164-166 W 81ST ST 90003

Certificate Information: 164-166 W 81ST ST 90003

Application / Permit
19010-10000-05390
Plan Check / Job No.
B19LA25475
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(N) 2 STORY DUPLEX W/ATT GARAGE
Permit Issued
Issued on 1/27/2020
Issuing Office
Metro
Current Status
CofO Issued on 7/31/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/3/2019 APPLICANT
Assigned to Plan Check Engineer 12/12/2019 LAMAR DAVIS
Green Plans Picked Up 12/13/2019 APPLICANT
Corrections Issued 12/16/2019 LAMAR DAVIS
Quality Review Completed 12/27/2019 HERNAN ARREOLA
Building Plans Picked Up 12/31/2019 APPLICANT
Plan Check Approved 1/16/2020 LAMAR DAVIS
Issued 1/27/2020 LADBS
CofO in Progress 7/16/2020 JOSEPH MCGARRY
Permit Finaled 7/31/2020 DEROLD HAUFF
CofO Issued 7/31/2020 DEROLD HAUFF
Permit Finaled 7/31/2020 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/8/2020 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 1/8/2020 EMIL KYUPELYAN
Sewer availability Cleared 1/8/2020 EMIL KYUPELYAN
Hydrant and Access approval Cleared 1/9/2020 GEORGE SUCHAND
Low Impact Development Cleared 1/14/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 1/14/2020 EMIL KYUPELYAN
Green Code Cleared 1/16/2020 KHEDER ALRAZAA

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/13/2020 Approved EUGENE CASSIDY
Deputy Reinf. Concrete 2/19/2020 Partial Approval EUGENE CASSIDY
Underground Mechanical 3/2/2020 Approved EUGENE CASSIDY
Wood Frame 3/2/2020 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 3/3/2020 Approved EUGENE CASSIDY
Insulation 3/3/2020 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 3/11/2020 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 4/7/2020 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 5/4/2020 Conditional Approval EUGENE CASSIDY
ELECTRICAL-Rough 5/4/2020 Approved EUGENE CASSIDY
Green Building Rough 5/4/2020 Approved EUGENE CASSIDY
HVAC-Rough 5/4/2020 Approved EUGENE CASSIDY
PLUMBING-Rough 5/4/2020 Approved EUGENE CASSIDY
Sewer 5/4/2020 Not Ready for Inspection EUGENE CASSIDY
Verify Sprinkler Sign Off 5/4/2020 Not Ready for Inspection EUGENE CASSIDY
Insulation 5/7/2020 Approved BRIAN CHRISTIAN
Drywall Nailing 5/12/2020 Approved BRIAN CHRISTIAN
Interior/Exterior Lathing 5/12/2020 Corrections Issued BRIAN CHRISTIAN
Interior/Exterior Lathing 5/18/2020 Approved BRIAN CHRISTIAN
Sewer 6/8/2020 Approved BRIAN CHRISTIAN
BUILDING-Rough-Frame 7/13/2020 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 7/13/2020 Approved ALEJANDRO DE ARTOLA
Final 7/13/2020 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 7/13/2020 Approved ALEJANDRO DE ARTOLA
Green Building Final 7/13/2020 Approved ALEJANDRO DE ARTOLA
HVAC-Final 7/13/2020 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 7/13/2020 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 7/13/2020 SGSOV Approved ALEJANDRO DE ARTOLA
Service/Power Release 7/13/2020 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 7/13/2020 Approved ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 7/13/2020 Approved ALEJANDRO DE ARTOLA
Final 7/16/2020 OK to Issue CofO JOSEPH MCGARRY
HVAC-Final 7/16/2020 Approved JOSEPH MCGARRY
HVAC-Rough 7/16/2020 Approved JOSEPH MCGARRY
Pre-Inspection 7/16/2020 Approved JOSEPH MCGARRY