6621 N VESPER AVE 91405

Certificate Information: 6621 N VESPER AVE 91405

Application / Permit
19010-10000-05722
Plan Check / Job No.
B19LA26454
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 1-STORY ACCESSSORY DWELLING UNIT PER AB494 AND SB229. NFPA13D FIRE SPRINKLERS REQUIRED.
Permit Issued
Issued on 10/2/2020
Issuing Office
Current Status
CofO Issued on 5/4/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/16/2019 APPLICANT
Assigned to Plan Check Engineer 12/20/2019 KEVIN MORALES
Corrections Issued 12/31/2019 KEVIN MORALES
Plan Check Approved 10/2/2020 KEVIN MORALES
Issued 10/2/2020 APPLICANT
CofO in Progress 4/14/2022 RICHARD DOCKUS
No Progress 4/15/2022 MICHAEL TEMPLE
CofO in Progress 4/23/2022 MICHAEL TEMPLE
CofO in Progress 5/3/2022 RICHARD DOCKUS
Permit Finaled 5/4/2022 RONALD MYRICK
CofO Issued 5/4/2022 RONALD MYRICK
Permit Finaled 5/4/2022 RONALD MYRICK

Permit Application Clearance Information

City Hist. Cultural Monument Cleared 5/15/2020 SUKI GERSHENHORN
HPOZ Cleared 5/15/2020 SUKI GERSHENHORN
Historic monument Cleared 5/15/2020 SUKI GERSHENHORN
Address approval Cleared 6/9/2020 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 6/9/2020 LEE GUILBEAUX
Sewer availability Cleared 6/9/2020 LEE GUILBEAUX
Hydrant and Access approval Cleared 7/7/2020 KURT CORRAL
Low Impact Development Cleared 8/25/2020 ROBIN YAMADA
Roof/Waste drainage to street Cleared 9/28/2020 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 9/28/2020 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/28/2021 Approved JENNIFER RABUCHIN
PLUMBING-Rough 4/28/2021 Partial Approval JENNIFER RABUCHIN
Sewer 4/28/2021 Approved JENNIFER RABUCHIN
Underground Mechanical 4/28/2021 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 6/1/2021 Corrections Issued JENNIFER RABUCHIN
Gas Test 6/1/2021 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 6/8/2021 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 6/8/2021 Approved JENNIFER RABUCHIN
Gas Test 6/8/2021 Partial Approval JENNIFER RABUCHIN
HVAC-Rough 6/8/2021 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 6/8/2021 Approved JENNIFER RABUCHIN
Shower Pan 6/8/2021 Approved JENNIFER RABUCHIN
Wood Frame 6/8/2021 Corrections Issued JENNIFER RABUCHIN
Insulation 6/18/2021 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 6/18/2021 Approved JAVIER RAMOS JR
HVAC-Rough 6/22/2021 Approved ARTHUR SARGSYAN
Insulation 6/22/2021 Approved ARTHUR SARGSYAN
Drywall Nailing 10/8/2021 Approved RICHARD DOCKUS
Green Building Rough 10/8/2021 Approved RICHARD DOCKUS
Interior/Exterior Lathing 10/8/2021 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 4/1/2022 Conditional Approval RICHARD DOCKUS
ELECTRICAL-Final 4/1/2022 Corrections Issued RICHARD DOCKUS
Final 4/1/2022 Not Ready for Inspection RICHARD DOCKUS
Green Building Final 4/1/2022 Approved RICHARD DOCKUS
HVAC-Final 4/1/2022 Approved RICHARD DOCKUS
PLUMBING-Final 4/1/2022 Corrections Issued RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 4/1/2022 SGSOV Approved RICHARD DOCKUS
Service/Power Release 4/1/2022 Not Required RICHARD DOCKUS
Smoke Detectors 4/1/2022 Approved RICHARD DOCKUS
Verify Sprinkler Sign Off 4/1/2022 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 4/4/2022 Approved MICHAEL TEMPLE
Special/Order Compliance 4/4/2022 Approved MICHAEL TEMPLE
ELECTRICAL-Final 4/8/2022 Approved RICHARD DOCKUS
HVAC-Final 4/8/2022 Approved RICHARD DOCKUS
PLUMBING-Final 4/8/2022 Approved RICHARD DOCKUS
Final 4/13/2022 Partial Inspection RICHARD DOCKUS
Special/Order Compliance 4/15/2022 Corrections Issued RICHARD DOCKUS
Final 5/2/2022 OK to Issue CofO RICHARD DOCKUS