
Green Building Rough 3/26/2024 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 3/26/2024 Not Ready for Inspection JEFFREY FULTON
Wood Frame 3/26/2024 Not Ready for Inspection JEFFREY FULTON
Green Building Rough 4/10/2024 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 4/10/2024 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 4/10/2024 Partial Approval DAVID BURKHEAD
Insulation 4/16/2024 Partial Inspection JEFFREY FULTON
Green Building Rough 4/23/2024 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 4/23/2024 Partial Inspection DAVID BURKHEAD
Wood Frame 4/23/2024 Partial Inspection DAVID BURKHEAD
Interior/Exterior Lathing 4/24/2024 Partial Approval DAVID BURKHEAD
Insulation 4/26/2024 Partial Approval EDWIN GREGORYONA
Wood Frame 4/29/2024 Partial Approval DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 5/3/2024 Not Ready for Inspection DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 5/14/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 5/29/2024 Partial Inspection JEFFREY FULTON
Green Building Rough 5/29/2024 Not Ready for Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 6/5/2024 Corrections Issued JEFFREY FULTON
Drywall Nailing 6/10/2024 Not Ready for Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 6/10/2024 Partial Inspection JEFFREY FULTON
Green Building Rough 6/10/2024 Not Ready for Inspection JEFFREY FULTON
Wood Frame 6/10/2024 Partial Inspection JEFFREY FULTON
Wood Frame 6/12/2024 Partial Inspection JEFFREY FULTON
Insulation 6/17/2024 Partial Approval EDWIN GREGORYONA
Drywall Nailing 6/25/2024 Partial Inspection JEFFREY FULTON
Green Building Rough 6/25/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 7/10/2024 Partial Inspection JEFFREY FULTON
Green Building Rough 7/10/2024 Not Ready for Inspection JEFFREY FULTON
Green Building Rough 7/11/2024 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 7/11/2024 Not Ready for Inspection JEFFREY FULTON
Wood Frame 7/11/2024 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 7/12/2024 Not Ready for Inspection JEFFREY FULTON
Green Building Rough 7/15/2024 Not Ready for Inspection JEFFREY FULTON
Light Gage Steel Frame 7/15/2024 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 7/15/2024 Not Ready for Inspection JEFFREY FULTON
Insulation 7/18/2024 Partial Approval DAVID BURKHEAD
Insulation 7/22/2024 Partial Inspection JEFFREY FULTON
Wood Frame 7/22/2024 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 7/24/2024 Partial Inspection JEFFREY FULTON
Green Building Rough 7/26/2024 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 7/26/2024 Not Ready for Inspection JEFFREY FULTON
Wood Frame 7/26/2024 Corrections Issued JEFFREY FULTON
Insulation 8/2/2024 Partial Inspection JEFFREY FULTON
Insulation 8/12/2024 Partial Approval RAMAZANALI ALMASI
Interior/Exterior Lathing 8/19/2024 Partial Approval LARRY ARNICK
Interior/Exterior Lathing 8/20/2024 Corrections Issued LARRY ARNICK
Insulation 8/21/2024 Not Ready for Inspection JEFFREY FULTON
Insulation 8/23/2024 Partial Approval LARRY ARNICK
Green Building Rough 8/26/2024 Not Ready for Inspection JEFFREY FULTON
Insulation 8/26/2024 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 8/26/2024 Not Ready for Inspection JEFFREY FULTON
Wood Frame 8/26/2024 Partial Inspection JEFFREY FULTON
Insulation 8/27/2024 Partial Inspection JEFFREY FULTON
Wood Frame 8/27/2024 Partial Inspection JEFFREY FULTON
Green Building Rough 8/29/2024 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 8/29/2024 Not Ready for Inspection JEFFREY FULTON
