2338 W BAXTER ST 90039
Certificate Information: 2338 W BAXTER ST 90039
- Application / Permit
- 19010-10000-05717
- Plan Check / Job No.
- B19LA26444
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT PER SB-229 & AB-494. NFPA-13D FIRE SPRINKLER REQUIRED.
- Permit Issued
- Issued on 6/17/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/16/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/24/2019 | ERWIN PASCUA |
| Corrections Issued | 12/31/2019 | ERWIN PASCUA |
| Quality Review Completed | 12/31/2019 | CHARLES CHANG |
| Building Plans Picked Up | 12/31/2019 | APPLICANT |
| Green Plans Picked Up | 12/31/2019 | APPLICANT |
| Applicant returned to address corrections | 3/3/2020 | ERWIN PASCUA |
| Plan Check Approved | 4/6/2020 | ERWIN PASCUA |
| Issued | 6/17/2020 | LADBS |
| CofO in Progress | 6/1/2023 | STUART CHAPMAN |
| Permit Finaled | 6/27/2023 | DEROLD HAUFF |
| CofO Issued | 6/27/2023 | DEROLD HAUFF |
| Permit Finaled | 6/27/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/2/2020 | ERIK BEASLEY |
| BHO/Hillside ordinance | Cleared | 1/2/2020 | ERIK BEASLEY |
| BHO/Hillside ordinance | Cleared | 1/2/2020 | ERIK BEASLEY |
| BHO/Hillside ordinance | Cleared | 1/2/2020 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 1/2/2020 | ERIK BEASLEY |
| Sewer availability | Cleared | 1/2/2020 | ERIK BEASLEY |
| Hydrant and Access approval | Cleared | 1/3/2020 | JEREMY CARTER |
| Green Code | Cleared | 3/10/2020 | ERWIN PASCUA |
| Low Impact Development | Cleared | 3/16/2020 | ORVAL HERNANDEZ-MARCIAL |
| Roof/Waste drainage to street | Cleared | 3/16/2020 | HISASHI KOBAYAKAWA |
| Excavation more than 5-ft deep | Cleared | 4/6/2020 | CALOSHA APPROVED |
| Grading Pre-Inspection | Cleared | 4/6/2020 | ERWIN PASCUA |
Contact Information
| Architect | Ehrlich,, Steven David; Lic. No.: C10142 | 10865 WASHINGTON BLVD CULVER CITY, CA 90232 |
| Contractor | D T K Builders Inc; Lic. No.: 813974-B | 3035 N COOLIDGE AVE LOS ANGELES, CA 90039 |
| Engineer | Lau,, David Harkwong; Lic. No.: C34961 | 12467 W WASHINGTON BLVD LOS ANGELES, CA 90066 |
| Engineer | Liu,, Haiyan Harry; Lic. No.: C81463 | 29247 MARILYN DR SANTA CLARITA, CA 91387 |
| Geologist | Swiatek,, Mark A; Lic. No.: EG1781 | 24203 VALLEY ST NEWHALL, CA 91321 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 8/21/2020 | Approved | KATHRYN BUTTERWORTH |
| Deputy Reinf. Concrete | 8/24/2020 | Conditional Approval | THOMAS LOGRASSO |
| Piling/Pier/Caisson | 8/25/2020 | Approved | STUART CHAPMAN |
| Deputy Reinf. Concrete | 8/26/2020 | Conditional Approval | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 9/15/2020 | Partial Approval | HAMIK HARTOUNIAN |
| Deputy Reinf. Concrete | 9/16/2020 | No Access for Inspection | ELMER BLAND |
| Deputy Reinf. Masonry | 9/25/2020 | No Access for Inspection | ELMER BLAND |
| Deputy Reinf. Masonry | 10/2/2020 | No Access for Inspection | ELMER BLAND |
| Excavation/Setback/Form/Re-Bar | 10/6/2020 | Approved | ARTHUR SARGSYAN |
| Deputy Reinf. Masonry | 10/7/2020 | No Access for Inspection | ELMER BLAND |
| Deputy Reinf. Masonry | 10/16/2020 | No Access for Inspection | ELMER BLAND |
| Green Building Rough | 10/21/2020 | Not Ready for Inspection | STUART CHAPMAN |
| Reinforced Masonry Frame | 10/21/2020 | Partial Approval | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 10/21/2020 | Not Ready for Inspection | STUART CHAPMAN |
| Deputy Reinf. Masonry | 10/22/2020 | No Access for Inspection | ELMER BLAND |
| Underground Mechanical | 11/16/2020 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/19/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Deputy Wood Construction | 2/24/2021 | No Access for Inspection | ELMER BLAND |
| Footing/Foundation/Slab | 4/13/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Underground Mechanical | 7/16/2021 | Approved | THOMAS LOGRASSO |
| Shower Pan | 8/2/2021 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 2/16/2022 | Corrections Issued | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 4/12/2022 | Conditional Approval | THOMAS LOGRASSO |
| HVAC-Rough | 4/12/2022 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Rough | 4/12/2022 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 6/9/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Gas Test | 6/9/2022 | Approved | THOMAS LOGRASSO |
| HVAC-Rough | 6/9/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 6/14/2022 | Corrections Issued | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 6/14/2022 | Approved | THOMAS LOGRASSO |
| Green Building Rough | 6/14/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| HVAC-Rough | 6/14/2022 | Approved | THOMAS LOGRASSO |
| Verify Sprinkler Sign Off | 6/14/2022 | Approved | THOMAS LOGRASSO |
| Insulation | 7/26/2022 | Conditional Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 9/19/2022 | Corrections Issued | STUART CHAPMAN |
| Drywall Nailing | 9/19/2022 | Conditional Approval | STUART CHAPMAN |
| Green Building Rough | 9/19/2022 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 10/5/2022 | Conditional Approval | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 11/30/2022 | Partial Approval | THOMAS LOGRASSO |
| ELECTRICAL-Final | 4/5/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Final | 4/5/2023 | Approved | THOMAS LOGRASSO |
| Smoke Detectors | 4/5/2023 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 4/10/2023 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 4/10/2023 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Final | 4/10/2023 | Approved | THOMAS LOGRASSO |
| Final | 4/10/2023 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 4/10/2023 | Approved | THOMAS LOGRASSO |
| Green Building Final | 4/10/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| HVAC-Final | 4/10/2023 | Approved | THOMAS LOGRASSO |
| Reinforced Masonry Frame | 4/10/2023 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 4/10/2023 | SGSOV Approved | THOMAS LOGRASSO |
| Service/Power Release | 4/10/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 4/27/2023 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 4/27/2023 | Approved | STUART CHAPMAN |
| Service/Power Release | 4/27/2023 | Not Ready for Inspection | STUART CHAPMAN |
| ELECTRICAL-Final | 5/17/2023 | Approved | STUART CHAPMAN |
| Final | 5/17/2023 | Corrections Issued | STUART CHAPMAN |
| PLUMBING-Final | 5/17/2023 | Approved | STUART CHAPMAN |
| Service/Power Release | 5/17/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 5/31/2023 | OK to Issue CofO | STUART CHAPMAN |
| Service/Power Release | 5/31/2023 | Approved | STUART CHAPMAN |