4367 S BERRYMAN AVE 1-21 90066

Certificate Information: 4367 S BERRYMAN AVE 1-21 90066

Application / Permit
19010-10000-05593
Plan Check / Job No.
B19LA26177
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 4 STORY 21 UNITS TYPE VA APARTMENT BUILDING OVER 1 LEVEL TYPE IA SUBTERRANEAN PARKING
Permit Issued
Issued on 3/21/2022
Issuing Office
Metro
Current Status
CofO Corrected on 8/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/12/2019 APPLICANT
Assigned to Plan Check Engineer 12/27/2019 HERNAN ARREOLA
Corrections Issued 12/30/2019 HERNAN ARREOLA
Quality Review Completed 1/7/2020 BILL STUTSMAN
Building Plans Picked Up 1/8/2020 APPLICANT
Applicant returned to address corrections 10/26/2020 HERNAN ARREOLA
Applicant returned to address corrections 11/19/2020 HERNAN ARREOLA
Plan Check Approved 3/21/2022 HERNAN ARREOLA
Issued 3/21/2022 APPLICANT
CofO in Progress 7/28/2025 DERRICK SPENCER
CofO Issued-Status Void 7/28/2025 HENRY BAGHDASSARIAN
Permit Finaled-Status Void 7/28/2025 HENRY BAGHDASSARIAN
Re-Activate Permit 8/1/2025 HENRY BAGHDASSARIAN
Permit Finaled 8/6/2025 HENRY BAGHDASSARIAN
CofO Corrected 8/6/2025 HENRY BAGHDASSARIAN
Permit Finaled 8/6/2025 HENRY BAGHDASSARIAN

Permit Application Clearance Information

Construction near power lines Cleared 2/8/2020 RIDWAN HARDY
Address approval Cleared 7/30/2020 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 8/25/2020 HISASHI KOBAYAKAWA
Sewer availability Cleared 8/25/2020 HISASHI KOBAYAKAWA
Frnt yard landscape/Water mgmt Cleared 11/18/2020 NOAH MCCOY
Opn space landscape/Water mgmt Cleared 11/18/2020 NOAH MCCOY
Highway dedication Cleared 8/5/2021 RAYMOND MUGAMBWA
Low Impact Development Cleared 8/13/2021 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 8/17/2021 KATHLEEN LEE
Hydrant and Access approval Cleared 9/27/2021 ROBERT DUFF
Specific Plan Cleared 11/11/2021 PETE EYRE
Fire Marshall Fire Life Safety Cleared 12/16/2021 OSCAR SALGADO JR
Green Code Cleared 12/23/2021 AARON COSTA
Permit Cleared 3/1/2022 KATHLEEN LEE
Building over 3-story or 36-ft Cleared 3/9/2022 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 3/9/2022 CALOSHA APPROVED

Contact Information

Architect Tighe,, Patrick J; Lic. No.: C27987 5757 VENICE BLVD      LOS ANGELES, CA 90019
Contractor L V Construction L L C; Lic. No.: 1043604-B 1768 MARY ROAD      ACTON, CA 93510
Engineer Fischer,, Kurt Mark; Lic. No.: S5432 PO BOX 809      POWAY, CA 92074
Engineer Irvine,, Jon Alan; Lic. No.: GE2891 145 N SIERRA MADRE BLVD STE 1      PASADENA, CA 91107

