2519 N SUNDOWN DR 90065
Certificate Information: 2519 N SUNDOWN DR 90065
- Application / Permit
- 19010-10000-05463
- Plan Check / Job No.
- B19LA25721
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SINGLE FAMILY DWELLING W/ATTACHED CARPORT PER ZA-2018-4256-ZAD-SPP (NFPA 13D THRU OUT)
- Permit Issued
- Issued on 4/5/2022
- Issuing Office
- Current Status
- CofO Issued on 4/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/5/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/2/2020 | MIGUEL JIMENEZ |
| Corrections Issued | 1/14/2020 | MIGUEL JIMENEZ |
| Quality Review Completed | 1/24/2020 | BILL STUTSMAN |
| Green Plans Picked Up | 8/7/2020 | APPLICANT |
| Applicant returned to address corrections | 8/11/2020 | AUNG SOE |
| Applicant returned to address corrections | 10/14/2021 | AUNG SOE |
| Applicant returned to address corrections | 10/25/2021 | AUNG SOE |
| Plan Check Approved | 10/26/2021 | AUNG SOE |
| Issued | 4/5/2022 | APPLICANT |
| Building Plans Picked Up | 4/7/2022 | APPLICANT |
| CofO in Progress | 4/18/2024 | HAMIK HARTOUNIAN |
| CofO Issued | 4/22/2024 | DEROLD HAUFF |
| Permit Finaled | 4/22/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 2/6/2020 | RIDWAN HARDY |
| Green Code | Cleared | 7/30/2020 | KHEDER ALRAZAA |
| Address approval | Cleared | 8/5/2020 | JEANIE LAM |
| BHO/Hillside ordinance | Cleared | 8/5/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 8/5/2020 | JEANIE LAM |
| Sewer availability | Cleared | 8/5/2020 | JEANIE LAM |
| Grading Pre-Inspection | Cleared | 9/1/2020 | PATRICK MISCHLICH |
| Trees in Parkway | Cleared | 9/10/2020 | JOHN KIM |
| Hydrant and Access approval | Cleared | 10/21/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 10/30/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 10/30/2020 | JEANIE LAM |
| Permit | Cleared | 12/28/2020 | JEANIE LAM |
| BHO/Hillside ordinance | Cleared | 6/24/2021 | THAN WIN |
| BHO/Hillside ordinance | Cleared | 8/19/2021 | ARMEN MEHRABIAN |
| Specific Plan | Cleared | 9/20/2021 | RICHARD REASER |
| ZI | Cleared | 9/20/2021 | RICHARD REASER |
Contact Information
| Contractor | Opus Builders Inc; Lic. No.: 1059646-B | 5244 VINELAND AVENUE NORTH HOLLYWOOD, CA 91601 |
| Engineer | Hansen,, Neil Christian; Lic. No.: L9027 | 135 N LAMER STREET APT A BURBANK, CA 91506 |
| Engineer | Kowalski,, Michael Thomas; Lic. No.: C44029 | 19556 TUMBLEWEED TR DESERT HOT SPRINGS, CA 92241 |
| Engineer | Marte,, Julie Anne Dayanghirang; Lic. No.: C84066 | PO BOX 1406 GLENDORA, CA 91740 |
| Engineer | Robles,, Gustavo; Lic. No.: C66797 | 981 W ARROW HWY 191 SAN DIMAS, CA 91773 |
| Engineer | Valencia,, Byron Steve; Lic. No.: C87372 | 13719 OXNARD ST 101 VAN NUYS, CA 91401 |
| Geologist | Robles,, Gustavo; Lic. No.: EG2422 | 981 W. ARROW HIGHWAY #191 SAN DIMAS, CA 91773 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/8/2022 | Partial Inspection | HAMIK HARTOUNIAN |
| Piling/Pier/Caisson | 5/31/2022 | Not Ready for Inspection | SCOTT FINNILA |
| Footing/Foundation/Slab | 6/2/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Deputy Reinf. Concrete | 6/7/2022 | Conditional Approval | HAMIK HARTOUNIAN |
| Piling/Pier/Caisson | 6/20/2022 | Approved | HAMIK HARTOUNIAN |
| Deputy Reinf. Concrete | 6/27/2022 | Conditional Approval | HAMIK HARTOUNIAN |
| Piling/Pier/Caisson | 6/30/2022 | Partial Approval | HAMIK HARTOUNIAN |
| Deputy Reinf. Concrete | 7/5/2022 | Conditional Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 8/8/2022 | Partial Approval | HAMIK HARTOUNIAN |
| Pre-Inspection | 10/3/2022 | Partial Inspection | HAMIK HARTOUNIAN |
| Deputy Drilled-In Anchors | 1/27/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| Deputy Steel/Welding | 2/13/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 2/15/2023 | Partial Approval | HAMIK HARTOUNIAN |
| Underground Mechanical | 2/15/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 5/1/2023 | Corrections Issued | SCOTT FINNILA |
| Green Building Rough | 5/1/2023 | Not Ready for Inspection | SCOTT FINNILA |
| Verify Sprinkler Sign Off | 5/1/2023 | Not Ready for Inspection | SCOTT FINNILA |
| BUILDING-Rough-Frame | 5/8/2023 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2023 | Partial Approval | SCOTT FINNILA |
| Verify Sprinkler Sign Off | 5/8/2023 | Not Ready for Inspection | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/18/2023 | Partial Approval | SCOTT FINNILA |
| HVAC-Rough | 6/28/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Rough | 7/6/2023 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Rough | 8/9/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| Deputy Wood Construction | 8/30/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 8/31/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/31/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Rough | 8/31/2023 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 8/31/2023 | Approved | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 8/31/2023 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 9/5/2023 | Conditional Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2023 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 9/5/2023 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 9/19/2023 | Conditional Approval | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 9/19/2023 | Partial Approval | BRIAN SULLIVAN |
| Sewer | 9/19/2023 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 9/26/2023 | Approved | HAMIK HARTOUNIAN |
| Insulation | 9/26/2023 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 9/26/2023 | Partial Approval | HAMIK HARTOUNIAN |
| Drywall Nailing | 10/16/2023 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 10/16/2023 | Partial Approval | BRENDAN MORELLI |
| Interior/Exterior Lathing | 11/22/2023 | Approved | OSVALDO PARAMO |
| Shower Pan | 11/22/2023 | Approved | OSVALDO PARAMO |
| Special/Order Compliance | 3/5/2024 | Partial Inspection | HAMIK HARTOUNIAN |
| Final | 4/12/2024 | Not Ready for Inspection | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 4/12/2024 | Approved | JOSEPH MCGARRY |
| Green Building Final | 4/12/2024 | Not Ready for Inspection | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 4/12/2024 | SGSOV Not Required | JOSEPH MCGARRY |
| Service/Power Release | 4/12/2024 | Not Required | JOSEPH MCGARRY |
| Smoke Detectors | 4/12/2024 | Approved | JOSEPH MCGARRY |
| Final | 4/16/2024 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Green Building Final | 4/16/2024 | Approved | HAMIK HARTOUNIAN |
| Service/Power Release | 4/16/2024 | Approved | HAMIK HARTOUNIAN |