Pre-Inspection
|
5/28/2024
|
Not Ready for Inspection
|
SEAN HAUPT
|
|
Deputy Grading
|
9/24/2024
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Grading
|
9/25/2024
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Grading
|
9/26/2024
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Grading
|
9/27/2024
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Grading
|
9/30/2024
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Grading
|
10/1/2024
|
Partial Approval
|
SEAN HAUPT
|
|
Piling/Pier/Caisson
|
10/1/2024
|
Corrections Issued
|
SEAN HAUPT
|
|
Deputy Grading
|
10/2/2024
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Reinf. Concrete
|
10/2/2024
|
Partial Approval
|
SEAN HAUPT
|
|
Piling/Pier/Caisson
|
10/2/2024
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Grading
|
10/3/2024
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Reinf. Concrete
|
10/3/2024
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Grading
|
10/4/2024
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Reinf. Concrete
|
10/4/2024
|
Partial Approval
|
SEAN HAUPT
|
|
Piling/Pier/Caisson
|
10/4/2024
|
Corrections Issued
|
SEAN HAUPT
|
|
Deputy Reinf. Concrete
|
10/7/2024
|
Approved
|
SEAN HAUPT
|
|
Piling/Pier/Caisson
|
10/7/2024
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Reinf. Concrete
|
10/8/2024
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Grading
|
10/9/2024
|
Approved
|
SEAN HAUPT
|
|
Deputy Reinf. Concrete
|
10/9/2024
|
Approved
|
SEAN HAUPT
|
|
Piling/Pier/Caisson
|
10/9/2024
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Reinf. Concrete
|
10/10/2024
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Grading
|
10/11/2024
|
Conditional Approval
|
CARLOS MATAMOROS
|
|
Deputy Reinf. Concrete
|
10/11/2024
|
Conditional Approval
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
10/11/2024
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Piling/Pier/Caisson
|
10/11/2024
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Footing/Foundation/Slab
|
10/15/2024
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Grading
|
10/16/2024
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Grading
|
10/17/2024
|
Partial Approval
|
SEAN HAUPT
|
|
Excavation/Setback/Form/Re-Bar
|
10/17/2024
|
Off-Hour Fees Due
|
|
|
Piling/Pier/Caisson
|
10/17/2024
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Grading
|
10/18/2024
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Grading
|
10/21/2024
|
Approved
|
SEAN HAUPT
|
|
Piling/Pier/Caisson
|
10/21/2024
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Grading
|
10/22/2024
|
Approved
|
SEAN HAUPT
|
|
Deputy Grading
|
10/22/2024
|
Partial Approval
|
SEAN HAUPT
|
|
Piling/Pier/Caisson
|
10/22/2024
|
Partial Approval
|
SEAN HAUPT
|
|
Piling/Pier/Caisson
|
10/23/2024
|
Not Ready for Inspection
|
SEAN HAUPT
|
|
Piling/Pier/Caisson
|
10/23/2024
|
Partial Approval
|
SEAN HAUPT
|
|
Piling/Pier/Caisson
|
10/24/2024
|
Partial Approval
|
DANIEL VERA
|
|
Piling/Pier/Caisson
|
10/25/2024
|
Off-Hour Fees Due
|
|
|
Piling/Pier/Caisson
|
10/25/2024
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Grading
|
10/28/2024
|
Approved
|
SEAN HAUPT
|
|
Deputy Reinf. Concrete
|
10/28/2024
|
Approved
|
SEAN HAUPT
|
|
Piling/Pier/Caisson
|
10/28/2024
|
Partial Approval
|
SEAN HAUPT
|
|
Piling/Pier/Caisson
|
10/29/2024
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Reinf. Concrete
|
10/30/2024
|
Partial Approval
|
SEAN HAUPT
|
|
Piling/Pier/Caisson
|
10/31/2024
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Reinf. Concrete
|
11/1/2024
|
Approved
|
SEAN HAUPT
|
|
Piling/Pier/Caisson
|
11/1/2024
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Reinf. Concrete