Inspector Information

VASIL MIHALEV, (310) 914-3920 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/17/2022 Approved JEFF BYTHEWAY
Excavation/Setback/Form/Re-Bar 8/31/2022 Partial Approval JEFF BYTHEWAY
Excavation/Setback/Form/Re-Bar 9/8/2022 Partial Approval JEFF BYTHEWAY
Footing/Foundation/Slab 9/8/2022 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 9/9/2022 Approved DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 9/13/2022 Partial Approval GRANT WOODS
Excavation/Setback/Form/Re-Bar 9/22/2022 Not Ready for Inspection GRANT WOODS
Excavation/Setback/Form/Re-Bar 9/23/2022 Partial Approval GRANT WOODS
Reinforced Concrete Frame 9/23/2022 Not Ready for Inspection GRANT WOODS
Reinforced Concrete Frame 9/27/2022 Not Ready for Inspection GRANT WOODS
Excavation/Setback/Form/Re-Bar 9/28/2022 Partial Approval GRANT WOODS
Deputy Reinf. Concrete 9/29/2022 Approved GRANT WOODS
Deputy Shotcrete 9/29/2022 Approved GRANT WOODS
Deputy Shotcrete 9/30/2022 Approved GRANT WOODS
Excavation/Setback/Form/Re-Bar 9/30/2022 Partial Approval GRANT WOODS
Deputy Reinf. Concrete 10/18/2022 Conditional Approval GRANT WOODS
Excavation/Setback/Form/Re-Bar 10/20/2022 Not Ready for Inspection GRANT WOODS
Footing/Foundation/Slab 10/20/2022 Not Ready for Inspection GRANT WOODS
Excavation/Setback/Form/Re-Bar 10/31/2022 Partial Approval GRANT WOODS
Deputy Reinf. Concrete 11/1/2022 Conditional Approval GRANT WOODS
Excavation/Setback/Form/Re-Bar 11/2/2022 Not Ready for Inspection ALAN NOVAK
Excavation/Setback/Form/Re-Bar 11/4/2022 Partial Approval ALAN NOVAK
Deputy Drilled-In Anchors 12/28/2022 Approved GRANT WOODS
Deputy Drilled-In Anchors 12/29/2022 Approved GRANT WOODS
Deputy Reinf. Concrete 12/30/2022 Approved GRANT WOODS
Excavation/Setback/Form/Re-Bar 12/30/2022 Partial Approval GRANT WOODS
Deputy Reinf. Concrete 1/3/2023 Approved GRANT WOODS
Deputy Reinf. Masonry 1/13/2023 Conditional Approval GRANT WOODS
Deputy Reinf. Concrete 1/26/2023 Conditional Approval GRANT WOODS
Deputy Reinf. Concrete 1/27/2023 Conditional Approval GRANT WOODS
Excavation/Setback/Form/Re-Bar 1/27/2023 Not Ready for Inspection GRANT WOODS
Deputy Other (see comments) 2/7/2023 Conditional Approval DERRICK SPENCER
Deputy Reinf. Concrete 2/8/2023 Conditional Approval DAVID TSAU
Deputy Reinf. Concrete 2/10/2023 Approved DERRICK SPENCER
Deputy Reinf. Concrete 2/14/2023 Conditional Approval GRANT WOODS
Deputy Reinf. Concrete 2/15/2023 Approved GRANT WOODS
Deputy Reinf. Concrete 2/16/2023 Approved GRANT WOODS
Excavation/Setback/Form/Re-Bar 2/16/2023 Partial Approval GRANT WOODS
Deputy Reinf. Concrete 2/21/2023 Conditional Approval GRANT WOODS
Deputy Drilled-In Anchors 3/9/2023 Conditional Approval GRANT WOODS
Deputy Reinf. Concrete 3/9/2023 Conditional Approval GRANT WOODS
Deputy Drilled-In Anchors 3/21/2023 Conditional Approval GRANT WOODS
Deputy Steel/Welding 3/23/2023 Conditional Approval GRANT WOODS
Deputy Steel/Welding 3/24/2023 Approved GRANT WOODS
Deputy Reinf. Concrete 3/28/2023 Conditional Approval SHAVONNE ESPINOZA
Deputy Steel/Welding 3/28/2023 Conditional Approval SHAVONNE ESPINOZA
Excavation/Setback/Form/Re-Bar 3/29/2023 Partial Approval GRANT WOODS
Footing/Foundation/Slab 3/29/2023 Partial Approval GRANT WOODS
Deputy Reinf. Concrete 3/30/2023 Conditional Approval GRANT WOODS
Deputy Drilled-In Anchors 4/6/2023 Conditional Approval GRANT WOODS
Deputy Steel/Welding 4/6/2023 Conditional Approval GRANT WOODS
Deputy Steel/Welding 4/10/2023 Approved GRANT WOODS
