6654 N DENNY AVE 91606

Certificate Information: 6654 N DENNY AVE 91606

Application / Permit
19010-10000-05604
Plan Check / Job No.
B19LA26219
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2-STORY ACCESSORY DWELLING UNIT PER AB 494 AMD SB 229 WITH ATTACHED GARAGE
Permit Issued
Issued on 8/2/2022
Issuing Office
Metro
Current Status
CofO Issued on 11/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/12/2019 APPLICANT
Assigned to Plan Check Engineer 12/18/2019 CRYSTEL MAALOUF
Plans on Hold 1/15/2020 JASON HEALEY
Hold Released 3/4/2020 JASON HEALEY
Corrections Issued 3/4/2020 CRYSTEL MAALOUF
Quality Review Completed 3/16/2020 BILL STUTSMAN
Green Plans Picked Up 9/3/2020 APPLICANT
Applicant returned to address corrections 5/19/2021 CRYSTEL MAALOUF
Applicant returned to address corrections 6/10/2021 CRYSTEL MAALOUF
Building Plans Picked Up 8/16/2021 APPLICANT
Applicant returned to address corrections 10/19/2021 CRYSTEL MAALOUF
Plan Check Approved 11/19/2021 CRYSTEL MAALOUF
Issued 8/2/2022 APPLICANT
CofO in Progress 9/25/2024 ROBERTO PALACIOS-LOPEZ
No Progress 10/18/2024 ROBERT GOLD
CofO in Progress 10/18/2024 ROBERT GOLD
Permit Finaled 11/14/2024 DANIEL ORRANTE
CofO Issued 11/14/2024 DANIEL ORRANTE
Permit Finaled 11/14/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 11/23/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 1/22/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 1/22/2021 JOHN TRIANTAFYLLOS
Hydrant and Access approval Cleared 2/1/2021 JOHN CONNEALLY
Low Impact Development Cleared 3/9/2021 SARAH YOUSSEF
Stormwater Pollution Mitigatn Cleared 3/9/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 3/11/2021 GABRIEL ROBLES
Green Code Cleared 10/19/2021 DONALD CRICHLOW

Contact Information

Contractor Owner-Builder       ,
Engineer Martirossyan,, Armen; Lic. No.: C64223 802 PORTOLA AVE      GLENDALE, CA 91206

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/9/2022 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 11/21/2022 Approved RYAN SALAZAR
BUILDING-Rough-Frame 12/2/2022 Partial Approval JOHN HAYES
PLUMBING-Rough 12/2/2022 Partial Approval JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 3/6/2023 Approved JOHN HAYES
BUILDING-Rough-Frame 4/24/2023 Partial Approval JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 4/24/2023 Partial Approval JOHN HAYES
Green Building Rough 4/24/2023 Not Ready for Inspection JOHN HAYES
Verify Sprinkler Sign Off 4/24/2023 Approved JOHN HAYES
BUILDING-Rough-Frame 6/16/2023 Partial Approval JENNIFER RABUCHIN
Deputy Wood Construction 6/16/2023 Conditional Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 6/16/2023 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 6/16/2023 Not Ready for Inspection JENNIFER RABUCHIN
Wood Frame 6/16/2023 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 6/30/2023 Approved JOHN HAYES
Interior/Exterior Lathing 8/14/2023 Corrections Issued JOHN HAYES
Rough-Elec/Plmb/HVAC 8/14/2023 Not Ready for Inspection JOHN HAYES
Interior/Exterior Lathing 9/15/2023 Not Ready for Inspection JOHN HAYES
Rough-Elec/Plmb/HVAC 9/15/2023 Not Ready for Inspection JOHN HAYES
Interior/Exterior Lathing 9/25/2023 Not Ready for Inspection ROBERT GOLD
Rough-Elec/Plmb/HVAC 9/25/2023 Corrections Issued ROBERT GOLD
BUILDING-Rough-Frame 10/2/2023 Conditional Approval ROBERT GOLD
Green Building Rough 10/2/2023 Approved ROBERT GOLD
Interior/Exterior Lathing 10/2/2023 Partial Approval ROBERT GOLD
Rough-Elec/Plmb/HVAC 10/2/2023 Approved ROBERT GOLD
Insulation 10/23/2023 Approved JUAN VALENZUELA
Drywall Nailing 11/6/2023 Partial Approval ROBERT GOLD
Shower Pan 3/1/2024 Approved ROBERT GOLD
Underground Mechanical 3/1/2024 Partial Approval ROBERT GOLD
Interior/Exterior Lathing 3/18/2024 Approved ROBERT GOLD
Underground Mechanical 3/18/2024 Partial Approval ROBERT GOLD
ELECTRICAL-Final 5/28/2024 Not Ready for Inspection DAVID MATSON
ELECTRICAL-Final 6/11/2024 Corrections Issued ROBERT GOLD
BUILDING-Rough-Frame 8/1/2024 Approved ROBERTO PALACIOS-LOPEZ
Final 8/1/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Gas Test 8/1/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 8/1/2024 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 8/1/2024 SGSOV Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 8/1/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Smoke Detectors 8/1/2024 Approved ROBERTO PALACIOS-LOPEZ
Final 9/18/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Gas Test 9/18/2024 Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 9/18/2024 Conditional Approval ROBERTO PALACIOS-LOPEZ
Final 9/25/2024 OK to Issue CofO ROBERTO PALACIOS-LOPEZ
Service/Power Release 9/25/2024 Approved ROBERTO PALACIOS-LOPEZ