205 S AVENUE 59 90042
Certificate Information: 205 S AVENUE 59 90042
- Application / Permit
- 19010-10000-05563
- Plan Check / Job No.
- B19LA26034
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE. (1 OF 3)
- Permit Issued
- Issued on 8/26/2020
- Issuing Office
- Current Status
- CofO Issued on 6/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/10/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/19/2019 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 12/29/2019 | FARSHAD ALIMOHAMADI |
| Quality Review Completed | 12/29/2019 | YOUNG KIM |
| Green Plans Picked Up | 12/30/2019 | APPLICANT |
| Applicant returned to address corrections | 7/2/2020 | FARSHAD ALIMOHAMADI |
| Building Plans Picked Up | 7/9/2020 | APPLICANT |
| Applicant returned to address corrections | 8/25/2020 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 8/26/2020 | FARSHAD ALIMOHAMADI |
| Issued | 8/26/2020 | APPLICANT |
| CofO in Progress | 6/5/2023 | AMY COLIN |
| CofO Issued | 6/25/2023 | DEROLD HAUFF |
| Permit Finaled | 6/25/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 1/14/2020 | GEORGE SUCHAND |
| Trees in Parkway | Cleared | 1/14/2020 | ADRIAN SANCHEZ |
| Green Code | Cleared | 2/19/2020 | VIVIAN LAO |
| Address approval | Cleared | 2/27/2020 | EMIL KYUPELYAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/27/2020 | EMIL KYUPELYAN |
| HPOZ | Cleared | 2/27/2020 | KATIE DEBIASE |
| Low Impact Development | Cleared | 2/27/2020 | ORVAL HERNANDEZ-MARCI |
| Miscellaneous | Cleared | 2/27/2020 | KATIE DEBIASE |
| Miscellaneous | Cleared | 2/27/2020 | KATIE DEBIASE |
| Permit | Cleared | 2/27/2020 | EMIL KYUPELYAN |
| Roof/Waste drainage to street | Cleared | 2/27/2020 | EMIL KYUPELYAN |
| Sewer availability | Cleared | 2/27/2020 | EMIL KYUPELYAN |
| GPI Written Notices | Cleared | 8/26/2020 | FARSHAD ALIMOHAMADI |
Contact Information
| Engineer | Chiang,, Tzuu Pien; Lic. No.: C72618 | 5399 STARLING DR JURUPA VALLEY, CA 91752 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 11/23/2020 | Partial Approval | COREY HUPP |
| Excavation/Setback/Form/Re-Bar | 12/14/2020 | Corrections Issued | COREY HUPP |
| Excavation/Setback/Form/Re-Bar | 12/18/2020 | Corrections Issued | COREY HUPP |
| Excavation/Setback/Form/Re-Bar | 12/28/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 12/30/2020 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 1/22/2021 | Approved | COREY HUPP |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2021 | Off-Hour Fees Due | |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2021 | Partial Approval | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2021 | Not Ready for Inspection | COREY HUPP |
| BUILDING-Rough-Frame | 5/14/2021 | Not Ready for Inspection | COREY HUPP |
| ELECTRICAL-Rough | 6/1/2021 | Not Ready for Inspection | COREY HUPP |
| Floor/Roof Diaphrgm/Shear Wall | 6/1/2021 | Partial Approval | COREY HUPP |
| BUILDING-Rough-Frame | 6/3/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Rough | 6/3/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| MERV13>=Rough | 6/3/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 6/3/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Wood Frame | 6/3/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 6/15/2021 | Corrections Issued | COREY HUPP |
| HVAC-Rough | 6/15/2021 | Corrections Issued | COREY HUPP |
| PLUMBING-Rough | 6/15/2021 | Corrections Issued | COREY HUPP |
| Deputy Wood Construction | 6/16/2021 | No Access for Inspection | JOHN HAMILTON |
| Rough-Elec/Plmb/HVAC | 6/21/2021 | Approved | COREY HUPP |
| Deputy Wood Construction | 8/27/2021 | Conditional Approval | ASHLEY THOMPSON |
| Wood Frame | 9/3/2021 | Corrections Issued | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2021 | Approved | OSVALDO PARAMO |
| Wood Frame | 12/9/2021 | Approved | OSVALDO PARAMO |
| Deputy Wood Construction | 1/14/2022 | Conditional Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 1/19/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 1/19/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| Wood Frame | 1/19/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Insulation | 2/9/2022 | Corrections Issued | COREY HUPP |
| BUILDING-Rough-Frame | 2/14/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Insulation | 2/14/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| MERV13>=Rough | 2/14/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Insulation | 2/24/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Wood Frame | 2/24/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Insulation | 3/8/2022 | Approved | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 3/8/2022 | Approved | CRAIG VAUGHAN |
| Wood Frame | 3/8/2022 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 4/4/2022 | Approved | RUBEN SALAS |
| Drywall Nailing | 4/6/2022 | Approved | AMY COLIN |
| Shower Pan | 5/17/2022 | Corrections Issued | AMY COLIN |
| Interior/Exterior Lathing | 5/23/2022 | Approved | AMY COLIN |
| Shower Pan | 5/23/2022 | Approved | AMY COLIN |
| BUILDING-Rough-Frame | 12/8/2022 | Approved | AMY COLIN |
| ELECTRICAL-Final | 12/8/2022 | Corrections Issued | AMY COLIN |
| Final | 12/8/2022 | Corrections Issued | AMY COLIN |
| Green Building Final | 12/8/2022 | Corrections Issued | AMY COLIN |
| Green Building Rough | 12/8/2022 | Approved | AMY COLIN |
| HVAC-Final | 12/8/2022 | Corrections Issued | AMY COLIN |
| MERV13>=Final | 12/8/2022 | Corrections Issued | AMY COLIN |
| MERV13>=Rough | 12/8/2022 | Approved | AMY COLIN |
| PLUMBING-Final | 12/8/2022 | Approved | AMY COLIN |
| SGSOV-Seismic Gas S/O Valve | 12/8/2022 | SGSOV Not Ready | AMY COLIN |
| Service/Power Release | 12/8/2022 | Not Ready for Inspection | AMY COLIN |
| Smoke Detectors | 12/8/2022 | Approved | AMY COLIN |
| Final | 3/14/2023 | Corrections Issued | AMY COLIN |
| Green Building Final | 3/14/2023 | Approved | AMY COLIN |
| MERV13>=Final | 3/14/2023 | Approved | AMY COLIN |
| SGSOV-Seismic Gas S/O Valve | 3/14/2023 | SGSOV Approved | AMY COLIN |
| Service/Power Release | 3/14/2023 | Approved | AMY COLIN |
| Final | 6/2/2023 | OK to Issue CofO | AMY COLIN |