Deputy Steel/Welding 4/19/2023 Approved DERRICK SPENCER
Deputy Wood Construction 4/24/2023 Partial Approval SORIN CIRSTOIU
Floor/Roof Diaphrgm/Shear Wall 4/28/2023 Partial Approval SORIN CIRSTOIU
Deputy Steel/Welding 5/8/2023 Approved GRANT WOODS
Reinforced Concrete Frame 5/10/2023 Approved AMANUEL BERHE
Deputy Reinf. Concrete 5/11/2023 Conditional Approval GRANT WOODS
Deputy Wood Construction 5/15/2023 Approved GRANT WOODS
Floor/Roof Diaphrgm/Shear Wall 5/16/2023 Not Ready for Inspection GRANT WOODS
Green Building Rough 5/16/2023 Not Ready for Inspection GRANT WOODS
Verify Sprinkler Sign Off 5/16/2023 Not Ready for Inspection GRANT WOODS
Wood Frame 5/16/2023 Not Ready for Inspection GRANT WOODS
Floor/Roof Diaphrgm/Shear Wall 5/22/2023 Partial Approval GRANT WOODS
Deputy Wood Construction 5/24/2023 Conditional Approval GRANT WOODS
Floor/Roof Diaphrgm/Shear Wall 5/24/2023 Not Ready for Inspection GRANT WOODS
Deputy Wood Construction 5/26/2023 Conditional Approval GRANT WOODS
Deputy Wood Construction 5/30/2023 Conditional Approval GRANT WOODS
Floor/Roof Diaphrgm/Shear Wall 6/6/2023 Partial Approval GRANT WOODS
Wall Anchors 6/6/2023 Not Ready for Inspection GRANT WOODS
Deputy Wood Construction 6/13/2023 Conditional Approval GRANT WOODS
Green Building Rough 6/27/2023 Not Ready for Inspection GRANT WOODS
Verify Sprinkler Sign Off 6/27/2023 Not Ready for Inspection GRANT WOODS
Deputy Wood Construction 6/28/2023 Conditional Approval GRANT WOODS
Floor/Roof Diaphrgm/Shear Wall 6/29/2023 Partial Approval GRANT WOODS
Wall Anchors 6/29/2023 Not Ready for Inspection GRANT WOODS
Wood Frame 6/29/2023 Partial Approval GRANT WOODS
Green Building Rough 7/3/2023 Not Ready for Inspection GRANT WOODS
Verify Sprinkler Sign Off 7/3/2023 Not Ready for Inspection GRANT WOODS
Wood Frame 7/3/2023 Partial Inspection GRANT WOODS
Deputy Wood Construction 7/14/2023 Conditional Approval GRANT WOODS
Deputy Wood Construction 7/31/2023 Conditional Approval ALAN NOVAK
Deputy Wood Construction 8/1/2023 Conditional Approval ALAN NOVAK
Deputy Wood Construction 8/2/2023 Approved JOEY BUCHANAN
Deputy Wood Construction 8/4/2023 Approved GRANT WOODS
Deputy Wood Construction 8/8/2023 Conditional Approval GRANT WOODS
Green Building Rough 8/8/2023 Not Ready for Inspection GRANT WOODS
Verify Sprinkler Sign Off 8/8/2023 Not Ready for Inspection GRANT WOODS
Wall Anchors 8/8/2023 Not Ready for Inspection GRANT WOODS
Wood Frame 8/8/2023 Not Ready for Inspection GRANT WOODS
Special/Order Compliance 8/10/2023 Partial Approval GRANT WOODS
Wall Anchors 8/10/2023 Partial Approval GRANT WOODS
Deputy Wood Construction 8/11/2023 Conditional Approval GRANT WOODS
Deputy Drilled-In Anchors 8/15/2023 Conditional Approval GRANT WOODS
Deputy Wood Construction 8/18/2023 Conditional Approval GRANT WOODS
Floor/Roof Diaphrgm/Shear Wall 8/24/2023 Not Ready for Inspection GRANT WOODS
Green Building Rough 8/24/2023 Not Ready for Inspection GRANT WOODS
Verify Sprinkler Sign Off 8/24/2023 Not Ready for Inspection GRANT WOODS
Wood Frame 8/24/2023 Not Ready for Inspection GRANT WOODS
Floor/Roof Diaphrgm/Shear Wall 8/28/2023 Not Ready for Inspection GRANT WOODS
Deputy Wood Construction 8/31/2023 Conditional Approval GRANT WOODS
Deputy Wood Construction 9/7/2023 Approved GRANT WOODS
Floor/Roof Diaphrgm/Shear Wall 9/7/2023 Not Ready for Inspection GRANT WOODS
Deputy Wood Construction 9/13/2023 Conditional Approval GRANT WOODS
Floor/Roof Diaphrgm/Shear Wall 9/13/2023 Not Ready for Inspection GRANT WOODS
