9416 S FIRTH BLVD 90002
Certificate Information: 9416 S FIRTH BLVD 90002
- Application / Permit
- 19010-10000-05551
- Plan Check / Job No.
- B19LA25942
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- (N) 3 STORY 39 UNIT APARTMENT TYPE VA WITH ON GRADE PARKING ONLY. TOC TIER 1
- Permit Issued
- Issued on 9/14/2020
- Issuing Office
- Current Status
- CofO Corrected on 11/13/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/9/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 12/18/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/19/2019 | HERNAN ARREOLA |
| Corrections Issued | 12/24/2019 | HERNAN ARREOLA |
| Quality Review Completed | 12/31/2019 | BILL STUTSMAN |
| Building Plans Picked Up | 1/2/2020 | APPLICANT |
| Applicant returned to address corrections | 2/21/2020 | HERNAN ARREOLA |
| Applicant returned to address corrections | 6/3/2020 | HERNAN ARREOLA |
| Green Plans Picked Up | 8/4/2020 | APPLICANT |
| Plan Check Approved | 8/26/2020 | HERNAN ARREOLA |
| Issued | 9/14/2020 | APPLICANT |
| TCO Issued (Expire Date: 04-07-2024) | 10/10/2023 | TED RIES |
| TCO Issued (Expire Date: 10-27-2024) | 4/30/2024 | ERNESTO CORRAL |
| CofO in Progress | 9/12/2024 | JAMES POWERS |
| CofO Issued-Status Void | 9/13/2024 | ERNESTO CORRAL |
| Permit Finaled-Status Void | 9/13/2024 | ERNESTO CORRAL |
| Re-Activate Permit | 11/4/2024 | ERNESTO CORRAL |
| Permit Finaled | 11/13/2024 | ERNESTO CORRAL |
| CofO Corrected | 11/13/2024 | ERNESTO CORRAL |
| Permit Finaled | 11/13/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| Address approval | Cleared | 2/6/2020 | JUAN ASHTON |
| Miscellaneous | Cleared | 2/10/2020 | ANNA VIDAL |
| Highway dedication | Cleared | 2/27/2020 | THOMAS LANG |
| Trees in Parkway | Cleared | 3/12/2020 | JOHN KIM |
| Green Code | Cleared | 6/16/2020 | NEGAR NEJAD |
| Eng Process Fee Ord 176,300 | Cleared | 7/1/2020 | RENZ SORIANO |
| Sewer availability | Cleared | 7/1/2020 | RENZ SORIANO |
| Low Impact Development | Cleared | 7/9/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 7/10/2020 | ROSA SILVA |
| Density Bonus 12.22.A.31 | Cleared | 7/21/2020 | LOUIE MILLER |
| Hydrant and Access approval | Cleared | 7/28/2020 | KURT CORRAL |
| Fire Marshall Fire Life Safety | Cleared | 8/4/2020 | WILLIAM JOHNS |
| DAS Clearance | Cleared | 8/12/2020 | WAI LAU |
| Hold | Cleared | 10/13/2020 | JASON SHEETS |
Contact Information
| Architect | Knight,, Brian Frederick; Lic. No.: C32905 | 919 PALM AVENUE SOUTH PASADENA, CA 91030 |
| Contractor | Silver Star Construction Engineering Inc; Lic. No.: 971938-B | 1614 S CENTRAL AVE GLENDALE, CA 91204 |
| Engineer | Kim,, Hosang; Lic. No.: C67288 | 10632 BALCOM AVE GRANADA HILLS, CA 91344 |
Inspector Information
| ALFREDO LOPEZ, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAMES POWERS, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/16/2020 | Approved | JAMES POWERS |
| Footing/Foundation/Slab | 1/8/2021 | Not Ready for Inspection | JAMES POWERS |
| Deputy Other (see comments) | 1/11/2021 | Partial Approval | JAMES POWERS |
| Footing/Foundation/Slab | 1/12/2021 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 1/14/2021 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 2/18/2021 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2021 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 4/6/2021 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 4/23/2021 | Conditional Approval | NICK DANERI |
| Floor/Roof Diaphrgm/Shear Wall | 4/26/2021 | Partial Approval | JONATHAN QUACH |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2021 | Not Ready for Inspection | JAMES POWERS |
| Insulation | 6/23/2021 | Partial Approval | JAMES POWERS |
| Deputy Drilled-In Anchors | 6/24/2021 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 7/9/2021 | Partial Approval | JAMES POWERS |
| Green Building Rough | 7/9/2021 | Approved | JAMES POWERS |
| Insulation | 7/9/2021 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 7/15/2021 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2021 | Approved | ERNESTO CORRAL |
| Insulation | 1/12/2022 | Partial Approval | JAMES POWERS |
| Insulation | 2/1/2022 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 2/11/2022 | Partial Approval | JAMES POWERS |
| Insulation | 2/23/2022 | Partial Approval | TED RIES |
| Interior/Exterior Lathing | 2/28/2022 | Not Ready for Inspection | JAMES POWERS |
| Interior/Exterior Lathing | 3/3/2022 | Approved | JAMES POWERS |
| Drywall Nailing | 3/11/2022 | Partial Approval | JAMES POWERS |
| Interior/Exterior Lathing | 5/3/2022 | Partial Approval | JAMES POWERS |
| Insulation | 5/18/2022 | Approved | JAMES POWERS |
| Light Gage Steel Frame | 5/25/2022 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 7/6/2022 | Approved | JAMES POWERS |
| Final | 7/27/2023 | Not Ready for Inspection | JAMES POWERS |
| Footing/Foundation/Slab | 7/27/2023 | Approved | JAMES POWERS |
| Green Building Final | 7/27/2023 | Approved | JAMES POWERS |
| SGSOV-Seismic Gas S/O Valve | 7/27/2023 | SGSOV Not Ready | JAMES POWERS |
| Smoke Detectors | 7/27/2023 | Not Ready for Inspection | JAMES POWERS |
| Verify Sprinkler Sign Off | 7/27/2023 | Not Ready for Inspection | JAMES POWERS |
| Wood Frame | 7/27/2023 | Partial Approval | JAMES POWERS |
| Final | 9/27/2023 | Not Ready for Inspection | LARRY ARNICK |
| SGSOV-Seismic Gas S/O Valve | 9/27/2023 | SGSOV Not Ready | LARRY ARNICK |
| Smoke Detectors | 9/27/2023 | Not Ready for Inspection | LARRY ARNICK |
| Verify Sprinkler Sign Off | 9/27/2023 | Not Ready for Inspection | LARRY ARNICK |
| Wood Frame | 9/27/2023 | Not Ready for Inspection | LARRY ARNICK |
| Final | 10/5/2023 | OK for TCO | JAMES POWERS |
| SGSOV-Seismic Gas S/O Valve | 10/5/2023 | SGSOV Approved | JAMES POWERS |
| Smoke Detectors | 10/5/2023 | Approved | JAMES POWERS |
| Verify Sprinkler Sign Off | 10/5/2023 | Approved | JAMES POWERS |
| Wood Frame | 10/5/2023 | Approved | JAMES POWERS |
| Final | 1/22/2024 | Not Ready for Inspection | LARRY ARNICK |
| Special/Order Compliance | 3/12/2024 | Approved | JAMES POWERS |
| Final | 8/21/2024 | Conditional Approval | LARRY ARNICK |
| Final | 9/12/2024 | OK to Issue CofO | JAMES POWERS |