827-827 1/2 N CENTENNIAL ST 90012

Certificate Information: 827-827 1/2 N CENTENNIAL ST 90012

Application / Permit
19010-10000-05624
Plan Check / Job No.
B19LA26270
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 3-STORY DUPLEX WITH GARAGES 1 OF 2
Permit Issued
Issued on 7/6/2021
Issuing Office
Current Status
CofO Issued on 12/13/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/12/2019 APPLICANT
Assigned to Plan Check Engineer 1/10/2020 ARSALAN SHABESTARI
Corrections Issued 1/27/2020 MIGUEL JIMENEZ
Quality Review Completed 2/6/2020 BILL STUTSMAN
Building Plans Picked Up 2/13/2020 APPLICANT
Applicant returned to address corrections 2/19/2020 MIGUEL JIMENEZ
Applicant returned to address corrections 4/8/2020 ARSALAN SHABESTARI
Applicant returned to address corrections 5/8/2020 ARSALAN SHABESTARI
Applicant returned to address corrections 7/13/2020 ARSALAN SHABESTARI
Green Plans Picked Up 7/27/2020 APPLICANT
Plan Check Approved 6/24/2021 ARSALAN SHABESTARI
Issued 7/6/2021 APPLICANT
CofO in Progress 12/5/2022 THOMAS LOGRASSO
Permit Finaled 12/13/2022 DEROLD HAUFF
CofO Issued 12/13/2022 DEROLD HAUFF
Permit Finaled 12/13/2022 DEROLD HAUFF

Permit Application Clearance Information

Historic Resource Verification Cleared 7/21/2020 MICAELA TORRES-GIL
Green Code Cleared 7/23/2020 DONALD CRICHLOW
Green Code Cleared 7/23/2020 MIGUEL JIMENEZ
Address approval Cleared 8/7/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 8/7/2020 RENZ SORIANO
Highway dedication Cleared 8/7/2020 RENZ SORIANO
Permit Cleared 8/7/2020 RENZ SORIANO
Disturb/Remove Protected Trees Cleared 8/12/2020 STEPHEN DUPREY
Hydrant and Access approval Cleared 8/18/2020 MATTHEW CRAIG
Low Impact Development Cleared 10/19/2020 MITESH PATEL
Abandoned oil well Cleared 4/1/2021 JOHN CONNEALLY
Abandoned oil well approval Cleared 4/1/2021 JOHN CONNEALLY
Redevelopment Project Area Cleared 4/5/2021 GRACIELA ACOSTA
ZI Cleared 4/5/2021 GRACIELA ACOSTA
ZI Cleared 4/12/2021 RICHARD REASER
Roof/Waste drainage to street Cleared 4/22/2021 RENZ SORIANO
Sewer availability Cleared 4/22/2021 RENZ SORIANO

Contact Information

Contractor Owner-Builder       ,
Engineer Alvarado,, Carlos Humberto; Lic. No.: C19857 745 N WALNUTHAVEN DR      WEST COVINA, CA 91790
Engineer Downey,, Henry Ross; Lic. No.: S2628 7463 VARNA AVE      NORTH HOLLYWOOD, CA 916054011