Wall Anchors 9/13/2023 Not Ready for Inspection GRANT WOODS
Deputy Drilled-In Anchors 9/15/2023 Conditional Approval GRANT WOODS
Floor/Roof Diaphrgm/Shear Wall 9/19/2023 Not Ready for Inspection GRANT WOODS
Floor/Roof Diaphrgm/Shear Wall 9/21/2023 Not Ready for Inspection GRANT WOODS
Floor/Roof Diaphrgm/Shear Wall 9/27/2023 Partial Approval GRANT WOODS
Deputy Wood Construction 9/28/2023 Conditional Approval GRANT WOODS
Deputy Wood Construction 10/3/2023 Conditional Approval GRANT WOODS
Floor/Roof Diaphrgm/Shear Wall 10/4/2023 Partial Approval GRANT WOODS
Green Building Rough 10/4/2023 Not Ready for Inspection GRANT WOODS
Verify Sprinkler Sign Off 10/4/2023 Not Ready for Inspection GRANT WOODS
Wood Frame 10/4/2023 Partial Approval GRANT WOODS
Deputy Wood Construction 10/5/2023 Conditional Approval GRANT WOODS
Deputy Wood Construction 10/13/2023 Conditional Approval GRANT WOODS
Floor/Roof Diaphrgm/Shear Wall 10/16/2023 Partial Inspection GRANT WOODS
Wall Anchors 10/16/2023 Partial Inspection GRANT WOODS
Drywall Nailing 11/9/2023 Partial Approval ALAN NOVAK
Floor/Roof Diaphrgm/Shear Wall 11/22/2023 Not Ready for Inspection GRANT WOODS
Special/Order Compliance 11/29/2023 Partial Inspection GRANT WOODS
Green Building Rough 11/30/2023 Not Ready for Inspection GRANT WOODS
Verify Sprinkler Sign Off 11/30/2023 Partial Approval GRANT WOODS
Wood Frame 11/30/2023 Partial Approval GRANT WOODS
Pre-Inspection 1/4/2024 Not Ready for Inspection GRANT WOODS
Interior/Exterior Lathing 2/16/2024 Not Ready for Inspection GRANT WOODS
Light Gage Steel Frame 2/21/2024 Partial Approval GRANT WOODS
Drywall Nailing 3/1/2024 Corrections Issued GRANT WOODS
Insulation 3/1/2024 Partial Approval GRANT WOODS
Interior/Exterior Lathing 3/6/2024 Corrections Issued GRANT WOODS
Special/Order Compliance 3/7/2024 Corrections Issued GRANT WOODS
Drywall Nailing 3/12/2024 Partial Approval GRANT WOODS
Drywall Nailing 3/13/2024 Partial Approval GRANT WOODS
Insulation 3/13/2024 Partial Approval GRANT WOODS
Interior/Exterior Lathing 6/21/2024 Not Ready for Inspection GRANT WOODS
Deputy Drilled-In Anchors 6/25/2024 Conditional Approval GRANT WOODS
Light Gage Steel Frame 6/25/2024 Not Ready for Inspection GRANT WOODS
Floor/Roof Diaphrgm/Shear Wall 7/30/2024 Not Ready for Inspection GRANT WOODS
Light Gage Steel Frame 8/12/2024 Not Ready for Inspection GRANT WOODS
Interior/Exterior Lathing 8/30/2024 Partial Approval GRANT WOODS
Special/Order Compliance 10/1/2024 Partial Inspection GRANT WOODS
Pre-Inspection 10/7/2024 Partial Approval GRANT WOODS
Special/Order Compliance 1/27/2025 Partial Inspection GRANT WOODS
Special/Order Compliance 3/14/2025 Approved DERRICK SPENCER
Posting Pre-Inspection 5/9/2025 Approved DERRICK SPENCER
Special/Order Compliance 5/9/2025 Approved DERRICK SPENCER
Verify Rec and Parks Fee Memo 5/9/2025 Approved DERRICK SPENCER
Final 5/14/2025 Not Ready for Inspection DERRICK SPENCER
Footing/Foundation/Slab 5/14/2025 Approved DERRICK SPENCER
Green Building Final 5/14/2025 Approved DERRICK SPENCER
Green Building Rough 5/14/2025 Approved DERRICK SPENCER
SGSOV-Seismic Gas S/O Valve 5/14/2025 SGSOV Approved DERRICK SPENCER
Smoke Detectors 5/14/2025 Approved DERRICK SPENCER
Verify Sprinkler Sign Off 5/14/2025 Approved DERRICK SPENCER
Wood Frame 5/14/2025 Approved DERRICK SPENCER
Final 5/28/2025 Not Ready for Inspection DERRICK SPENCER
Verify Rec and Parks Fee Memo 5/28/2025 Approved DERRICK SPENCER
Final 6/4/2025 OK to Issue CofO DERRICK SPENCER