Permit Issued
Issued on 8/21/2024
Issuing Office
Metro
Current Status
Issued on 8/21/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/13/2019 APPLICANT
Assigned to Plan Check Engineer 12/24/2019 SUNMIN LEE
Corrections Issued 1/29/2020 RAHEL BEYENE
Quality Review Completed 2/1/2020 STANLEY RAAP
Applicant returned to address corrections 7/15/2022 RAHEL BEYENE
Applicant returned to address corrections 7/26/2022 RAHEL BEYENE
Applicant returned to address corrections 7/27/2022 RAHEL BEYENE
Applicant returned to address corrections 7/28/2022 RAHEL BEYENE
Building Plans Picked Up 7/29/2022 APPLICANT
Applicant returned to address corrections 2/16/2024 SUNMIN LEE
Applicant returned to address corrections 4/19/2024 SUNMIN LEE
Applicant returned to address corrections 5/10/2024 SUNMIN LEE
Plan Check Approved 8/21/2024 SUNMIN LEE
Issued 8/21/2024 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/17/2020 DINAH GARIN
Sewer availability Cleared 6/17/2020 DINAH GARIN
Hydrant and Access approval Cleared 5/18/2021 KURT CORRAL
Low Impact Development Cleared 3/29/2022 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 4/9/2022 STEVEN JIN
Permit Cleared 4/21/2022 DINAH GARIN
Coastal Zone Cleared 7/29/2022 ANACANY HURTADO
Miscellaneous Cleared 7/29/2022 ANACANY HURTADO
Miscellaneous Cleared 7/29/2022 ANACANY HURTADO
Specific Plan Cleared 7/29/2022 ANACANY HURTADO
Specific Plan Cleared 7/29/2022 ANACANY HURTADO
ZA Case Cleared 7/29/2022 ANACANY HURTADO
ZA Case Cleared 7/29/2022 ANACANY HURTADO
Excavation more than 5-ft deep Cleared 6/22/2023 CALOSHA APPROVED
Green Code Cleared 4/10/2024 RAHEL BEYENE
Specific Plan Cleared 8/13/2024 FREDDY GARCIA

Contact Information

Architect Elmanovich,, Vladimir; Lic. No.: C25822 134 N WESTGATE AVE      LOS ANGELES, CA 90049
Contractor Owner-Builder       ,
Engineer Levitas,, Felix; Lic. No.: C62311 6634 VALJEAN AVE      VAN NUYS, CA 91406
Engineer Mccormick,, Charles Norman; Lic. No.: C32534 15408 E 4TH AVE APT 114      SPOKANE VALLEY, WA 99037
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22814 DOLOROSA ST      WOODLAND HILLS, CA 91367

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

METHANE-Subgrade 9/18/2024 Corrections Issued HERBERT GIRON
METHANE-Barrier 10/11/2024 Approved HERBERT GIRON
METHANE-Subgrade 10/11/2024 Approved HERBERT GIRON
Underground Mechanical 10/12/2024 Partial Approval BOBBY KEY
Deputy Methane Barrier 10/15/2024 Approved HERBERT GIRON
Footing/Foundation/Slab 10/15/2024 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 10/16/2024 Approved HERBERT GIRON
Deputy Reinf. Concrete 10/17/2024 Conditional Approval HERBERT GIRON
Deputy Steel/Welding 12/2/2024 Conditional Approval DAVID FEILER
Deputy Steel/Welding 12/17/2024 Conditional Approval DAVID FEILER
Deputy Steel/Welding 1/10/2025 Conditional Approval HERBERT GIRON
Deputy Steel/Welding 2/11/2025 Conditional Approval HERBERT GIRON
Deputy Steel/Welding 3/4/2025 Conditional Approval JAYLIN GRAVITTE
PLUMBING-Rough 5/15/2025 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Rough 5/22/2025 Partial Approval JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 5/22/2025 Partial Approval JESUS RODRIGUEZ
PLUMBING-Rough 5/22/2025 Partial Approval JESUS RODRIGUEZ
Deck 6/12/2025 Partial Approval JESUS RODRIGUEZ
PLUMBING-Rough 6/12/2025 Partial Approval JESUS RODRIGUEZ
Deck 7/9/2025 Partial Approval RUBEN RIVAS
ELECTRICAL-Rough 7/9/2025 Partial Approval RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 9/4/2025 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Rough 9/4/2025 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 9/5/2025 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 9/5/2025 Partial Approval JESUS RODRIGUEZ
HVAC-Rough 9/5/2025 Approved JESUS RODRIGUEZ
PLUMBING-Rough 9/5/2025 Approved JESUS RODRIGUEZ
Insulation 9/29/2025 Corrections Issued JESUS RODRIGUEZ
Verify Sprinkler Sign Off 9/29/2025 Approved JESUS RODRIGUEZ
Insulation 10/30/2025 Corrections Issued JESUS RODRIGUEZ
Insulation 11/3/2025 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 11/7/2025 Approved JESUS RODRIGUEZ
Drywall Nailing 11/7/2025 Approved JESUS RODRIGUEZ
Green Building Rough 11/7/2025 Approved JESUS RODRIGUEZ
Insulation 11/7/2025 Approved JESUS RODRIGUEZ
METHANE-Rough 11/7/2025 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 2/24/2026 Corrections Issued RUBEN RIVAS
ELECTRICAL-Final 3/16/2026 Approved MICHAEL ALLEN
Green Building Final 3/16/2026 Not Ready for Inspection MICHAEL ALLEN
Reinforced Concrete Frame 3/16/2026 Approved MICHAEL ALLEN
SGSOV-Seismic Gas S/O Valve 3/16/2026 SGSOV Not Ready MICHAEL ALLEN
Service/Power Release 3/16/2026 Corrections Issued MICHAEL ALLEN
Smoke Detectors 3/16/2026 Approved MICHAEL ALLEN
ELECTRICAL-Final 4/21/2026 Approved RUBEN RIVAS
Service/Power Release 4/21/2026 Approved RUBEN RIVAS