712 N WILTON PL 90038
Certificate Information: 712 N WILTON PL 90038
- Application / Permit
- 19010-10000-05535
- Plan Check / Job No.
- B19LA25906
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- (N) 2 STORY OFFICE BUILDING
- Permit Issued
- Issued on 4/22/2021
- Issuing Office
- Current Status
- CofO Issued on 12/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/9/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/19/2019 | HERNAN ARREOLA |
| Corrections Issued | 12/24/2019 | HERNAN ARREOLA |
| Quality Review Completed | 12/31/2019 | BILL STUTSMAN |
| Building Plans Picked Up | 1/22/2020 | APPLICANT |
| Disabled Access Plans Picked Up | 1/22/2020 | APPLICANT |
| Green Plans Picked Up | 2/26/2021 | APPLICANT |
| Plan Check Approved | 3/23/2021 | HERNAN ARREOLA |
| Issued | 4/22/2021 | APPLICANT |
| CofO in Progress | 12/12/2023 | DAVID BURKHEAD |
| Permit Finaled | 12/13/2023 | ERNESTO CORRAL |
| CofO Issued | 12/13/2023 | ERNESTO CORRAL |
| Permit Finaled | 12/13/2023 | ERNESTO CORRAL |
Permit Application Clearance Information
| "D" conditions | Cleared | 1/22/2020 | RICHARD REASER |
| Address approval | Cleared | 1/22/2020 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 1/22/2020 | THOMAS LANG |
| Hydrant and Access approval | Cleared | 1/22/2020 | JEREMY CARTER |
| Sewer availability | Cleared | 1/22/2020 | THOMAS LANG |
| ZI | Cleared | 1/22/2020 | RICHARD REASER |
| Trees in Parkway | Cleared | 2/21/2020 | ADRIAN SANCHEZ |
| Low Impact Development | Cleared | 12/24/2020 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 12/24/2020 | RENZ SORIANO |
| Highway dedication | Cleared | 1/5/2021 | JAMES MORALEZ |
| Green Code | Cleared | 2/26/2021 | AARON COSTA |
| DAS Clearance | Cleared | 3/4/2021 | CHOI YAN |
Contact Information
| Architect | Thorne,, Benjamin Brinkley; Lic. No.: C30311 | 5611 HOLLYWOOD BLVD LOS ANGELES, CA 90028 |
| Contractor | Vancrest Construction Corp; Lic. No.: 393800-B | 7171 NORTH FIGUEROA STREET LOS ANGELES, CA 90042 |
| Engineer | Daugherty,, Daniel Thomas; Lic. No.: C76588 | 31129 VIA COLINAS STE 707 WESTLAKE VILLAGE, CA 91362 |
| Engineer | Galbreath,, Sean Martin; Lic. No.: S5653 | 600 SOUTH LAKE AVE STE 308 PASADENA, CA 91106 |
Inspector Information
| DAVID BURKHEAD, (213) 482-7294 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/12/2021 | Partial Approval | DAVID BURKHEAD |
| Footing/Foundation/Slab | 8/12/2021 | Partial Approval | DAVID BURKHEAD |
| Excavation/Setback/Form/Re-Bar | 8/17/2021 | Partial Approval | DAVID BURKHEAD |
| Footing/Foundation/Slab | 8/17/2021 | Partial Approval | DAVID BURKHEAD |
| Green Building Rough | 8/27/2021 | Not Ready for Inspection | DAVID BURKHEAD |
| Verify Sprinkler Sign Off | 8/27/2021 | Not Ready for Inspection | DAVID BURKHEAD |
| Wood Frame | 8/27/2021 | Partial Inspection | DAVID BURKHEAD |
| Floor/Roof Diaphrgm/Shear Wall | 9/17/2021 | Partial Approval | DAVID BURKHEAD |
| Green Building Rough | 1/25/2022 | Not Ready for Inspection | DAVID BURKHEAD |
| Interior/Exterior Lathing | 1/25/2022 | Approved | DAVID BURKHEAD |
| Verify Sprinkler Sign Off | 1/25/2022 | Not Ready for Inspection | DAVID BURKHEAD |
| Wall Anchors | 1/25/2022 | Approved | DAVID BURKHEAD |
| Wood Frame | 1/25/2022 | Partial Inspection | DAVID BURKHEAD |
| Green Building Rough | 3/23/2022 | Approved | DANIEL MC AULIFFE |
| Verify Sprinkler Sign Off | 3/23/2022 | Approved | DANIEL MC AULIFFE |
| Wood Frame | 3/23/2022 | Approved | DANIEL MC AULIFFE |
| Insulation | 3/29/2022 | Approved | DAVID BURKHEAD |
| Drywall Nailing | 3/31/2022 | Partial Inspection | DAVID BURKHEAD |
| Drywall Nailing | 4/6/2022 | Approved | DAVID BURKHEAD |
| Excavation/Setback/Form/Re-Bar | 6/29/2022 | Partial Approval | GREGORY POMISH |
| Excavation/Setback/Form/Re-Bar | 9/13/2022 | Partial Approval | TED RIES |
| Final | 8/31/2023 | Corrections Issued | DAVID BURKHEAD |
| Footing/Foundation/Slab | 8/31/2023 | Approved | DAVID BURKHEAD |
| Green Building Final | 8/31/2023 | Not Ready for Inspection | DAVID BURKHEAD |
| SGSOV-Seismic Gas S/O Valve | 8/31/2023 | SGSOV Approved | DAVID BURKHEAD |
| Smoke Detectors | 8/31/2023 | Approved | DAVID BURKHEAD |
| Special/Order Compliance | 10/25/2023 | Approved | DAVID BURKHEAD |
| Final | 12/11/2023 | OK to Issue CofO | DAVID BURKHEAD |