9958 W REGENT ST 1-24 90034

Certificate Information: 9958 W REGENT ST 1-24 90034

Application / Permit
19010-10000-05587
Plan Check / Job No.
B19LA26160
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 5 STORY, TYPE III-A 24 UNIT(3 ELI, 1 VL, AND 1 LI) APARTMENT BUILDING OVER 1 STORY TYPE IA PARKING PER 12.22.A.33 AND DIR-2019-7558-TOC
Permit Issued
Issued on 5/19/2022
Issuing Office
Current Status
Issued on 5/19/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/19/2019 APPLICANT
Assigned to Plan Check Engineer 1/9/2020 KESETE HAREGOT
Corrections Issued 1/13/2020 KESETE HAREGOT
Quality Review Completed 1/24/2020 ARMEN JIVALAGIAN
Applicant returned to address corrections 6/3/2021 KEVIN MORALES
Applicant returned to address corrections 10/6/2021 KEVIN MORALES
Plan Check Approved 1/18/2022 KEVIN MORALES
Issued 5/19/2022 APPLICANT
Building Plans Picked Up 6/1/2022 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/23/2021 RAYMOND MUGAMBWA
Address approval Cleared 2/25/2021 RAYMOND MUGAMBWA
Permit Cleared 3/25/2021 RAYMOND MUGAMBWA
Grading Pre-Inspection Cleared 4/30/2021 BRIAN MILLER
Building over 3-story or 36-ft Cleared 6/1/2021 CALOSHA APPROVED
Hydrant and Access approval Cleared 6/1/2021 KURT CORRAL
Highway dedication Cleared 6/15/2021 RAYMOND MUGAMBWA
Sewer availability Cleared 6/16/2021 RAYMOND MUGAMBWA
Trees in Parkway Cleared 7/8/2021 JOHN KIM
Green Code Cleared 7/13/2021 KESETE HAREGOT
GPI Written Notices Cleared 8/11/2021 KESETE HAREGOT
Work Adjacent to Public Way Cleared 8/11/2021 SAUL GARCIA
Disturb/Remove Protected Trees Cleared 8/19/2021 ADRIAN SANCHEZ
Fire Marshall Fire Life Safety Cleared 9/27/2021 MENOA AGHAJANI
DAS Clearance Cleared 9/30/2021 KESETE HAREGOT
DCP conditions approval Cleared 10/5/2021 DORIS KWOK
Density Bonus 12.22.A.31 Cleared 10/5/2021 DORIS KWOK
Public Housing Cleared 10/12/2021 JOEL LAUNCHBAUGH
Tract Map conditions Cleared 10/19/2021 TERRI OSBORNE
Frnt yard landscape/Water mgmt Cleared 10/26/2021 TERRI OSBORNE
Miscellaneous Cleared 10/26/2021 TERRI OSBORNE
Opn space landscape/Water mgmt Cleared 10/26/2021 TERRI OSBORNE
Specific Plan Cleared 11/15/2021 PEDRO AYALA
Specific Plan Cleared 11/15/2021 PEDRO AYALA
Bicycle Parking Cleared 11/16/2021 RAYMOND MUGAMBWA
Specific Plan Cleared 12/21/2021 DYLAN SITTIG
Low Impact Development Cleared 1/5/2022 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 1/10/2022 RAYMOND MUGAMBWA

Contact Information

Contractor Project Delivery Group West; Lic. No.: 1002189-B 2862 BALLESTEROS LN      TUSTIN, CA 92782
Engineer Fischer,, Kurt Mark; Lic. No.: S5432 PO BOX 809      POWAY, CA 92074

Inspector Information

PAUL DAVIDSON, (310) 914-3914 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Pre-Inspection 12/13/2024   

