717-717 1/2 W 47TH ST 90037

Certificate Information: 717-717 1/2 W 47TH ST 90037

Application / Permit
19010-10000-05550
Plan Check / Job No.
B19LA25940
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
PROPOSED 3-STORY DUPLEX AT REAR
Permit Issued
Issued on 9/18/2020
Issuing Office
Current Status
CofO Issued on 10/13/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/9/2019 APPLICANT
Green Plans Picked Up 12/17/2019 APPLICANT
Assigned to Plan Check Engineer 12/20/2019 SINA KHOSRAVI
Corrections Issued 12/28/2019 SINA KHOSRAVI
Quality Review Completed 12/29/2019 YOUNG KIM
Applicant returned to address corrections 3/25/2020 SINA KHOSRAVI
Plan Check Approved 4/8/2020 SINA KHOSRAVI
Building Plans Picked Up 4/8/2020 APPLICANT
Issued 9/18/2020 APPLICANT
CofO in Progress 10/6/2021 JOAQUIN GREENOUGH
Permit Finaled 10/13/2021 DEROLD HAUFF
CofO Issued 10/13/2021 DEROLD HAUFF
Permit Finaled 10/13/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/26/2020 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 2/26/2020 EMIL KYUPELYAN
Sewer availability Cleared 2/26/2020 EMIL KYUPELYAN
Green Code Cleared 3/9/2020 COLIN LOREDO
Low Impact Development Cleared 3/13/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 3/13/2020 THOMAS LANG
Hydrant and Access approval Cleared 3/16/2020 JOHN CONNEALLY
Frnt yard landscape/Water mgmt Cleared 3/18/2020 KENTON TRINH

Contact Information

Contractor Vickers Construction Company Inc; Lic. No.: 1008338-B 952 E 116TH STREET      LOS ANGELES, CA 90059
Engineer Salto,, Alvaro; Lic. No.: C83859 7366 W MANCHESTER AVE #B      LOS ANGELES, CA 90045
Engineer Sanchez,, Pablo Beltran; Lic. No.: C86223 1840 S GAFFEY ST 382      SAN PEDRO, CA 90731

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/16/2020 Partial Approval ROBERT MCDOWELL
Underground Mechanical 10/16/2020 Approved ROBERT MCDOWELL
Excavation/Setback/Form/Re-Bar 10/22/2020 Corrections Issued ROBERT MCDOWELL
Excavation/Setback/Form/Re-Bar 10/27/2020 Approved ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 11/24/2020 Partial Approval ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 12/21/2020 Partial Approval ROBERT MCDOWELL
Deputy Wood Construction 1/28/2021 Approved ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 1/28/2021 Approved ROBERT MCDOWELL
Deputy Wood Construction 2/2/2021 No Access for Inspection ELMER BLAND
ELECTRICAL-Rough 2/24/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
HVAC-Rough 2/24/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
PLUMBING-Rough 2/24/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 3/10/2021 Approved ROBERT MCDOWELL
ELECTRICAL-Rough 3/10/2021 Approved ROBERT MCDOWELL
Green Building Rough 3/10/2021 Not Ready for Inspection ROBERT MCDOWELL
HVAC-Rough 3/10/2021 Approved ROBERT MCDOWELL
Verify Sprinkler Sign Off 3/10/2021 Approved ROBERT MCDOWELL
Wood Frame 3/10/2021 Approved ROBERT MCDOWELL
Insulation 3/15/2021 Approved ROBERT MCDOWELL
Drywall Nailing 3/26/2021 Approved ROBERT MCDOWELL
Green Building Rough 3/26/2021 Approved ROBERT MCDOWELL
Interior/Exterior Lathing 3/26/2021 Approved ROBERT MCDOWELL
ELECTRICAL-Final 9/7/2021 Approved JOAQUIN GREENOUGH
Final 9/7/2021 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 9/7/2021 Approved JOAQUIN GREENOUGH
Gas Test 9/7/2021 Approved JOAQUIN GREENOUGH
Green Building Final 9/7/2021 Approved JOAQUIN GREENOUGH
HVAC-Final 9/7/2021 Approved JOAQUIN GREENOUGH
PLUMBING-Final 9/7/2021 Approved JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 9/7/2021 SGSOV Approved JOAQUIN GREENOUGH
Service/Power Release 9/7/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Smoke Detectors 9/7/2021 Approved JOAQUIN GREENOUGH
Final 9/17/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Service/Power Release 9/17/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Final 9/22/2021 Corrections Issued JOAQUIN GREENOUGH
Service/Power Release 9/22/2021 Approved JOAQUIN GREENOUGH
Final 10/5/2021 OK to Issue CofO JOAQUIN GREENOUGH