1208 N ARDMORE AVE 90029

Certificate Information: 1208 N ARDMORE AVE 90029

Application / Permit
19010-10000-05556
Plan Check / Job No.
B19LA25980
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 40'X19' (760 SQFT) DETACHED ACCESSORY DWELLING UNIT PER AB494 AND SB229 CONSISTING OF: TWO BEDROOM WITH CLOSET ONE FULL BATHROOM KITCHEN, DINING, LIVING ROOM, AND STACKABLE WASHER AND DRYER
Permit Issued
Issued on 2/18/2020
Issuing Office
San Pedro
Current Status
CofO Issued on 11/20/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/10/2019 APPLICANT
Assigned to Plan Check Engineer 12/18/2019 AMIR DANAI
Corrections Issued 12/24/2019 AMIR DANAI
Quality Review Completed 1/14/2020 JASON HEALEY
Building Plans Picked Up 1/17/2020 APPLICANT
Green Plans Picked Up 1/24/2020 APPLICANT
Plan Check Approved 2/14/2020 AMIR DANAI
Issued 2/18/2020 LADBS
CofO in Progress 11/17/2020 BRIAN SULLIVAN
Permit Finaled 11/20/2020 DEROLD HAUFF
CofO Issued 11/20/2020 DEROLD HAUFF
Permit Finaled 11/20/2020 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/21/2020 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 1/21/2020 ELAINE LEI
Sewer availability Cleared 1/21/2020 ELAINE LEI
Hydrant and Access approval Cleared 1/30/2020 GILBERT URREA
Construction near power lines Cleared 2/5/2020 OSCAR CASTRO
Construction within easement Cleared 2/5/2020 OSCAR CASTRO
Low Impact Development Cleared 2/10/2020 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 2/10/2020 EMIL KYUPELYAN
Green Code Cleared 2/12/2020 COLIN LOREDO

Contact Information

Contractor Divine Grace Construction; Lic. No.: 933197-B 9672 ALONDRA BLVD      BELLFLOWER, CA 90706
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVENUE      LONG BEACH, CA 90813

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/10/2020 Not Ready for Inspection BRIAN SULLIVAN
Underground Mechanical 4/15/2020 Corrections Issued BRIAN SULLIVAN
Footing/Foundation/Slab 4/17/2020 Not Ready for Inspection BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 4/20/2020 Approved BRIAN SULLIVAN
Special/Order Compliance 4/22/2020 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 5/27/2020 Corrections Issued JOSEPH MCGARRY
Green Building Rough 5/27/2020 Not Ready for Inspection JOSEPH MCGARRY
Underground Mechanical 5/27/2020 Not Ready for Inspection JOSEPH MCGARRY
Verify Sprinkler Sign Off 5/27/2020 Not Ready for Inspection JOSEPH MCGARRY
ELECTRICAL-Rough 6/3/2020 Corrections Issued BRIAN SULLIVAN
Green Building Rough 6/3/2020 Approved BRIAN SULLIVAN
HVAC-Rough 6/3/2020 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 6/3/2020 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Rough 6/3/2020 Corrections Issued BRIAN SULLIVAN
BUILDING-Rough-Frame 6/9/2020 Conditional Approval BRIAN SULLIVAN
ELECTRICAL-Rough 6/9/2020 Approved BRIAN SULLIVAN
PLUMBING-Rough 6/9/2020 Approved BRIAN SULLIVAN
Drywall Nailing 6/16/2020 Partial Approval CHRISTOPHER DELLEFIELD
Insulation 6/16/2020 Partial Approval CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 6/16/2020 Partial Approval CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 6/19/2020 Not Ready for Inspection BRIAN SULLIVAN
Interior/Exterior Lathing 6/22/2020 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Insulation 6/23/2020 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 6/23/2020 Partial Approval CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 8/21/2020 Approved ENRIQUE MIRELES
Drywall Nailing 8/21/2020 Approved ENRIQUE MIRELES
Final 8/21/2020 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 8/21/2020 Approved ENRIQUE MIRELES
Green Building Final 8/21/2020 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 8/21/2020 SGSOV Not Ready ENRIQUE MIRELES
Service/Power Release 8/21/2020 Not Ready for Inspection ENRIQUE MIRELES
Smoke Detectors 8/21/2020 Approved ENRIQUE MIRELES
Verify Sprinkler Sign Off 8/21/2020 Approved ENRIQUE MIRELES
ELECTRICAL-Final 9/10/2020 Not Ready for Inspection BRIAN SULLIVAN
Final 9/10/2020 Corrections Issued BRIAN SULLIVAN
HVAC-Final 9/10/2020 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Final 9/10/2020 Approved BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 9/10/2020 SGSOV Not Ready BRIAN SULLIVAN
Service/Power Release 9/10/2020 Not Ready for Inspection BRIAN SULLIVAN
ELECTRICAL-Final 10/20/2020 Not Ready for Inspection JOSEPH MCGARRY
Final 10/20/2020 Not Ready for Inspection JOSEPH MCGARRY
HVAC-Final 10/20/2020 Not Ready for Inspection JOSEPH MCGARRY
PLUMBING-Final 10/20/2020 Not Ready for Inspection JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 10/20/2020 SGSOV Not Ready JOSEPH MCGARRY
Service/Power Release 10/20/2020 Not Required JOSEPH MCGARRY
Final 11/6/2020 Corrections Issued JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 11/6/2020 SGSOV Not Ready JOSEPH MCGARRY
ELECTRICAL-Final 11/10/2020 Approved RAUL BARAJAS
Final 11/10/2020 Corrections Issued RAUL BARAJAS
HVAC-Final 11/10/2020 Approved RAUL BARAJAS
PLUMBING-Final 11/10/2020 Corrections Issued RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 11/10/2020 SGSOV Approved RAUL BARAJAS
Final 11/17/2020 OK to Issue CofO BRIAN SULLIVAN
PLUMBING-Final 11/17/2020 Approved BRIAN SULLIVAN