Inspection Request History

Deputy Reinf. Concrete 7/15/2022 Approved JEFF BYTHEWAY
Pre-Inspection 7/15/2022 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 7/20/2022 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 7/22/2022 Approved SORIN CIRSTOIU
Floor/Roof Diaphrgm/Shear Wall 7/26/2022 Not Ready for Inspection JEFF BYTHEWAY
Piling/Pier/Caisson 7/26/2022 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 7/27/2022 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 7/29/2022 Approved DERRICK SPENCER
Deputy Reinf. Concrete 8/4/2022 Approved JEFF BYTHEWAY
Excavation/Setback/Form/Re-Bar 8/4/2022 Partial Approval JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 8/4/2022 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 8/8/2022 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 8/10/2022 Approved JEFF BYTHEWAY
Deputy Drilled-In Anchors 9/9/2022 Approved JEFF BYTHEWAY
Excavation/Setback/Form/Re-Bar 9/9/2022 Partial Approval JEFF BYTHEWAY
Footing/Foundation/Slab 9/9/2022 Partial Approval JEFF BYTHEWAY
Deputy Drilled-In Anchors 9/12/2022 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 9/14/2022 Approved JEFF BYTHEWAY
Deputy Reinf. Masonry 9/19/2022 Approved DERRICK SPENCER
Deputy Reinf. Masonry 9/19/2022 No Access for Inspection JEFF BYTHEWAY
Deputy Reinf. Masonry 9/22/2022 Conditional Approval DERRICK SPENCER
Deputy Reinf. Masonry 9/23/2022 Approved DERRICK SPENCER
Deputy Reinf. Masonry 9/26/2022 Conditional Approval DERRICK SPENCER
Deputy Reinf. Masonry 9/27/2022 Conditional Approval DERRICK SPENCER
Deputy Reinf. Masonry 9/29/2022 Approved JEFF BYTHEWAY
Deputy Reinf. Masonry 9/30/2022 Approved JEFF BYTHEWAY
Green Building Rough 10/5/2022 Not Ready for Inspection DERRICK SPENCER
Masonry Wall/Backfill 10/5/2022 Partial Approval DERRICK SPENCER
Reinforced Masonry Frame 10/5/2022 Not Ready for Inspection DERRICK SPENCER
Verify Sprinkler Sign Off 10/5/2022 Not Ready for Inspection DERRICK SPENCER
Deputy Reinf. Masonry 10/12/2022 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 10/24/2022 Approved DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 10/31/2022 Not Ready for Inspection DERRICK SPENCER
Footing/Foundation/Slab 10/31/2022 Not Ready for Inspection DERRICK SPENCER
Structural Steel Frame 10/31/2022 Not Ready for Inspection DERRICK SPENCER
Wall Anchors 10/31/2022 Not Ready for Inspection DERRICK SPENCER
Deputy Reinf. Concrete 11/1/2022 Approved DERRICK SPENCER
Deputy Reinf. Concrete 11/2/2022 Approved DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 11/2/2022 Not Ready for Inspection DERRICK SPENCER
Structural Steel Frame 11/2/2022 Not Ready for Inspection DERRICK SPENCER
Wall Anchors 11/2/2022 Partial Approval DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 11/4/2022 Partial Approval DERRICK SPENCER
Footing/Foundation/Slab 11/4/2022 Partial Approval DERRICK SPENCER
Structural Steel Frame 11/4/2022 Partial Approval DERRICK SPENCER
Wall Anchors 11/4/2022 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 11/7/2022 Approved DERRICK SPENCER
Deputy Drilled-In Anchors 12/9/2022 Approved DERRICK SPENCER
Pre-Inspection 12/29/2022 Approved DERRICK SPENCER
Deputy Wood Construction 12/30/2022 Conditional Approval JEFF BYTHEWAY
Deputy Wood Construction 1/19/2023 Conditional Approval DERRICK SPENCER
Deputy Wood Construction 2/22/2023 Approved DERRICK SPENCER
Deputy Wood Construction 3/6/2023 Conditional Approval JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 4/14/2023 Partial Approval DERRICK SPENCER
Green Building Rough 4/14/2023 Not Ready for Inspection DERRICK SPENCER
Verify Sprinkler Sign Off 4/14/2023 Approved DERRICK SPENCER
