244 S GRAMERCY PL 90004
Certificate Information: 244 S GRAMERCY PL 90004
- Application / Permit
- 19010-10000-05566
- Plan Check / Job No.
- B19LA26043
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SINGLE FAMILY DWELLING WITH 2-CAR ATTACHED GARAGE
- Permit Issued
- Issued on 3/19/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/19/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/10/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/18/2019 | AMIR DANAI |
| Corrections Issued | 12/20/2019 | AMIR DANAI |
| Quality Review Completed | 12/24/2019 | TIEN JEN WANG |
| Building Plans Picked Up | 1/30/2020 | APPLICANT |
| Green Plans Picked Up | 1/30/2020 | APPLICANT |
| Plan Check Approved | 3/17/2020 | AMIR DANAI |
| Issued | 3/19/2020 | LADBS |
| CofO in Progress | 5/11/2021 | CHRIS CHRISTENSEN |
| Permit Finaled | 5/19/2021 | DEROLD HAUFF |
| CofO Issued | 5/19/2021 | DEROLD HAUFF |
| Permit Finaled | 5/19/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Green Code | Cleared | 3/4/2020 | KHEDER ALRAZAA |
| Address approval | Cleared | 3/10/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/10/2020 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 3/10/2020 | GILBERT URREA |
| Low Impact Development | Cleared | 3/10/2020 | ANDRES COVARRUBIAS |
| Permit | Cleared | 3/10/2020 | JEANIE LAM |
| Sewer availability | Cleared | 3/10/2020 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 3/17/2020 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/26/2020 | Approved | JUSTIN CURTIS |
| Special/Order Compliance | 4/14/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Pre-Inspection | 4/20/2020 | Approved | ARTHUR SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 6/2/2020 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 6/2/2020 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 6/5/2020 | Approved | ARTHUR SARGSYAN |
| Wood Frame | 6/23/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| Green Building Rough | 6/26/2020 | Partial Inspection | HAMIK HARTOUNIAN |
| Insulation | 6/26/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 6/26/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| Wood Frame | 6/26/2020 | Partial Approval | HAMIK HARTOUNIAN |
| Insulation | 6/30/2020 | Partial Approval | ARTHUR SARGSYAN |
| PLUMBING-Rough | 6/30/2020 | Partial Approval | ARTHUR SARGSYAN |
| Wood Frame | 7/6/2020 | Approved | ARTHUR SARGSYAN |
| Wood Frame | 7/22/2020 | Partial Approval | ENRIQUE MIRELES |
| Wood Frame | 8/4/2020 | No Access for Inspection | CHRIS CHRISTENSEN |
| Wood Frame | 8/5/2020 | Partial Approval | ARTHUR SARGSYAN |
| Wood Frame | 8/13/2020 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 8/24/2020 | Corrections Issued | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 8/24/2020 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 8/25/2020 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 9/1/2020 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Rough | 9/1/2020 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 9/1/2020 | Corrections Issued | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 9/1/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Rough | 9/4/2020 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 9/10/2020 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 9/10/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 9/10/2020 | Approved | CHRIS CHRISTENSEN |
| Wood Frame | 9/10/2020 | Approved | CHRIS CHRISTENSEN |
| Insulation | 9/16/2020 | Partial Approval | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 9/16/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| Insulation | 9/17/2020 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 9/17/2020 | Partial Approval | JOSEPH MCGARRY |
| Drywall Nailing | 9/23/2020 | Approved | CHRIS CHRISTENSEN |
| Gas Test | 9/23/2020 | Approved | CHRIS CHRISTENSEN |
| Insulation | 9/23/2020 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 10/8/2020 | Approved | CHRIS CHRISTENSEN |
| Shower Pan | 10/8/2020 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 2/18/2021 | Corrections Issued | JOSEPH MCGARRY |
| HVAC-Final | 2/18/2021 | Corrections Issued | JOSEPH MCGARRY |
| PLUMBING-Final | 2/18/2021 | Corrections Issued | JOSEPH MCGARRY |
| ELECTRICAL-Final | 2/25/2021 | Approved | CHRIS CHRISTENSEN |
| Final | 2/25/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 2/25/2021 | Approved | CHRIS CHRISTENSEN |
| Gas Test | 2/25/2021 | Approved | CHRIS CHRISTENSEN |
| Green Building Final | 2/25/2021 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 2/25/2021 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 2/25/2021 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 2/25/2021 | SGSOV Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 2/25/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Smoke Detectors | 2/25/2021 | Approved | CHRIS CHRISTENSEN |
| Final | 3/22/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Service/Power Release | 3/22/2021 | Approved | CHRIS CHRISTENSEN |
| Final | 4/20/2021 | Corrections Issued | JOSEPH MCGARRY |
| Final | 5/10/2021 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Service/Power Release | 5/10/2021 | Approved | CHRIS CHRISTENSEN |