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/5/2021 Corrections Issued THOMAS LOGRASSO
PLUMBING-Rough 8/5/2021 Partial Approval THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 8/9/2021 Partial Approval THOMAS LOGRASSO
Footing/Foundation/Slab 8/9/2021 Partial Approval THOMAS LOGRASSO
ELECTRICAL-Rough 8/17/2021 Partial Approval THOMAS LOGRASSO
METHANE-Subgrade 8/17/2021 Conditional Approval THOMAS LOGRASSO
Footing/Foundation/Slab 8/20/2021 Partial Inspection THOMAS LOGRASSO
METHANE-Barrier 8/20/2021 Not Ready for Inspection THOMAS LOGRASSO
METHANE-Subgrade 8/20/2021 Not Ready for Inspection THOMAS LOGRASSO
Footing/Foundation/Slab 8/30/2021 Partial Approval THOMAS LOGRASSO
METHANE-Barrier 8/30/2021 Conditional Approval THOMAS LOGRASSO
METHANE-Subgrade 8/30/2021 Conditional Approval THOMAS LOGRASSO
Reinforced Concrete Frame 8/30/2021 Conditional Approval THOMAS LOGRASSO
Deputy Steel/Welding 11/10/2021 Conditional Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 12/1/2021 Approved THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 12/23/2021 Partial Approval THOMAS LOGRASSO
METHANE-Barrier 12/23/2021 Approved THOMAS LOGRASSO
METHANE-Subgrade 12/23/2021 Approved THOMAS LOGRASSO
Deputy Wood Construction 1/11/2022 Conditional Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 1/24/2022 Corrections Issued THOMAS LOGRASSO
ELECTRICAL-Rough 3/8/2022 Approved THOMAS LOGRASSO
Gas Test 3/8/2022 Approved THOMAS LOGRASSO
HVAC-Rough 3/8/2022 Approved THOMAS LOGRASSO
PLUMBING-Rough 3/8/2022 Conditional Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 3/16/2022 Conditional Approval STUART CHAPMAN
Deputy Wood Construction 3/16/2022 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 3/16/2022 Partial Approval STUART CHAPMAN
Green Building Rough 3/16/2022 Not Ready for Inspection STUART CHAPMAN
MERV13>=Rough 3/16/2022 Approved STUART CHAPMAN
METHANE-Rough 3/16/2022 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Rough 3/16/2022 Approved STUART CHAPMAN
Verify Sprinkler Sign Off 3/16/2022 Partial Approval STUART CHAPMAN
Green Building Rough 4/1/2022 Approved THOMAS LOGRASSO
Insulation 4/1/2022 Corrections Issued THOMAS LOGRASSO
Shower Pan 4/1/2022 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 4/8/2022 Partial Approval THOMAS LOGRASSO
Verify Sprinkler Sign Off 4/8/2022 Approved THOMAS LOGRASSO
Drywall Nailing 4/12/2022 Approved THOMAS LOGRASSO
Sewer 5/24/2022 Approved THOMAS LOGRASSO
Underground Mechanical 6/29/2022 Corrections Issued THOMAS LOGRASSO
Underground Mechanical 7/6/2022 Approved THOMAS LOGRASSO
ELECTRICAL-Final 9/9/2022 Approved THOMAS LOGRASSO
HVAC-Final 9/9/2022 Corrections Issued THOMAS LOGRASSO
PLUMBING-Final 9/9/2022 Corrections Issued THOMAS LOGRASSO
Smoke Detectors 9/9/2022 Approved THOMAS LOGRASSO
ELECTRICAL-Final 9/20/2022 Approved THOMAS LOGRASSO
Green Building Final 9/20/2022 Partial Approval THOMAS LOGRASSO
HVAC-Final 9/20/2022 Partial Approval THOMAS LOGRASSO
PLUMBING-Final 9/20/2022 Partial Approval THOMAS LOGRASSO
Service/Power Release 9/28/2022 Approved THOMAS LOGRASSO
Green Building Final 10/6/2022 Approved THOMAS LOGRASSO
HVAC-Final 10/6/2022 Approved THOMAS LOGRASSO
MERV13>=Final 10/6/2022 Approved THOMAS LOGRASSO
METHANE-Final 10/6/2022 Not Ready for Inspection THOMAS LOGRASSO
PLUMBING-Final 10/6/2022 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 11/22/2022 Partial Inspection FREDDIE RIVERA
Footing/Foundation/Slab 11/22/2022 Partial Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 11/22/2022 SGSOV Not Ready FREDDIE RIVERA
Structural Steel Frame 11/22/2022 Partial Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 11/29/2022 Approved THOMAS LOGRASSO
Final 11/29/2022 Corrections Issued THOMAS LOGRASSO
Footing/Foundation/Slab 11/29/2022 Approved THOMAS LOGRASSO
METHANE-Final 11/29/2022 Approved THOMAS LOGRASSO
METHANE-Rough 11/29/2022 Approved THOMAS LOGRASSO
Pre-Inspection 11/29/2022 Approved THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 11/29/2022 SGSOV Approved THOMAS LOGRASSO
Structural Steel Frame 11/29/2022 Approved THOMAS LOGRASSO
Final 12/2/2022 OK to Issue CofO THOMAS LOGRASSO
Service/Power Release 12/2/2022 Partial Inspection THOMAS LOGRASSO