263-263 1/2 W 42ND ST 90037
Certificate Information: 263-263 1/2 W 42ND ST 90037
- Application / Permit
- 19010-10000-05406
- Plan Check / Job No.
- B19LA25496
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2 STORY DUPLEX WITH ATTACHED 3 CAR GARAGE.
- Permit Issued
- Issued on 3/16/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/13/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/3/2019 | APPLICANT |
| Green Plans Picked Up | 12/10/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/12/2019 | RACHEL BEYENE |
| Corrections Issued | 12/24/2019 | RACHEL BEYENE |
| Quality Review Completed | 1/4/2020 | STANLEY RAAP |
| Building Plans Picked Up | 1/9/2020 | APPLICANT |
| Plan Check Approved | 3/4/2020 | RAHEL BEYENE |
| Issued | 3/16/2020 | LADBS |
| Permit Finaled-Status Void | 6/9/2020 | FREDDIE RIVERA |
| Re-Activate Permit | 6/11/2020 | FREDDIE RIVERA |
| CofO in Progress | 8/29/2020 | ROBERT MCDOWELL |
| Permit Finaled | 11/13/2020 | DEROLD HAUFF |
| CofO Issued | 11/13/2020 | DEROLD HAUFF |
| Permit Finaled | 11/13/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Green Code | Cleared | 2/18/2020 | COLIN LOREDO |
| Hydrant and Access approval | Cleared | 2/21/2020 | GEORGE SUCHAND |
| Address approval | Cleared | 2/25/2020 | JEANETTE VONG |
| Community Plan Implem. Overlay | Cleared | 2/25/2020 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 2/25/2020 | JEANETTE VONG |
| Low Impact Development | Cleared | 2/25/2020 | MITESH PATEL |
| Permit | Cleared | 2/25/2020 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 2/25/2020 | JUAN ASHTON |
| Sewer availability | Cleared | 2/25/2020 | JEANETTE VONG |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/16/2020 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2020 | Partial Approval | ROBERT MCDOWELL |
| Underground Mechanical | 4/24/2020 | Approved | ROBERT MCDOWELL |
| Insulation | 4/27/2020 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2020 | Partial Approval | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2020 | Partial Approval | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 5/29/2020 | Corrections Issued | RUBEN SALAS |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2020 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 6/15/2020 | Conditional Approval | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 6/15/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 6/15/2020 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 6/17/2020 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 6/17/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| HVAC-Rough | 6/17/2020 | Approved | ROBERT MCDOWELL |
| MERV13>=Rough | 6/17/2020 | Approved | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 6/17/2020 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 6/18/2020 | Approved | SABAS ALONSO |
| Insulation | 6/18/2020 | Approved | SABAS ALONSO |
| Drywall Nailing | 6/22/2020 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 6/22/2020 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 8/28/2020 | Approved | ROBERT MCDOWELL |
| Final | 8/28/2020 | OK to Issue CofO | ROBERT MCDOWELL |
| Footing/Foundation/Slab | 8/28/2020 | Approved | ROBERT MCDOWELL |
| Green Building Final | 8/28/2020 | Approved | ROBERT MCDOWELL |
| HVAC-Final | 8/28/2020 | Approved | ROBERT MCDOWELL |
| MERV13>=Final | 8/28/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Final | 8/28/2020 | Approved | ROBERT MCDOWELL |
| Reinforced Concrete Frame | 8/28/2020 | Approved | ROBERT MCDOWELL |
| SGSOV-Seismic Gas S/O Valve | 8/28/2020 | SGSOV Approved | ROBERT MCDOWELL |
| Service/Power Release | 8/28/2020 | Approved | ROBERT MCDOWELL |
| Smoke Detectors | 8/28/2020 | Approved | ROBERT MCDOWELL |