6559 S BRYNHURST AVE 90043

Certificate Information: 6559 S BRYNHURST AVE 90043

Application / Permit
19010-10000-05509
Plan Check / Job No.
B19LA25847
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
CONSTRUCT A NEW 4-STORY APARTMENT, 4 STORIES TYPE IIIA ON 1 STORY TYPE IA PODIUM. UTILIZE TOC TIER 3. PROPOSE TOP 4 STORY ARE FACTORY BUILT HOUSING (SHIPPING CONTAINER) 1 OF 2
Permit Issued
Issued on 12/10/2020
Issuing Office
Current Status
CofO Issued on 11/26/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/6/2019 APPLICANT
Assigned to Plan Check Engineer 1/2/2020 VU NGUYEN
Corrections Issued 1/28/2020 VU NGUYEN
Quality Review Completed 2/11/2020 ALLEN MANALANSAN
Building Plans Picked Up 2/13/2020 APPLICANT
Disabled Access Plans Picked Up 2/13/2020 APPLICANT
Applicant returned to address corrections 3/17/2020 VU NGUYEN
Applicant returned to address corrections 3/26/2020 VU NGUYEN
Applicant returned to address corrections 4/9/2020 VU NGUYEN
Applicant returned to address corrections 7/7/2020 VU NGUYEN
Green Plans Picked Up 11/10/2020 APPLICANT
Plan Check Approved 11/19/2020 VU NGUYEN
Issued 12/10/2020 APPLICANT
CofO in Progress 11/26/2024 JAMES POWERS
Permit Finaled 11/26/2024 ERNESTO CORRAL
CofO Issued 11/26/2024 ERNESTO CORRAL
Permit Finaled 11/26/2024 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 2/25/2020 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 2/25/2020 ERIK BEASLEY
Highway dedication Cleared 2/25/2020 ERIK BEASLEY
Permit Cleared 2/25/2020 ERIK BEASLEY
Sewer availability Cleared 2/27/2020 GUILLERMO PETRA
Trees in Parkway Cleared 3/12/2020 JOHN KIM
Hydrant and Access approval Cleared 4/22/2020 GEORGE SUCHAND
CPC Cleared 6/3/2020 SHEILA GERSHON
Frnt yard landscape/Water mgmt Cleared 6/3/2020 SHEILA GERSHON
Miscellaneous Cleared 6/3/2020 SHEILA GERSHON
Opn space landscape/Water mgmt Cleared 6/3/2020 SHEILA GERSHON
Redevelopment Project Area Cleared 6/3/2020 SHEILA GERSHON
Fire Marshall Fire Life Safety Cleared 6/19/2020 VIDAL GARCIA
Density Bonus 12.22.A.31 Cleared 6/22/2020 KENNETH LE
Green Code Cleared 6/25/2020 VIVIAN LAO
Low Impact Development Cleared 7/8/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 7/13/2020 CECILIO NAVARRO
DAS Clearance Cleared 8/5/2020 ELIZABETH TOMS
Building over 3-story or 36-ft Cleared 8/26/2020 CALOSHA APPROVED

Contact Information

Architect Hwangbo,, James Sungkyum; Lic. No.: C37990 421 S LA FAYETTE PARK PLACE #604      LOS ANGELES, CA 90057
Contractor Forma Builders; Lic. No.: 1063990-B 13319 POWAY ROAD #123      POWAY, CA 92064
Engineer Babayan,, Raffi Samuel; Lic. No.: C72168 7718 DAY STREET      LOS ANGELES, CA 91042
Engineer Garcia,, Lionel Jesus; Lic. No.: C58475 24702 NARBONNE AVE      LOMITA, CA 90717
Engineer Kang,, Danniel; Lic. No.: S6242 633 E 223RD ST B      CARSON, CA 90745

