234-236 E 109TH PL 90061

Certificate Information: 234-236 E 109TH PL 90061

Application / Permit
19010-10000-05408
Plan Check / Job No.
B19LA25497
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2 STORY DUPLEX WITH ATTACHED 2 CAR GARAGE
Permit Issued
Issued on 3/16/2020
Issuing Office
Metro
Current Status
CofO Issued on 10/19/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/3/2019 APPLICANT
Assigned to Plan Check Engineer 12/12/2019 FERNANDO FLORES
Green Plans Picked Up 12/13/2019 APPLICANT
Corrections Issued 12/19/2019 FERNANDO FLORES
Quality Review Completed 1/6/2020 ARMEN JIVALAGIAN
Building Plans Picked Up 1/9/2020 APPLICANT
Applicant returned to address corrections 1/22/2020 FERNANDO FLORES
Plan Check Approved 1/28/2020 FERNANDO FLORES
Issued 3/16/2020 LADBS
CofO in Progress 10/16/2020 EUGENE CASSIDY
Permit Finaled 10/19/2020 DEROLD HAUFF
CofO Issued 10/19/2020 DEROLD HAUFF
Permit Finaled 10/19/2020 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development Cleared 1/16/2020 ORVAL HERNANDEZ-MARCI
Address approval Cleared 1/21/2020 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 1/21/2020 ERIK BEASLEY
Sewer availability Cleared 1/21/2020 ERIK BEASLEY
Green Code Cleared 1/22/2020 NEGAR NEJAD
Hydrant and Access approval Cleared 1/22/2020 JEREMY CARTER
Roof/Waste drainage to street Cleared 1/22/2020 THOMAS LANG

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/6/2020 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 5/26/2020 Partial Approval EUGENE CASSIDY
Underground Mechanical 5/26/2020 Partial Approval EUGENE CASSIDY
Insulation 5/27/2020 Partial Approval BRIAN CHRISTIAN
Floor/Roof Diaphrgm/Shear Wall 5/28/2020 Partial Approval BRIAN CHRISTIAN
Floor/Roof Diaphrgm/Shear Wall 6/9/2020 Partial Approval BRIAN CHRISTIAN
BUILDING-Rough-Frame 6/25/2020 Not Ready for Inspection BRIAN CHRISTIAN
Floor/Roof Diaphrgm/Shear Wall 6/25/2020 Partial Approval BRIAN CHRISTIAN
Floor/Roof Diaphrgm/Shear Wall 6/30/2020 Partial Approval BRIAN CHRISTIAN
BUILDING-Rough-Frame 7/21/2020 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Rough 7/21/2020 Approved EUGENE CASSIDY
Green Building Rough 7/21/2020 Approved EUGENE CASSIDY
HVAC-Rough 7/21/2020 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 7/21/2020 Not Ready for Inspection EUGENE CASSIDY
Rough-Elec/Plmb/HVAC 7/21/2020 Not Ready for Inspection EUGENE CASSIDY
Verify Sprinkler Sign Off 7/21/2020 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 7/22/2020 Approved EUGENE CASSIDY
Gas Test 7/22/2020 Approved EUGENE CASSIDY
HVAC-Rough 7/22/2020 Approved EUGENE CASSIDY
PLUMBING-Rough 7/22/2020 Approved EUGENE CASSIDY
Insulation 7/27/2020 Approved EUGENE CASSIDY
Drywall Nailing 8/5/2020 Approved EUGENE CASSIDY
Interior/Exterior Lathing 8/5/2020 Approved EUGENE CASSIDY
ELECTRICAL-Final 10/15/2020 Approved EUGENE CASSIDY
Final 10/15/2020 OK to Issue CofO EUGENE CASSIDY
Green Building Final 10/15/2020 Approved EUGENE CASSIDY
HVAC-Final 10/15/2020 Approved EUGENE CASSIDY
PLUMBING-Final 10/15/2020 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 10/15/2020 SGSOV Approved EUGENE CASSIDY
Service/Power Release 10/15/2020 Approved EUGENE CASSIDY
Smoke Detectors 10/15/2020 Approved EUGENE CASSIDY