4262 S HARVARD BLVD 90062

Certificate Information: 4262 S HARVARD BLVD 90062

Application / Permit
19010-10000-05496
Plan Check / Job No.
B19LA25831
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
19' x 22' NEW 1 STORY ACCESSORY DWELLING UNIT PER AB 494 & SB 229
Permit Issued
Issued on 9/24/2020
Issuing Office
Current Status
Issued on 9/24/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/6/2019 APPLICANT
Assigned to Plan Check Engineer 12/13/2019 CRYSTEL MAALOUF
Corrections Issued 12/16/2019 CRYSTEL MAALOUF
Quality Review Completed 12/17/2019 JASON HEALEY
Building Plans Picked Up 12/23/2019 APPLICANT
Green Plans Picked Up 1/22/2020 APPLICANT
Applicant returned to address corrections 2/13/2020 CRYSTEL MAALOUF
Plan Check Approved 2/19/2020 CRYSTEL MAALOUF
Issued 9/24/2020 APPLICANT

Permit Application Clearance Information

Address approval Cleared 12/23/2019 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 12/23/2019 EMIL KYUPELYAN
Roof/Waste drainage to street Cleared 12/23/2019 EMIL KYUPELYAN
Sewer availability Cleared 12/23/2019 EMIL KYUPELYAN
Green Code Cleared 2/11/2020 CRYSTEL MAALOUF

Contact Information

Contractor Levet Inc; Lic. No.: 1027447-B 1110 SONORA AVE #101      GLENDALE, CA 91201
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/15/2020 Partial Approval ROBERT MCDOWELL
Footing/Foundation/Slab 10/21/2020 Approved ROBERT MCDOWELL
Wood Frame 12/2/2020 Approved ROBERT MCDOWELL
Wood Frame 12/7/2020 Not Ready for Inspection FREDDIE RIVERA
Sewer 1/15/2021 Approved ROBERT MCDOWELL
Underground Mechanical 1/15/2021 Approved ROBERT MCDOWELL
ELECTRICAL-Rough 2/4/2021 Approved ROBERT MCDOWELL
HVAC-Rough 2/4/2021 Approved ROBERT MCDOWELL
PLUMBING-Rough 2/4/2021 Approved ROBERT MCDOWELL
Wood Frame 2/4/2021 Approved ROBERT MCDOWELL
Insulation 2/8/2021 Approved ROBERT MCDOWELL
Drywall Nailing 2/18/2021 Approved DAVID FEILER
Interior/Exterior Lathing 3/3/2021 Approved ROBERT MCDOWELL
SGSOV-Seismic Gas S/O Valve 3/25/2021 SGSOV Not Ready ROBERT MCDOWELL
Verify Sprinkler Sign Off 3/25/2021 Not Ready for Inspection ROBERT MCDOWELL
Pre-Inspection 4/1/2021 Corrections Issued ROBERT MCDOWELL
BUILDING-Rough-Frame 4/7/2021 Conditional Approval ROBERT MCDOWELL
ELECTRICAL-Final 4/7/2021 Approved ROBERT MCDOWELL
Final 4/7/2021 Not Ready for Inspection ROBERT MCDOWELL
Green Building Final 4/7/2021 Approved ROBERT MCDOWELL
Green Building Rough 4/7/2021 Approved ROBERT MCDOWELL
HVAC-Final 4/7/2021 Approved ROBERT MCDOWELL
PLUMBING-Final 4/7/2021 Approved ROBERT MCDOWELL
SGSOV-Seismic Gas S/O Valve 4/7/2021 SGSOV Approved ROBERT MCDOWELL
Smoke Detectors 4/7/2021 Approved ROBERT MCDOWELL
Verify Sprinkler Sign Off 4/7/2021 Conditional Approval ROBERT MCDOWELL
BUILDING-Rough-Frame 3/7/2023 Approved STUART CHAPMAN
Final 3/7/2023 Corrections Issued STUART CHAPMAN
Service/Power Release 3/7/2023 Not Ready for Inspection STUART CHAPMAN
Verify Sprinkler Sign Off 3/7/2023 Approved STUART CHAPMAN