|
12/27/2024
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Reinf. Concrete
|
12/30/2024
|
Approved
|
SEAN HAUPT
|
|
Piling/Pier/Caisson
|
1/23/2025
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Reinf. Concrete
|
1/24/2025
|
Conditional Approval
|
TEMISTOCLES CAAL
|
|
Piling/Pier/Caisson
|
1/24/2025
|
Not Ready for Inspection
|
TEMISTOCLES CAAL
|
|
Deputy Reinf. Concrete
|
1/28/2025
|
Partial Approval
|
SEAN HAUPT
|
|
Piling/Pier/Caisson
|
1/28/2025
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Reinf. Concrete
|
1/29/2025
|
Approved
|
SEAN HAUPT
|
|
Piling/Pier/Caisson
|
1/29/2025
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Reinf. Concrete
|
1/30/2025
|
Partial Approval
|
SEAN HAUPT
|
|
Piling/Pier/Caisson
|
2/10/2025
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Reinf. Concrete
|
2/11/2025
|
Partial Approval
|
SEAN HAUPT
|
|
Piling/Pier/Caisson
|
2/11/2025
|
Not Ready for Inspection
|
SEAN HAUPT
|
|
Piling/Pier/Caisson
|
2/12/2025
|
Corrections Issued
|
SEAN HAUPT
|
|
Piling/Pier/Caisson
|
2/13/2025
|
Partial Approval
|
DANIEL VERA
|
|
Deputy Grading
|
2/14/2025
|
Partial Approval
|
SEAN HAUPT
|
|
Piling/Pier/Caisson
|
2/20/2025
|
Partial Approval
|
DANIEL VERA
|
|
Deputy Reinf. Concrete
|
2/25/2025
|
Partial Approval
|
SEAN HAUPT
|
|
Piling/Pier/Caisson
|
2/26/2025
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Drilled-In Anchors
|
3/3/2025
|
Partial Approval
|
SEAN HAUPT
|
|
Piling/Pier/Caisson
|
3/4/2025
|
Approved
|
SEAN HAUPT
|
|
Piling/Pier/Caisson
|
3/7/2025
|
Partial Approval
|
SEAN HAUPT
|
|
Piling/Pier/Caisson
|
3/14/2025
|
Approved
|
SEAN HAUPT
|
|
Piling/Pier/Caisson
|
3/21/2025
|
Partial Approval
|
DANIEL VERA
|
|
Piling/Pier/Caisson
|
3/31/2025
|
Off-Hour Fees Due
|
|
|
Piling/Pier/Caisson
|
4/1/2025
|
Partial Approval
|
SEAN HAUPT
|
|
Footing/Foundation/Slab
|
4/9/2025
|
Corrections Issued
|
SEAN HAUPT
|
|
Piling/Pier/Caisson
|
4/9/2025
|
Partial Approval
|
SEAN HAUPT
|
|
Excavation/Setback/Form/Re-Bar
|
7/8/2025
|
Corrections Issued
|
SEAN HAUPT
|
|
Deputy Grading
|
7/10/2025
|
Approved
|
SEAN HAUPT
|
|
Deputy Other (see comments)
|
7/10/2025
|
Approved
|
SEAN HAUPT
|
|
Excavation/Setback/Form/Re-Bar
|
7/10/2025
|
Corrections Issued
|
SEAN HAUPT
|
|
Deputy Grading
|
7/11/2025
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Grading
|
7/14/2025
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Deputy Grading
|
7/15/2025
|
Partial Approval
|
SEAN HAUPT
|
|
Excavation/Setback/Form/Re-Bar
|
7/18/2025
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Reinf. Concrete
|
7/25/2025
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Reinf. Concrete
|
7/28/2025
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Reinf. Concrete
|
7/30/2025
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Reinf. Concrete
|
7/31/2025
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Reinf. Concrete
|
8/6/2025
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Reinf. Concrete
|
8/7/2025
|
Approved
|
SEAN HAUPT
|
|
Piling/Pier/Caisson
|
8/7/2025
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Reinf. Concrete
|
8/8/2025
|
Partial Approval
|
SEAN HAUPT
|
|
Piling/Pier/Caisson
|
8/8/2025
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
8/18/2025
|
Partial Approval
|
SEAN HAUPT
|
|
Piling/Pier/Caisson
|
8/18/2025
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Reinf. Concrete
|
8/19/2025
|
Approved
|
SEAN HAUPT
|
|
Piling/Pier/Caisson
|
8/19/2025
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Reinf. Concrete
|
8/25/2025
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Reinf. Concrete
|
9/3/2025
|
Partial Approval
|
SEAN HAUPT
|
|
Excavation/Setback/Form/Re-Bar
