330 S SYCAMORE AVE 90036
Certificate Information: 330 S SYCAMORE AVE 90036
- Application / Permit
- 19010-10000-05571
- Plan Check / Job No.
- B19LA26080
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (4'-0" X 20'-3") 2ND STORYADDITION TO EXISTING 2-STORY FLOOR REC ROOM/GARAGE & CONVERT TO ACCESSORY DWELLING UNIT W/ ATTACHED ONE CAR GARAGE PER AB 494 & SB 229
- Permit Issued
- Issued on 1/30/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/10/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/19/2019 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 12/27/2019 | FARSHAD ALIMOHAMADI |
| Quality Review Completed | 12/28/2019 | YOUNG KIM |
| Building Plans Picked Up | 1/7/2020 | APPLICANT |
| Green Plans Picked Up | 1/7/2020 | APPLICANT |
| Plan Check Approved | 1/30/2020 | FARSHAD ALIMOHAMADI |
| Issued | 1/30/2020 | LADBS |
| CofO in Progress | 12/16/2021 | CHRIS CHRISTENSEN |
| Permit Finaled | 2/23/2023 | DANIEL ORRANTE |
| CofO Issued | 2/23/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/23/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 1/7/2020 | THOMAS LANG |
| Roof/Waste drainage to street | Cleared | 1/7/2020 | THOMAS LANG |
| Construction near power lines | Cleared | 1/10/2020 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 1/28/2020 | THOMAS LANG |
| Green Code | Cleared | 1/28/2020 | VIVIAN LAO |
| Sewer availability | Cleared | 1/28/2020 | THOMAS LANG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lee,, Jaeyol; Lic. No.: C51639 | 430 S GARFIELD AVE SUITE 301 ALHAMBRA, CA 91801 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 5/7/2020 | Partial Approval | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 5/7/2020 | Not Ready for Inspection | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 6/12/2020 | Partial Approval | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 6/12/2020 | Approved | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 6/12/2020 | Partial Approval | ARTHUR SARGSYAN |
| PLUMBING-Rough | 6/12/2020 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 6/26/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 6/26/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 6/26/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Rough | 6/26/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| METHANE-Barrier | 6/26/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| METHANE-Rough | 6/26/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| METHANE-Subgrade | 6/26/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 7/7/2020 | Partial Approval | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 7/7/2020 | Approved | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 7/7/2020 | Approved | ARTHUR SARGSYAN |
| Green Building Rough | 7/7/2020 | Approved | ARTHUR SARGSYAN |
| METHANE-Barrier | 7/7/2020 | Approved | ARTHUR SARGSYAN |
| METHANE-Rough | 7/7/2020 | Approved | ARTHUR SARGSYAN |
| METHANE-Subgrade | 7/7/2020 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Rough | 7/7/2020 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 1/6/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Final | 1/6/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 1/6/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 1/6/2021 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 1/6/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 3/3/2021 | Approved | JOSEPH MCGARRY |
| Final | 3/3/2021 | Corrections Issued | JOSEPH MCGARRY |
| Green Building Final | 3/3/2021 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 3/3/2021 | SGSOV Approved | JOSEPH MCGARRY |
| Final | 3/30/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Smoke Detectors | 3/30/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Final | 5/4/2021 | Approved | CHRIS CHRISTENSEN |
| Final | 5/4/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| Green Building Final | 5/4/2021 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 5/4/2021 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 5/4/2021 | Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 5/4/2021 | Approved | CHRIS CHRISTENSEN |
| Final | 7/15/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Final | 12/15/2021 | OK to Issue CofO | CHRIS CHRISTENSEN |