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/19/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 1/19/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/20/2021 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 2/12/2021 Partial Approval JAMES POWERS
Green Building Rough 2/25/2021 Not Ready for Inspection JAMES POWERS
Reinforced Masonry Frame 2/25/2021 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 2/25/2021 Not Ready for Inspection JAMES POWERS
Excavation/Setback/Form/Re-Bar 3/2/2021 Partial Approval JAMES POWERS
Green Building Rough 3/2/2021 Approved JAMES POWERS
Verify Sprinkler Sign Off 3/2/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 3/3/2021 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 3/8/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 3/8/2021 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 3/11/2021 Not Ready for Inspection JAMES POWERS
Excavation/Setback/Form/Re-Bar 3/12/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 3/12/2021 Partial Approval JAMES POWERS
Reinforced Masonry Frame 3/12/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 3/12/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/15/2021 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 3/17/2021 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 3/18/2021 Not Ready for Inspection LANNY MERRICK
Reinforced Masonry Frame 3/30/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 3/30/2021 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 4/9/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 4/9/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 4/12/2021 Partial Approval JAMES POWERS
Reinforced Masonry Frame 4/13/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 4/14/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 4/16/2021 Partial Approval JAMES POWERS
Reinforced Masonry Frame 4/16/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 4/21/2021 Partial Approval JAMES POWERS
Reinforced Masonry Frame 4/21/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 4/21/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Masonry 4/22/2021 Conditional Approval RAFAEL ESPINOZA
Light Gage Steel Frame 4/23/2021 Not Ready for Inspection JOEY BUCHANAN
Reinforced Masonry Frame 4/23/2021 Not Ready for Inspection JOEY BUCHANAN
Verify Sprinkler Sign Off 4/23/2021 Not Ready for Inspection JOEY BUCHANAN
Masonry Wall/Backfill 4/24/2021 Off-Hour Fees Due
Masonry Wall/Backfill 4/24/2021 Partial Approval DAVID BURKHEAD
Deputy Reinf. Masonry 4/28/2021 Approved JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 4/28/2021 Not Ready for Inspection JOEY BUCHANAN
Deputy Reinf. Masonry 4/29/2021 Conditional Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 4/29/2021 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 4/30/2021 Approved JOEY BUCHANAN
Deputy Reinf. Masonry 5/7/2021 Partial Approval JAMES POWERS
Masonry Wall/Backfill 5/10/2021 Partial Approval JAMES POWERS
Reinforced Masonry Frame 5/10/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 5/10/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Masonry 5/11/2021 Conditional Approval LEOPOLDO MENDOZA
Deputy Reinf. Masonry 5/14/2021 Partial Approval JAMES POWERS
Reinforced Masonry Frame 5/14/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 5/14/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Masonry 5/17/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 6/4/2021 Partial Approval JAMES POWERS
Reinforced Masonry Frame 6/4/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 6/4/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 7/12/2021 Conditional Approval DAVID TSAU
Deputy Reinf. Concrete 7/29/2021 Partial Approval JAMES POWERS
Reinforced Masonry Frame 8/13/2021 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 8/13/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 8/20/2021 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 8/20/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 8/25/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 8/25/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 8/25/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 8/26/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/30/2021 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 9/20/2021 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 9/24/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 9/27/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 9/27/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 9/28/2021 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 10/1/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 10/21/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Steel/Welding 10/22/2021 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 10/26/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 10/27/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 10/28/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 10/29/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 11/2/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 11/3/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 11/4/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 11/5/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 11/10/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 11/12/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 11/16/2021 Conditional Approval TED RIES
Wood Frame 11/17/2021 Not Ready for Inspection DAVID BURKHEAD
Deputy Steel/Welding 11/18/2021 Conditional Approval TED RIES
Deputy Steel/Welding 11/19/2021 Conditional Approval TED RIES
Deputy Steel/Welding 11/23/2021 Conditional Approval TED RIES
Deputy Steel/Welding 11/24/2021 Conditional Approval ERNESTO CORRAL
Deputy Steel/Welding 11/29/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 11/30/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 12/1/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 12/2/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 12/3/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 12/8/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 12/9/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 12/10/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 12/16/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 12/17/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 12/20/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 12/21/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 12/22/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 12/23/2021 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 1/4/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 1/4/2022 Partial Approval JAMES POWERS
Reinforced Concrete Frame 1/4/2022 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 1/4/2022 Not Ready for Inspection JAMES POWERS
Deputy Steel/Welding 1/5/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/6/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 1/6/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 1/7/2022 Approved TED RIES
Deputy Steel/Welding 1/10/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 1/11/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 1/12/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 1/13/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 1/14/2022 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 1/21/2022 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 1/26/2022 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 1/27/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 1/27/2022 Partial Approval JAMES POWERS
Wood Frame 2/4/2022 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 2/10/2022 Partial Approval JAMES POWERS
Wood Frame 2/11/2022 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 2/14/2022 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 2/15/2022 Partial Approval JAMES POWERS
Pre-Inspection 1/20/2023 Partial Approval JAMES POWERS
Masonry Wall/Backfill 2/17/2023 Partial Approval JAMES POWERS
Pre-Inspection 4/6/2023 Partial Approval JAMES POWERS
Masonry Wall/Backfill 4/26/2023 Partial Inspection JAMES POWERS
Wood Frame 5/9/2023 Partial Approval JAMES POWERS
Insulation 5/15/2023 Partial Approval GREGORY POMISH
Pre-Inspection 6/1/2023 Not Ready for Inspection LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 6/9/2023 Partial Approval JAMES POWERS
Pre-Inspection 6/12/2023 Corrections Issued LARRY ARNICK
Drywall Nailing 7/13/2023 Corrections Issued LARRY ARNICK
Drywall Nailing 7/19/2023 Partial Approval JAMES POWERS
Wood Frame 7/21/2023 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 7/26/2023 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/18/2023 Not Ready for Inspection JAMES POWERS
Deputy Drilled-In Anchors 9/25/2023 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/27/2023 Partial Approval JAMES POWERS
Masonry Wall/Backfill 9/27/2023 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 9/27/2023 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Masonry 10/2/2023 Partial Approval JAMES POWERS
Insulation 10/2/2023 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 10/3/2023 Partial Approval JAMES POWERS
Drywall Nailing 10/6/2023 Partial Approval JAMES POWERS
Insulation 10/10/2023 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/20/2023 Not Ready for Inspection JAMES POWERS
Wall Anchors 10/26/2023 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 11/1/2023 Partial Approval JAMES POWERS
Drywall Nailing 11/8/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/4/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 4/16/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 4/18/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 4/24/2024 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 5/2/2024 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 6/20/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 7/5/2024 Partial Approval JAMES POWERS
Final 11/8/2024 OK for TCO JAMES POWERS
Footing/Foundation/Slab 11/8/2024 Approved JAMES POWERS
Green Building Final 11/8/2024 Approved JAMES POWERS
Reinforced Concrete Frame 11/8/2024 Approved JAMES POWERS
Reinforced Masonry Frame 11/8/2024 Approved JAMES POWERS
SGSOV-Seismic Gas S/O Valve 11/8/2024 SGSOV No Gas JAMES POWERS
Smoke Detectors 11/8/2024 Approved JAMES POWERS
Verify Sprinkler Sign Off 11/8/2024 Approved JAMES POWERS
Deputy Drilled-In Anchors 11/26/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/26/2024 Partial Approval JAMES POWERS
Final 11/26/2024 OK to Issue CofO JAMES POWERS