454 E 27TH ST 90011
Certificate Information: 454 E 27TH ST 90011
- Application / Permit
- 19010-10000-05493
- Plan Check / Job No.
- B19LA25827
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED 1-STORY ACCESSORY DWELLING UNIT PER AB 494 AND SB 229.
- Permit Issued
- Issued on 1/22/2020
- Issuing Office
- Metro
- Current Status
- Issued on 1/22/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/6/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/13/2019 | MICHAEL LOPEZ |
| Corrections Issued | 12/17/2019 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 12/31/2019 | MICHAEL LOPEZ |
| Plan Check Approved | 1/9/2020 | MICHAEL LOPEZ |
| Issued | 1/22/2020 | LADBS |
Permit Application Clearance Information
| Address approval | Cleared | 12/23/2019 | EMIL KYUPELYAN |
| Community Plan Implem. Overlay | Cleared | 12/23/2019 | TERRI OSBORNE |
| Eng Process Fee Ord 176,300 | Cleared | 12/23/2019 | EMIL KYUPELYAN |
| Roof/Waste drainage to street | Cleared | 12/23/2019 | EMIL KYUPELYAN |
| Sewer availability | Cleared | 12/23/2019 | EMIL KYUPELYAN |
| Low Impact Development | Cleared | 1/2/2020 | ORVAL HERNANDEZ-MARCI |
| Hydrant and Access approval | Cleared | 1/7/2020 | JEREMY CARTER |
Contact Information
| Contractor | Levet Inc; Lic. No.: 1027447-B | 1110 SONORA AVE #101 GLENDALE, CA 91201 |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/24/2020 | Corrections Issued | JOAQUIN GREENOUGH |
| METHANE-Barrier | 2/24/2020 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| METHANE-Subgrade | 2/24/2020 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 2/24/2020 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 3/19/2020 | Partial Approval | JOAQUIN GREENOUGH |
| Green Building Rough | 3/19/2020 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| METHANE-Rough | 3/19/2020 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 3/19/2020 | Partial Approval | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 3/19/2020 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 4/8/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 4/8/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| METHANE-Rough | 4/8/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 4/8/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 4/17/2020 | Conditional Approval | FREDDIE RIVERA |
| ELECTRICAL-Rough | 4/17/2020 | Approved | FREDDIE RIVERA |
| Green Building Rough | 4/17/2020 | Conditional Approval | FREDDIE RIVERA |
| METHANE-Rough | 4/17/2020 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 4/17/2020 | Approved | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 4/17/2020 | Approved | FREDDIE RIVERA |
| Insulation | 4/27/2020 | Not Ready for Inspection | SABAS ALONSO |
| Insulation | 4/30/2020 | Corrections Issued | SABAS ALONSO |
| Interior/Exterior Lathing | 4/30/2020 | Not Ready for Inspection | SABAS ALONSO |
| Insulation | 5/4/2020 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 5/4/2020 | Approved | SABAS ALONSO |
| Drywall Nailing | 5/12/2020 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 6/12/2020 | Approved | ROBERT MCDOWELL |
| Shower Pan | 6/12/2020 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 7/8/2020 | Approved | FREDDIE RIVERA |
| Final | 7/8/2020 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 7/8/2020 | Approved | FREDDIE RIVERA |
| Green Building Final | 7/8/2020 | Approved | FREDDIE RIVERA |
| Green Building Rough | 7/8/2020 | Approved | FREDDIE RIVERA |
| METHANE-Barrier | 7/8/2020 | Approved | FREDDIE RIVERA |
| METHANE-Subgrade | 7/8/2020 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 7/8/2020 | SGSOV Approved | FREDDIE RIVERA |
| Service/Power Release | 7/8/2020 | Approved | FREDDIE RIVERA |
| Smoke Detectors | 7/8/2020 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 7/16/2020 | Approved | ROBERT MCDOWELL |
| Final | 7/16/2020 | Corrections Issued | ROBERT MCDOWELL |
| HVAC-Final | 7/16/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Final | 7/16/2020 | Approved | ROBERT MCDOWELL |