803 W 140TH ST 90247

Certificate Information: 803 W 140TH ST 90247

Application / Permit
19010-10000-05420
Plan Check / Job No.
B19LA25553
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW 22' X 22'8" (499 SF), ONE STORY, TYPE "V" RECREATION ROOM WITH 1/2 BATHROOM PER WFPP DESIGN.
Permit Issued
Issued on 5/26/2020
Issuing Office
Metro
Current Status
CofO Issued on 8/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/3/2019 APPLICANT
Assigned to Plan Check Engineer 12/13/2019 STARR CHEN
Corrections Issued 12/13/2019 STARR CHEN
Quality Review Completed 12/17/2019 JASON HEALEY
Building Plans Picked Up 12/23/2019 APPLICANT
Green Plans Picked Up 1/28/2020 APPLICANT
Plan Check Approved 3/17/2020 STARR CHEN
Issued 5/26/2020 LADBS
CofO in Progress 6/16/2022 JOHN KLARIN
Permit Finaled 8/23/2022 DEROLD HAUFF
CofO Issued 8/23/2022 DEROLD HAUFF
Permit Finaled 8/23/2022 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/28/2020 ERIK BEASLEY
Hydrant and Access approval Cleared 1/28/2020 GEORGE SUCHAND
Roof/Waste drainage to street Cleared 1/28/2020 ERIK BEASLEY
Sewer availability Cleared 1/28/2020 ERIK BEASLEY
Green Code Cleared 2/13/2020 VIVIAN LAO
Low Impact Development Cleared 3/10/2020 JORGE MEJIA LEMUS

Contact Information

Contractor R D B & Sons Construction Inc; Lic. No.: 960735-B 714 W 144TH STREET      GARDENA, CA 90247

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/2/2020 Corrections Issued JOHN KLARIN
METHANE-Barrier 7/2/2020 Not Ready for Inspection JOHN KLARIN
METHANE-Subgrade 7/2/2020 Corrections Issued JOHN KLARIN
Footing/Foundation/Slab 10/19/2020 Not Ready for Inspection DAVID FEILER
METHANE-Barrier 10/19/2020 Not Ready for Inspection DAVID FEILER
METHANE-Subgrade 10/19/2020 Corrections Issued DAVID FEILER
Footing/Foundation/Slab 10/27/2020 Corrections Issued EUGENE CASSIDY
METHANE-Barrier 10/27/2020 Not Ready for Inspection EUGENE CASSIDY
METHANE-Subgrade 10/27/2020 Not Ready for Inspection EUGENE CASSIDY
Special/Order Compliance 3/25/2021 Corrections Issued WILLIAM ROSE
Excavation/Setback/Form/Re-Bar 4/27/2021 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 7/9/2021 Corrections Issued EUGENE CASSIDY
METHANE-Barrier 7/9/2021 Approved EUGENE CASSIDY
METHANE-Subgrade 7/9/2021 Approved EUGENE CASSIDY
Footing/Foundation/Slab 7/16/2021 Approved EUGENE CASSIDY
PLUMBING-Rough 8/13/2021 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 9/30/2021 Corrections Issued EUGENE CASSIDY
Green Building Rough 9/30/2021 Not Ready for Inspection EUGENE CASSIDY
METHANE-Rough 9/30/2021 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 9/30/2021 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 10/7/2021 Not Ready for Inspection JOHN KLARIN
Green Building Rough 10/7/2021 Not Ready for Inspection JOHN KLARIN
BUILDING-Rough-Frame 11/12/2021 Corrections Issued EUGENE CASSIDY
Green Building Rough 11/12/2021 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 11/18/2021 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 11/18/2021 Partial Approval EUGENE CASSIDY
Green Building Rough 11/18/2021 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 11/18/2021 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 11/24/2021 Approved JOHN KLARIN
Green Building Rough 11/24/2021 Approved JOHN KLARIN
Insulation 1/14/2022 Corrections Issued EUGENE CASSIDY
Interior/Exterior Lathing 1/14/2022 Not Ready for Inspection EUGENE CASSIDY
Insulation 1/25/2022 Approved ALIZAH MAYAGOITIA
Drywall Nailing 2/7/2022 Approved EUGENE CASSIDY
Interior/Exterior Lathing 2/7/2022 Approved EUGENE CASSIDY
Final 3/17/2022 Corrections Issued JOHN KLARIN
Green Building Final 3/17/2022 Corrections Issued JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 3/17/2022 SGSOV Approved JOHN KLARIN
Service/Power Release 3/17/2022 Not Ready for Inspection JOHN KLARIN
Smoke Detectors 3/17/2022 Approved JOHN KLARIN
Final 4/8/2022 Not Ready for Inspection JOHN KLARIN
Green Building Final 4/8/2022 Not Ready for Inspection JOHN KLARIN
Service/Power Release 4/8/2022 Not Ready for Inspection JOHN KLARIN
Final 4/26/2022 Not Ready for Inspection JOHN KLARIN
Green Building Final 4/26/2022 Not Ready for Inspection JOHN KLARIN
Service/Power Release 4/26/2022 Not Ready for Inspection JOHN KLARIN
Pre-Inspection 4/29/2022 Approved JOHN KLARIN
Final 5/6/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Green Building Final 5/6/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Service/Power Release 5/6/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Final 6/7/2022 Corrections Issued JOHN KLARIN
Green Building Final 6/7/2022 Approved JOHN KLARIN
Service/Power Release 6/7/2022 Not Ready for Inspection JOHN KLARIN
Final 6/15/2022 OK to Issue CofO JOHN KLARIN
Service/Power Release 6/15/2022 Approved JOHN KLARIN