234-236 E 109TH PL 90061
Certificate Information: 234-236 E 109TH PL 90061
- Application / Permit
- 19010-10000-05408
- Plan Check / Job No.
- B19LA25497
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2 STORY DUPLEX WITH ATTACHED 2 CAR GARAGE
- Permit Issued
- Issued on 3/16/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/19/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/3/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/12/2019 | FERNANDO FLORES |
| Green Plans Picked Up | 12/13/2019 | APPLICANT |
| Corrections Issued | 12/19/2019 | FERNANDO FLORES |
| Quality Review Completed | 1/6/2020 | ARMEN JIVALAGIAN |
| Building Plans Picked Up | 1/9/2020 | APPLICANT |
| Applicant returned to address corrections | 1/22/2020 | FERNANDO FLORES |
| Plan Check Approved | 1/28/2020 | FERNANDO FLORES |
| Issued | 3/16/2020 | LADBS |
| CofO in Progress | 10/16/2020 | EUGENE CASSIDY |
| Permit Finaled | 10/19/2020 | DEROLD HAUFF |
| CofO Issued | 10/19/2020 | DEROLD HAUFF |
| Permit Finaled | 10/19/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Low Impact Development | Cleared | 1/16/2020 | ORVAL HERNANDEZ-MARCI |
| Address approval | Cleared | 1/21/2020 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 1/21/2020 | ERIK BEASLEY |
| Sewer availability | Cleared | 1/21/2020 | ERIK BEASLEY |
| Green Code | Cleared | 1/22/2020 | NEGAR NEJAD |
| Hydrant and Access approval | Cleared | 1/22/2020 | JEREMY CARTER |
| Roof/Waste drainage to street | Cleared | 1/22/2020 | THOMAS LANG |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/6/2020 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2020 | Partial Approval | EUGENE CASSIDY |
| Underground Mechanical | 5/26/2020 | Partial Approval | EUGENE CASSIDY |
| Insulation | 5/27/2020 | Partial Approval | BRIAN CHRISTIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2020 | Partial Approval | BRIAN CHRISTIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2020 | Partial Approval | BRIAN CHRISTIAN |
| BUILDING-Rough-Frame | 6/25/2020 | Not Ready for Inspection | BRIAN CHRISTIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/25/2020 | Partial Approval | BRIAN CHRISTIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2020 | Partial Approval | BRIAN CHRISTIAN |
| BUILDING-Rough-Frame | 7/21/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Rough | 7/21/2020 | Approved | EUGENE CASSIDY |
| Green Building Rough | 7/21/2020 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 7/21/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 7/21/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Rough-Elec/Plmb/HVAC | 7/21/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 7/21/2020 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 7/22/2020 | Approved | EUGENE CASSIDY |
| Gas Test | 7/22/2020 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 7/22/2020 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 7/22/2020 | Approved | EUGENE CASSIDY |
| Insulation | 7/27/2020 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 8/5/2020 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 8/5/2020 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 10/15/2020 | Approved | EUGENE CASSIDY |
| Final | 10/15/2020 | OK to Issue CofO | EUGENE CASSIDY |
| Green Building Final | 10/15/2020 | Approved | EUGENE CASSIDY |
| HVAC-Final | 10/15/2020 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 10/15/2020 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 10/15/2020 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 10/15/2020 | Approved | EUGENE CASSIDY |
| Smoke Detectors | 10/15/2020 | Approved | EUGENE CASSIDY |