537 E GRAND BLVD 90291
Certificate Information: 537 E GRAND BLVD 90291
- Application / Permit
- 19010-10000-05809
- Plan Check / Job No.
- B19LA26700
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1 ) NEW 3-STORY SINGLE FAMILY RESIDENCE 1 OF 3
- Permit Issued
- Issued on 10/5/2020
- Issuing Office
- Current Status
- CofO Issued on 1/17/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/18/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/2/2020 | ARSALAN SHABESTARI |
| Green Plans Picked Up | 1/3/2020 | APPLICANT |
| Corrections Issued | 1/7/2020 | ARSALAN SHABESTARI |
| Quality Review Completed | 1/11/2020 | YOUNG KIM |
| Applicant returned to address corrections | 8/17/2020 | ARSALAN SHABESTARI |
| Plan Check Approved | 9/10/2020 | ARSALAN SHABESTARI |
| Issued | 10/5/2020 | APPLICANT |
| Building Plans Picked Up | 10/9/2020 | APPLICANT |
| CofO in Progress | 1/9/2023 | EVAN COOPER |
| Permit Finaled | 1/17/2023 | DANIEL ORRANTE |
| CofO Issued | 1/17/2023 | DANIEL ORRANTE |
| Permit Finaled | 1/17/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Green Code | Cleared | 2/10/2020 | VIVIAN LAO |
| Address approval | Cleared | 2/13/2020 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 2/13/2020 | CELINA MORENO |
| Permit | Cleared | 2/13/2020 | CELINA MORENO |
| Sewer availability | Cleared | 2/13/2020 | CELINA MORENO |
| Low Impact Development | Cleared | 5/29/2020 | SARAH YOUSSEF |
| Coastal Zone | Cleared | 8/3/2020 | RICHARD REASER |
| Coastal Zone | Cleared | 8/3/2020 | RICHARD REASER |
| Miscellaneous | Cleared | 8/3/2020 | RICHARD REASER |
| Miscellaneous | Cleared | 8/3/2020 | RICHARD REASER |
| Miscellaneous | Cleared | 8/3/2020 | RICHARD REASER |
| ZI | Cleared | 8/3/2020 | RICHARD REASER |
| ZI | Cleared | 8/3/2020 | RICHARD REASER |
| Hydrant and Access approval | Cleared | 8/10/2020 | JOHN CONNEALLY |
| Miscellaneous | Cleared | 8/10/2020 | RICHARD REASER |
| Miscellaneous | Cleared | 8/10/2020 | RICHARD REASER |
| Roof/Waste drainage to street | Cleared | 8/20/2020 | HISASHI KOBAYAKAWA |
| Specific Plan | Cleared | 8/24/2020 | VALERIA CEJA |
| Miscellaneous | Cleared | 9/2/2020 | RICHARD REASER |
| Miscellaneous | Cleared | 9/2/2020 | RICHARD REASER |
| Specific Plan | Cleared | 9/2/2020 | RICHARD REASER |
Contact Information
| Contractor | Taylor Made Homes Inc; Lic. No.: 818492-B | 825 WILSHIRE BLVD #128 SANTA MONICA, CA 90401 |
| Engineer | Pirbadian,, Amir; Lic. No.: C72413 | 5435 BALBOA BLVD 214 ENCINO, CA 91342 |
| Geologist | Schick,, John Wayne; Lic. No.: EG1300 | 7650 HASKELL AVENUE STE D VAN NUYS, CA 91406 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/7/2020 | Not Ready for Inspection | DAVID HEINE |
| METHANE-Subgrade | 10/7/2020 | Approved | DAVID HEINE |
| Underground Mechanical | 10/7/2020 | Approved | DAVID HEINE |
| Footing/Foundation/Slab | 10/30/2020 | Partial Approval | DAVID HEINE |
| METHANE-Barrier | 10/30/2020 | Approved | DAVID HEINE |
| METHANE-Final | 10/30/2020 | Not Ready for Inspection | DAVID HEINE |
| Underground Mechanical | 10/30/2020 | Partial Approval | DAVID HEINE |
| Footing/Foundation/Slab | 11/5/2020 | Partial Approval | DAVID HEINE |
| Underground Mechanical | 11/5/2020 | Partial Approval | DAVID HEINE |
| ELECTRICAL-Rough | 12/3/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| Reinforced Concrete Frame | 12/3/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| ELECTRICAL-Rough | 12/7/2020 | Partial Inspection | JUAN VALENZUELA |
| Reinforced Concrete Frame | 12/7/2020 | Partial Approval | JUAN VALENZUELA |
| Sewer | 1/12/2021 | Approved | JUAN VALENZUELA |
| Underground Mechanical | 1/12/2021 | Partial Inspection | JUAN VALENZUELA |
| Reinforced Concrete Frame | 2/24/2021 | Corrections Issued | JOHNNY MIRANDA |
