910-912 E 84TH PL 90001

Certificate Information: 910-912 E 84TH PL 90001

Application / Permit
19010-10000-05389
Plan Check / Job No.
B19LA25474
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(N) 2 STORY DUPLEX W/ATT GARAGE
Permit Issued
Issued on 10/6/2020
Issuing Office
Current Status
CofO Issued on 2/11/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/3/2019 APPLICANT
Assigned to Plan Check Engineer 12/12/2019 LAMAR DAVIS
Corrections Issued 12/17/2019 LAMAR DAVIS
Quality Review Completed 12/27/2019 HERNAN ARREOLA
Building Plans Picked Up 12/31/2019 APPLICANT
Green Plans Picked Up 7/2/2020 APPLICANT
Plan Check Approved 8/24/2020 LAMAR DAVIS
Issued 10/6/2020 APPLICANT
CofO in Progress 2/9/2021 MICHAEL FAUNCE
Permit Finaled 2/11/2021 DEROLD HAUFF
CofO Issued 2/11/2021 DEROLD HAUFF
Permit Finaled 2/11/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/8/2020 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 1/8/2020 EMIL KYUPELYAN
Sewer availability Cleared 1/8/2020 EMIL KYUPELYAN
Hydrant and Access approval Cleared 1/9/2020 GEORGE SUCHAND
Green Code Cleared 7/1/2020 KHEDER ALRAZAA
Low Impact Development Cleared 8/5/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 8/7/2020 RENZ SORIANO

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/16/2020 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 10/16/2020 Conditional Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 10/26/2020 Partial Approval ALEJANDRO DE ARTOLA
PLUMBING-Rough 10/26/2020 Partial Approval ALEJANDRO DE ARTOLA
Sewer 10/26/2020 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 10/26/2020 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 10/27/2020 Not Ready for Inspection ALEJANDRO DE ARTOLA
Insulation 10/27/2020 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 10/28/2020 Partial Approval ALEJANDRO DE ARTOLA
Green Building Rough 10/28/2020 Partial Approval ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 10/28/2020 Not Ready for Inspection ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 11/2/2020 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 11/17/2020 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 11/20/2020 Approved DAVID FEILER
HVAC-Rough 11/20/2020 Corrections Issued DAVID FEILER
BUILDING-Rough-Frame 11/24/2020 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 11/24/2020 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 11/24/2020 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 11/24/2020 Approved ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 11/24/2020 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 11/30/2020 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 11/30/2020 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 11/30/2020 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 11/30/2020 Approved ALEJANDRO DE ARTOLA
Insulation 11/30/2020 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 12/1/2020 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 12/4/2020 Corrections Issued JOAQUIN GREENOUGH
Interior/Exterior Lathing 12/4/2020 Not Ready for Inspection JOAQUIN GREENOUGH
Drywall Nailing 12/9/2020 Approved EUGENE CASSIDY
Interior/Exterior Lathing 12/9/2020 Partial Approval EUGENE CASSIDY
Interior/Exterior Lathing 12/31/2020 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Final 1/27/2021 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 1/27/2021 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 1/27/2021 SGSOV Approved ALEJANDRO DE ARTOLA
Service/Power Release 1/27/2021 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 1/28/2021 Approved ALEJANDRO DE ARTOLA
Final 1/28/2021 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 1/28/2021 Approved ALEJANDRO DE ARTOLA
Gas Test 1/28/2021 Approved ALEJANDRO DE ARTOLA
Green Building Final 1/28/2021 Approved ALEJANDRO DE ARTOLA
HVAC-Final 1/28/2021 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 1/28/2021 Approved ALEJANDRO DE ARTOLA
Service/Power Release 1/28/2021 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 1/28/2021 Approved ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 1/28/2021 Approved ALEJANDRO DE ARTOLA
Final 2/2/2021 Conditional Approval ALEJANDRO DE ARTOLA