1164 W 37TH PL 90007

Certificate Information: 1164 W 37TH PL 90007

Application / Permit
19010-10000-05848
Plan Check / Job No.
B19LA26802
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 3-STORY WITH ROOFTOP DECK 6-UNIT APARTMENT BUILDING PER TOC TIER 4. TYPE V-A CONSTRUCTION AND FULLY SPRINKLERED NFPA 13.
Permit Issued
Issued on 2/22/2021
Issuing Office
Current Status
CofO Issued on 12/17/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/19/2019 APPLICANT
Assigned to Plan Check Engineer 1/9/2020 EMMANUEL MARTINEZ
Corrections Issued 1/13/2020 EMMANUEL MARTINEZ
Quality Review Completed 1/23/2020 ARMEN JIVALAGIAN
Disabled Access Plans Picked Up 1/28/2020 APPLICANT
Building Plans Picked Up 1/31/2020 APPLICANT
Applicant returned to address corrections 10/22/2020 SAM CHANG
Applicant returned to address corrections 11/4/2020 SAM CHANG
Green Plans Picked Up 12/8/2020 APPLICANT
Applicant returned to address corrections 1/5/2021 SAM CHANG
Applicant returned to address corrections 1/26/2021 SAM CHANG
Applicant returned to address corrections 2/5/2021 SAM CHANG
Plan Check Approved 2/16/2021 SAM CHANG
Issued 2/22/2021 APPLICANT
CofO in Progress 12/14/2021 JAMES POWERS
CofO Issued 12/17/2021 ERNESTO CORRAL
Permit Finaled 12/17/2021 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 2/26/2020 CELINA MORENO
Highway dedication Cleared 2/26/2020 CELINA MORENO
Permit Cleared 2/26/2020 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 3/10/2020 CECILIO NAVARRO
Sewer availability Cleared 3/10/2020 CECILIO NAVARRO
Community Plan Implem. Overlay Cleared 3/16/2020 OSCAR CASTRO
Community Plan Implem. Overlay Cleared 5/20/2020 SAM NAVID
Community Plan Implem. Overlay Cleared 6/2/2020 MOHAMMAD HASAN
Density Bonus 12.22.A.31 Cleared 6/12/2020 DORIS KWOK
Low Impact Development Cleared 7/6/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 7/13/2020 CELINA MORENO
Trees in Parkway Cleared 7/21/2020 JOHN KIM
Community Plan Implem. Overlay Cleared 7/28/2020 ADRIAN SANCHEZ
Frnt yard landscape/Water mgmt Cleared 8/5/2020 JOE LUCKEY
Hydrant and Access approval Cleared 9/9/2020 MATTHEW CRAIG
Green Code Cleared 9/29/2020 KHEDER ALRAZAA
ZI Cleared 9/30/2020 RAFAEL FONTES
DAS Clearance Cleared 10/1/2020 EMMANUEL MARTINEZ
Fire Marshall Fire Life Safety Cleared 11/16/2020 OSCAR SALGADO JR
Community Plan Implem. Overlay Cleared 12/30/2020 RAFAEL FONTES

Contact Information

Architect Holtz,, Donald Lee; Lic. No.: C21677 2404 WILSHIRE BLVD SUITE 6F      LOS ANGELES, CA 90057
Contractor Owner-Builder       ,
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065
Engineer Tuchscher,, James Todd; Lic. No.: C77649 5503 E 2ND ST      LONG BEACH, CA 90803
Geologist Siskowic,, John Gary; Lic. No.: GEO8255 515 S CATALINA AVE APT A      REDONDO BEACH, CA 90277
Landscape Architect Jones,, Anne Ermatinger; Lic. No.: LA5999 2735 W AVE 33      LOS ANGELES, CA 90065

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/23/2021 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 3/23/2021 Not Ready for Inspection JAMES POWERS
METHANE-Barrier 3/23/2021 Approved JAMES POWERS
METHANE-Subgrade 3/23/2021 Approved JAMES POWERS
Footing/Foundation/Slab 4/1/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 4/6/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 4/16/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 4/26/2021 Corrections Issued NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 4/27/2021 Partial Approval JOEY BUCHANAN
Deputy Wood Construction 5/13/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 5/13/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 5/21/2021 Approved JOEY BUCHANAN
Deputy Wood Construction 5/27/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 6/4/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 6/8/2021 Partial Approval JAMES POWERS
Green Building Rough 6/8/2021 Approved JAMES POWERS
METHANE-Rough 6/8/2021 Approved JAMES POWERS
Verify Sprinkler Sign Off 6/8/2021 Not Ready for Inspection JAMES POWERS
Insulation 6/22/2021 Approved JAMES POWERS
Interior/Exterior Lathing 6/25/2021 Partial Approval LEOPOLDO MENDOZA
Drywall Nailing 7/20/2021 Approved JAMES POWERS
Final 11/24/2021 Not Ready for Inspection JONATHAN QUACH
Footing/Foundation/Slab 11/24/2021 Not Ready for Inspection JONATHAN QUACH
Green Building Final 11/24/2021 Not Ready for Inspection JONATHAN QUACH
SGSOV-Seismic Gas S/O Valve 11/24/2021 SGSOV Not Ready JONATHAN QUACH
Smoke Detectors 11/24/2021 Not Ready for Inspection JONATHAN QUACH
Verify Sprinkler Sign Off 11/24/2021 Not Ready for Inspection JONATHAN QUACH
Wood Frame 11/24/2021 Not Ready for Inspection JONATHAN QUACH
Final 12/2/2021 OK for TCO JAMES POWERS
Footing/Foundation/Slab 12/2/2021 Approved JAMES POWERS
Green Building Final 12/2/2021 Approved JAMES POWERS
SGSOV-Seismic Gas S/O Valve 12/2/2021 SGSOV Approved JAMES POWERS
Smoke Detectors 12/2/2021 Approved JAMES POWERS
Verify Sprinkler Sign Off 12/2/2021 Approved JAMES POWERS
Wood Frame 12/2/2021 Approved JAMES POWERS
Final 12/13/2021 OK to Issue CofO JAMES POWERS