|
9/3/2025
|
Partial Approval
|
SEAN HAUPT
|
|
Piling/Pier/Caisson
|
9/3/2025
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Reinf. Concrete
|
9/4/2025
|
Approved
|
SEAN HAUPT
|
|
HVAC-Rough
|
9/4/2025
|
Not Ready for Inspection
|
SEAN HAUPT
|
|
Piling/Pier/Caisson
|
9/4/2025
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Shotcrete
|
9/8/2025
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Shotcrete
|
9/9/2025
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Shotcrete
|
9/10/2025
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Excavation/Setback/Form/Re-Bar
|
9/12/2025
|
Not Ready for Inspection
|
SEAN HAUPT
|
|
Footing/Foundation/Slab
|
9/12/2025
|
Not Ready for Inspection
|
SEAN HAUPT
|
|
Pre-Inspection
|
9/12/2025
|
Not Ready for Inspection
|
SEAN HAUPT
|
|
Excavation/Setback/Form/Re-Bar
|
9/16/2025
|
Not Ready for Inspection
|
SEAN HAUPT
|
|
Excavation/Setback/Form/Re-Bar
|
9/19/2025
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Shotcrete
|
9/22/2025
|
Partial Approval
|
SEAN HAUPT
|
|
Footing/Foundation/Slab
|
10/1/2025
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Reinf. Concrete
|
10/2/2025
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Grading
|
10/24/2025
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Grading
|
10/27/2025
|
Partial Approval
|
SEAN HAUPT
|
|
Footing/Foundation/Slab
|
11/12/2025
|
Partial Approval
|
SEAN HAUPT
|
|
Piling/Pier/Caisson
|
11/12/2025
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Shotcrete
|
12/5/2025
|
Partial Approval
|
SEAN HAUPT
|
|
Deputy Shotcrete
|
12/9/2025
|
Partial Approval
|
SEAN HAUPT
|
|
Excavation/Setback/Form/Re-Bar
|
12/9/2025
|
Partial Approval
|
SEAN HAUPT
|
|
PLUMBING-Rough
|
12/18/2025
|
Partial Approval
|
CARLOS MATAMOROS
|
|
PLUMBING-Rough
|
12/19/2025
|
Corrections Issued
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
12/29/2025
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Special/Order Compliance
|
12/29/2025
|
Approved
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
1/21/2026
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Footing/Foundation/Slab
|
1/21/2026
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Deputy Reinf. Concrete
|
1/29/2026
|
Approved
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
1/29/2026
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
2/6/2026
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
3/10/2026
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
3/24/2026
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Deputy Reinf. Concrete
|
3/25/2026
|
Conditional Approval
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
3/31/2026
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Deputy Other (see comments)
|
4/1/2026
|
Conditional Approval
|
ANDREW NAVE
|
|
Excavation/Setback/Form/Re-Bar
|
4/8/2026
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Footing/Foundation/Slab
|
4/8/2026
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Deputy Reinf. Concrete
|
4/24/2026
|
Conditional Approval
|
ANDREW NAVE
|
|
Deputy Shotcrete
|
4/24/2026
|
Conditional Approval
|
ANDREW NAVE
|
|
Underground Mechanical
|
5/13/2026
|
Partial Approval
|
CARLOS MATAMOROS
|
|
ELECTRICAL-Rough
|
5/14/2026
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Deputy Reinf. Concrete
|
5/19/2026
|
Conditional Approval
|
ANDREW NAVE
|
|
Deputy Reinf. Concrete
|
5/20/2026
|
Conditional Approval
|
ANDREW NAVE
|
|
ELECTRICAL-Rough
|
5/22/2026
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
5/22/2026
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
6/2/2026
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
6/9/2026
|
Partial Approval
|
CARLOS MATAMOROS
|