Wood Frame 8/29/2024 Partial Inspection JEFFREY FULTON
Insulation 8/30/2024 Partial Inspection JEFFREY FULTON
Green Building Rough 9/3/2024 Not Ready for Inspection JEFFREY FULTON
Insulation 9/3/2024 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 9/3/2024 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 9/4/2024 Partial Inspection JEFFREY FULTON
Wood Frame 9/4/2024 Partial Inspection JEFFREY FULTON
Green Building Rough 9/6/2024 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 9/6/2024 Partial Approval DAVID BURKHEAD
Wood Frame 9/6/2024 Partial Approval DAVID BURKHEAD
Drywall Nailing 9/9/2024 Partial Approval EDWIN GREGORYONA
Green Building Rough 9/11/2024 Not Ready for Inspection JEFFREY FULTON
Insulation 9/11/2024 Partial Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 9/11/2024 Not Ready for Inspection JEFFREY FULTON
Wood Frame 9/11/2024 Partial Inspection JEFFREY FULTON
Insulation 9/12/2024 Partial Inspection JEFFREY FULTON
Insulation 9/17/2024 Not Ready for Inspection JEFFREY FULTON
Insulation 9/18/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 9/20/2024 Partial Inspection JEFFREY FULTON
Green Building Rough 9/20/2024 Approved JEFFREY FULTON
Drywall Nailing 9/26/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 10/1/2024 Partial Inspection JEFFREY FULTON
Insulation 10/1/2024 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 10/1/2024 Partial Inspection JEFFREY FULTON
Drywall Nailing 10/30/2024 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 1/10/2025 Partial Inspection JEFFREY FULTON
Masonry Wall/Backfill 1/10/2025 Partial Inspection JEFFREY FULTON
Special/Order Compliance 4/2/2025 Not Ready for Inspection DAVID BURKHEAD
Special/Order Compliance 4/7/2025 Partial Inspection JEFFREY FULTON
Special/Order Compliance 10/29/2025 Partial Inspection JEFFREY FULTON
Drywall Nailing 12/29/2025 Not Ready for Inspection JEFFREY FULTON
Final 12/29/2025 Partial Inspection JEFFREY FULTON
Footing/Foundation/Slab 12/29/2025 Not Ready for Inspection JEFFREY FULTON
Green Building Final 12/29/2025 Not Ready for Inspection JEFFREY FULTON
Reinforced Concrete Frame 12/29/2025 Not Ready for Inspection JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 12/29/2025 SGSOV Not Ready JEFFREY FULTON
Smoke Detectors 12/29/2025 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 12/29/2025 Not Ready for Inspection JEFFREY FULTON
Wood Frame 12/29/2025 Not Ready for Inspection JEFFREY FULTON
Final 1/5/2026 Partial Inspection JEFFREY FULTON
Pre-Inspection 1/8/2026 Not Ready for Inspection JEFFREY FULTON
Special/Order Compliance 1/8/2026 Not Ready for Inspection JEFFREY FULTON
Final 1/9/2026 Not Ready for Inspection JEFFREY FULTON
Drywall Nailing 3/6/2026 Approved DAVID BURKHEAD
Final 3/6/2026 Partial Inspection DAVID BURKHEAD
Footing/Foundation/Slab 3/6/2026 Approved DAVID BURKHEAD
Green Building Final 3/6/2026 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 3/6/2026 Conditional Approval DAVID BURKHEAD
SGSOV-Seismic Gas S/O Valve 3/6/2026 SGSOV Approved DAVID BURKHEAD
Smoke Detectors 3/6/2026 Approved DAVID BURKHEAD
Verify Sprinkler Sign Off 3/6/2026 Approved DAVID BURKHEAD
Wood Frame 3/6/2026 Conditional Approval DAVID BURKHEAD
Final 3/13/2026 Partial Approval DAVID BURKHEAD
Green Building Final 3/13/2026 Approved DAVID BURKHEAD
Reinforced Concrete Frame 3/13/2026 Approved DAVID BURKHEAD
Wood Frame 3/13/2026 Approved DAVID BURKHEAD
Final 5/12/2026 OK to Issue CofO DAVID BURKHEAD