14333 W AETNA ST 91401

Certificate Information: 14333 W AETNA ST 91401

Application / Permit
19010-10000-05665
Plan Check / Job No.
B19LA26361
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(11) Homeless Shelter
Work Description
Emergency Homeless Shelter per Government Code Section 8698.4 and LAMC Section 91.8605. State Approved Modular Sleeping Unit, 70 Beds Total ( 40 Men and 30 Women). A Bridge Home.
Permit Issued
Issued on 6/3/2020
Issuing Office
Current Status
CofO Issued on 7/2/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/13/2019 APPLICANT
Assigned to Plan Check Engineer 12/16/2019 EUGENE BARBEAU
Disabled Access Plans Picked Up 12/18/2019 APPLICANT
Corrections Issued 12/19/2019 EUGENE BARBEAU
Quality Review Completed 12/19/2019 CATHERINE NUEZCA GABA
Green Plans Picked Up 12/19/2019 APPLICANT
Plan Check Approved 3/16/2020 EUGENE BARBEAU
Issued 6/3/2020 APPLICANT
CofO in Progress 7/2/2020 JEFFREY DURAN
Permit Finaled 7/2/2020 JEFFREY DURAN
CofO Issued 7/2/2020 JEFFREY DURAN
Permit Finaled 7/2/2020 JEFFREY DURAN

Permit Application Clearance Information

Address approval Cleared 12/18/2019 ERIK BEASLEY
Roof/Waste drainage to street Cleared 12/18/2019 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 12/19/2019 JEANIE LAM
Sewer availability Cleared 12/19/2019 JEANIE LAM
DAS Clearance Cleared 12/20/2019 EUGENE BARBEAU
Metro Rail approval Cleared 12/20/2019 EUGENE BARBEAU
Green Code Cleared 12/23/2019 KHEDER ALRAZAA
Hydrant and Access approval Cleared 12/23/2019 JEREMY CARTER

Contact Information

Architect Lehrer,, Michael Berryl; Lic. No.: C12115 LEHRER ARCHITECTS LA INC   2140 HYPERION AVE    LOS ANGELES, CA 90027
Contractor Ford E C Inc; Lic. No.: 396212-A 10850 WILSHIRE BLVD #380      LOS ANGELES, CA 90024
Engineer Forcier,, Easton Rene; Lic. No.: GE2948 233 TULANE ROAD      COSTA MESA, CA 92626

Inspector Information

JOHN KITCKO, (818) 374-1109 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/4/2020 Conditional Approval JEFFREY DURAN
Pre-Inspection 6/11/2020 Partial Approval JOHN KITCKO
Final 6/30/2020 Not Ready for Inspection JOHN KITCKO
Footing/Foundation/Slab 6/30/2020 Approved JOHN KITCKO
Green Building Final 6/30/2020 Not Ready for Inspection JOHN KITCKO
Green Building Rough 6/30/2020 Approved JOHN KITCKO
SGSOV-Seismic Gas S/O Valve 6/30/2020 SGSOV No Gas JOHN KITCKO
Smoke Detectors 6/30/2020 Approved JOHN KITCKO
Verify Sprinkler Sign Off 6/30/2020 Not Ready for Inspection JOHN KITCKO
Wood Frame 6/30/2020 Partial Inspection JOHN KITCKO
Final 7/1/2020 Partial Inspection DANNY RODRIGUEZ
Final 7/2/2020 OK to Issue CofO JEFFREY DURAN
Green Building Final 7/2/2020 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 7/2/2020 Approved DANNY RODRIGUEZ
Wood Frame 7/2/2020 Not Ready for Inspection DANNY RODRIGUEZ