2026 S FEDERAL AVE 90025
Certificate Information: 2026 S FEDERAL AVE 90025
- Application / Permit
- 19010-10000-05794
- Plan Check / Job No.
- B19LA26664
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 3 STORY SINGLE FAMILY DWELLING UNIT (FRONT UNIT) NFPA13D THUR-OUT
- Permit Issued
- Issued on 11/2/2020
- Issuing Office
- Current Status
- CofO Issued on 1/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/18/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2019 | AUNG SOE |
| Corrections Issued | 1/2/2020 | AUNG SOE |
| Quality Review Completed | 1/8/2020 | TIEN JEN WANG |
| Applicant returned to address corrections | 2/4/2020 | AUNG SOE |
| Green Plans Picked Up | 8/17/2020 | APPLICANT |
| Plan Check Approved | 9/11/2020 | AUNG SOE |
| Issued | 11/2/2020 | APPLICANT |
| Building Plans Picked Up | 11/9/2020 | APPLICANT |
| CofO in Progress | 1/2/2024 | MICHAEL PELHAM |
| Permit Finaled | 1/5/2024 | DANIEL ORRANTE |
| CofO Issued | 1/5/2024 | DANIEL ORRANTE |
| Permit Finaled | 1/5/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/13/2020 | ERIK BEASLEY |
| Specific Plan | Cleared | 1/13/2020 | COLLINS ALLAN |
| Specific Plan | Cleared | 1/13/2020 | RICHARD REASER |
| Specific Plan | Cleared | 1/13/2020 | SARAHI ORTEGA |
| Tenant Habitability Plan | Cleared | 1/13/2020 | MICHAEL SOTO |
| ZA Case | Cleared | 1/13/2020 | RICHARD REASER |
| Low Impact Development | Cleared | 7/17/2020 | ROBIN YAMADA |
| Address approval | Cleared | 7/20/2020 | ERIK BEASLEY |
| Hydrant and Access approval | Cleared | 7/20/2020 | KURT CORRAL |
| Roof/Waste drainage to street | Cleared | 7/20/2020 | ERIK BEASLEY |
| Sewer availability | Cleared | 7/20/2020 | ERIK BEASLEY |
| Green Code | Cleared | 8/14/2020 | VIVIAN LAO |
Contact Information
| Architect | Dong, Woo Kim; Lic. No.: C37061 | 818 S BROADWAY LOS ANGELES, CA 90014 |
| Contractor | G L Construction Group Inc; Lic. No.: 994049-B | 324 S DIAMOND BAR BLVD STE 367 DIAMOND BAR, CA 91765 |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
| Engineer | Kim,, Hong Kook; Lic. No.: C64529 | 839 S MUIRFIELD RD LOS ANGELES, CA 90005 |
| Engineer | Kim,, Hosang; Lic. No.: C67288 | 10632 BALCOM AVE GRANADA HILLS, CA 91344 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 4/6/2022 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 4/6/2022 | Approved | OGANES TARAKHCHYAN |
| Verify Sprinkler Sign Off | 4/6/2022 | Approved | OGANES TARAKHCHYAN |
| Insulation | 4/29/2022 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 5/12/2022 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 5/19/2022 | Approved | BRENDAN LOONEY |
| ELECTRICAL-Final | 1/12/2023 | Corrections Issued | ASHLEY THOMPSON |
| ELECTRICAL-Final | 1/17/2023 | Approved | CLAYTON GRAHAM |
| PLUMBING-Final | 1/30/2023 | Not Ready for Inspection | JULIAN AMAYA |
| PLUMBING-Final | 2/13/2023 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Final | 2/17/2023 | Approved | STEPHANIE SWANSON |
| Service/Power Release | 3/6/2023 | Approved | CLAYTON GRAHAM |
| Final | 5/12/2023 | Corrections Issued | EVAN COOPER |
| HVAC-Final | 5/12/2023 | Approved | EVAN COOPER |
| Final | 5/16/2023 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 5/16/2023 | Approved | HERBERT GIRON |
| Green Building Final | 5/16/2023 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 5/16/2023 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 5/16/2023 | Approved | HERBERT GIRON |
| Final | 5/19/2023 | Corrections Issued | MICHAEL PELHAM |
| Final | 12/29/2023 | Conditional Approval | MICHAEL PELHAM |