| Underground Mechanical | 2/24/2021 | Corrections Issued | JOHNNY MIRANDA |
| Reinforced Concrete Frame | 2/25/2021 | Corrections Issued | JOHNNY MIRANDA |
| Underground Mechanical | 2/25/2021 | Partial Approval | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 2/26/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Reinforced Concrete Frame | 2/26/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Reinforced Masonry Frame | 2/26/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Underground Mechanical | 2/26/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Reinforced Concrete Frame | 3/2/2021 | Partial Approval | JOHNNY MIRANDA |
| Deputy Reinf. Concrete | 3/3/2021 | Conditional Approval | JOHNNY MIRANDA |
| Reinforced Concrete Frame | 3/18/2021 | Partial Approval | JOHNNY MIRANDA |
| Underground Mechanical | 3/18/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 3/25/2021 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2021 | Corrections Issued | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2021 | Partial Approval | KENNETH NAGLE |
| Reinforced Concrete Frame | 4/21/2021 | Partial Approval | KENNETH NAGLE |
| Wood Frame | 4/21/2021 | Partial Approval | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 6/7/2021 | Partial Approval | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 7/16/2021 | Corrections Issued | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 8/2/2021 | Conditional Approval | BRENDAN LOONEY |
| HVAC-Rough | 8/2/2021 | Conditional Approval | BRENDAN LOONEY |
| METHANE-Rough | 8/2/2021 | Approved | BRENDAN LOONEY |
| PLUMBING-Rough | 8/2/2021 | Corrections Issued | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 8/17/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 8/17/2021 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 8/17/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| HVAC-Rough | 8/17/2021 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 8/17/2021 | Approved | JOHNNY MIRANDA |
| Verify Sprinkler Sign Off | 8/17/2021 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 9/17/2021 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 9/17/2021 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 9/17/2021 | Partial Approval | JOHNNY MIRANDA |
| Insulation | 9/20/2021 | Approved | JOHNNY MIRANDA |
| Shower Pan | 9/30/2021 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 11/19/2021 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 11/19/2021 | Approved | DAVID FEILER |
| ELECTRICAL-Final | 5/10/2022 | Corrections Issued | DAVID FEILER |
| Gas Test | 5/10/2022 | Approved | DAVID FEILER |
| Special/Order Compliance | 6/6/2022 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 6/30/2022 | Partial Approval | DAVID FEILER |
| PLUMBING-Final | 6/30/2022 | Corrections Issued | DAVID FEILER |
| ELECTRICAL-Final | 7/12/2022 | Approved | DAVID FEILER |
| PLUMBING-Final | 7/12/2022 | Not Ready for Inspection | DAVID FEILER |
| Final | 7/21/2022 | Not Ready for Inspection | DAVID FEILER |
| Footing/Foundation/Slab | 7/21/2022 | Approved | DAVID FEILER |
| Green Building Final | 7/21/2022 | Corrections Issued | DAVID FEILER |
| PLUMBING-Final | 7/21/2022 | Approved | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 7/21/2022 | SGSOV Not Ready | DAVID FEILER |
| Service/Power Release | 7/21/2022 | Not Ready for Inspection | DAVID FEILER |
| Smoke Detectors | 7/21/2022 | Corrections Issued | DAVID FEILER |
| Service/Power Release | 7/28/2022 | Approved | DAVID FEILER |
| Final | 1/9/2023 | OK to Issue CofO | EVAN COOPER |
| Green Building Final | 1/9/2023 | Approved | EVAN COOPER |
| HVAC-Final | 1/9/2023 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 1/9/2023 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 1/9/2023 | Approved | EVAN COOPER |