Wood Frame 4/14/2023 Partial Approval DERRICK SPENCER
Deputy Wood Construction 5/2/2023 Approved DERRICK SPENCER
Deputy Drilled-In Anchors 9/27/2023 Approved DERRICK SPENCER
Special/Order Compliance 11/28/2023 Approved DERRICK SPENCER
Deputy Wood Construction 12/4/2023 Approved DERRICK SPENCER
Floor/Roof Diaphrgm/Shear Wall 1/26/2024 Partial Approval DERRICK SPENCER
Deputy Wood Construction 2/13/2024 Conditional Approval PAUL DAVIDSON
Floor/Roof Diaphrgm/Shear Wall 2/16/2024 Not Ready for Inspection PAUL DAVIDSON
Floor/Roof Diaphrgm/Shear Wall 2/29/2024 Partial Approval DERRICK SPENCER
Pre-Inspection 2/29/2024 Approved DERRICK SPENCER
Floor/Roof Diaphrgm/Shear Wall 3/14/2024 Conditional Approval PAUL DAVIDSON
Green Building Rough 3/14/2024 Not Ready for Inspection PAUL DAVIDSON
Wall Anchors 3/14/2024 Not Ready for Inspection PAUL DAVIDSON
Wood Frame 3/14/2024 Not Ready for Inspection PAUL DAVIDSON
Light Gage Steel Frame 3/27/2024 Partial Approval DERRICK SPENCER
Floor/Roof Diaphrgm/Shear Wall 4/4/2024 Not Ready for Inspection PAUL DAVIDSON
Floor/Roof Diaphrgm/Shear Wall 4/5/2024 Partial Approval PAUL DAVIDSON
Floor/Roof Diaphrgm/Shear Wall 4/12/2024 Partial Approval DERRICK SPENCER
Floor/Roof Diaphrgm/Shear Wall 4/23/2024 Not Ready for Inspection PAUL DAVIDSON
Floor/Roof Diaphrgm/Shear Wall 4/25/2024 Partial Approval PAUL DAVIDSON
Drywall Nailing 4/26/2024 Not Ready for Inspection PAUL DAVIDSON
Green Building Rough 4/26/2024 Not Ready for Inspection PAUL DAVIDSON
Deputy Wood Construction 5/1/2024 Conditional Approval PAUL DAVIDSON
Floor/Roof Diaphrgm/Shear Wall 5/1/2024 Partial Approval PAUL DAVIDSON
Insulation 5/14/2024 Not Ready for Inspection PAUL DAVIDSON
Drywall Nailing 5/15/2024 Partial Approval PAUL DAVIDSON
Floor/Roof Diaphrgm/Shear Wall 5/15/2024 Not Ready for Inspection PAUL DAVIDSON
Green Building Rough 5/15/2024 Approved PAUL DAVIDSON
Pre-Inspection 5/20/2024 Partial Inspection PAUL DAVIDSON
Deputy Wood Construction 5/21/2024 Conditional Approval PAUL DAVIDSON
Deputy Wood Construction 5/22/2024 Conditional Approval PAUL DAVIDSON
Floor/Roof Diaphrgm/Shear Wall 5/23/2024 Not Ready for Inspection PAUL DAVIDSON
Pre-Inspection 5/29/2024 Partial Inspection PAUL DAVIDSON
Insulation 6/10/2024 Corrections Issued PAUL DAVIDSON
Insulation 6/12/2024 Not Ready for Inspection GRANT WOODS
Drywall Nailing 7/2/2024 Partial Inspection PAUL DAVIDSON
Drywall Nailing 7/10/2024 Partial Approval PAUL DAVIDSON
Insulation 7/16/2024 Not Ready for Inspection PAUL DAVIDSON
Drywall Nailing 7/19/2024 Partial Approval PAUL DAVIDSON
Insulation 8/9/2024 Partial Approval PAUL DAVIDSON
Special/Order Compliance 8/9/2024 Corrections Issued PAUL DAVIDSON
Deputy Wood Construction 8/13/2024 Conditional Approval PAUL DAVIDSON
Deputy Wood Construction 8/23/2024 Conditional Approval PAUL DAVIDSON
Wood Frame 9/3/2024 Not Ready for Inspection DANIEL VARNUM
Interior/Exterior Lathing 9/5/2024 Partial Approval DANIEL VARNUM
Drywall Nailing 9/13/2024 Partial Approval DANIEL VARNUM
Light Gage Steel Frame 9/13/2024 Partial Approval DANIEL VARNUM
Drywall Nailing 9/23/2024 Partial Approval DANIEL VARNUM
Wood Frame 10/10/2024 Partial Approval DANIEL VARNUM
Drywall Nailing 10/16/2024 Partial Approval DANIEL VARNUM
Drywall Nailing 10/24/2024 Partial Inspection DANIEL VARNUM
Drywall Nailing 10/30/2024 Partial Approval DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 11/4/2024 Partial Approval DANIEL VARNUM
Drywall Nailing 11/14/2024 Partial Approval DANIEL VARNUM
Wood Frame 11/20/2024 Partial Approval PAUL DAVIDSON
Drywall Nailing 12/3/2024 Partial Approval DANIEL VARNUM
Light Gage Steel Frame 12/3/2024 Not Ready for Inspection DANIEL VARNUM