1255 W 52ND ST 90037
Certificate Information: 1255 W 52ND ST 90037
- Application / Permit
- 19010-10000-05534
- Plan Check / Job No.
- B19LA25898
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-STORY 30'X21'3" ACCESSORY DWELLING UNIT PER AB 494 & SB 229
- Permit Issued
- Issued on 6/5/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/13/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/9/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/13/2019 | AMIR DANAI |
| Corrections Issued | 12/18/2019 | AMIR DANAI |
| Quality Review Completed | 12/18/2019 | JASON HEALEY |
| Building Plans Picked Up | 12/30/2019 | APPLICANT |
| Green Plans Picked Up | 4/14/2020 | APPLICANT |
| Plan Check Approved | 5/19/2020 | AMIR DANAI |
| Issued | 6/5/2020 | LADBS |
| CofO in Progress | 11/10/2020 | HORACE FULTZ |
| Permit Finaled | 11/13/2020 | DEROLD HAUFF |
| CofO Issued | 11/13/2020 | DEROLD HAUFF |
| Permit Finaled | 11/13/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/6/2020 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 1/14/2020 | JEANIE LAM |
| Sewer availability | Cleared | 1/14/2020 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 1/31/2020 | JEREMY CARTER |
| Green Code | Cleared | 4/9/2020 | VIVIAN LAO |
| Low Impact Development | Cleared | 4/28/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 5/4/2020 | JEANIE LAM |
Contact Information
| Contractor | M C Construction; Lic. No.: 1028997-B | 23280 HAMLIN ST WEST HILLS, CA 91307 |
| Engineer | Kim,, Hong Kook; Lic. No.: C64529 | 839 S MUIRFIELD RD LOS ANGELES, CA 90005 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/15/2020 | Corrections Issued | FREDDIE RIVERA |
| PLUMBING-Rough | 6/15/2020 | Partial Approval | FREDDIE RIVERA |
| Footing/Foundation/Slab | 6/18/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Rough | 6/19/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Wood Frame | 6/30/2020 | Partial Approval | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 8/3/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Rough | 8/3/2020 | Approved | ROBERT MCDOWELL |
| Wood Frame | 8/3/2020 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 8/7/2020 | Approved | SABAS ALONSO |
| Insulation | 8/7/2020 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 8/7/2020 | Partial Approval | SABAS ALONSO |
| Drywall Nailing | 8/12/2020 | Approved | SABAS ALONSO |
| Green Building Rough | 8/12/2020 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 8/12/2020 | Approved | SABAS ALONSO |
| Shower Pan | 8/12/2020 | Approved | SABAS ALONSO |
| Underground Mechanical | 9/3/2020 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 9/30/2020 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Final | 9/30/2020 | Approved | ROBERT MCDOWELL |
| Final | 9/30/2020 | Conditional Approval | ROBERT MCDOWELL |
| Green Building Final | 9/30/2020 | Approved | ROBERT MCDOWELL |
| HVAC-Final | 9/30/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Final | 9/30/2020 | Approved | ROBERT MCDOWELL |
| SGSOV-Seismic Gas S/O Valve | 9/30/2020 | SGSOV Approved | ROBERT MCDOWELL |
| Service/Power Release | 9/30/2020 | Approved | ROBERT MCDOWELL |
| Smoke Detectors | 9/30/2020 | Approved | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 9/30/2020 | Approved | ROBERT MCDOWELL |