129-131 W 115TH ST 90061
Certificate Information: 129-131 W 115TH ST 90061
- Application / Permit
- 19010-10000-05385
- Plan Check / Job No.
- B19LA25441
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2-STORY DUPLEX WITH ATTACHED 1-CAR GARAGE AT FRONT & 2- CAR GARAGE AT REAR.
- Permit Issued
- Issued on 3/16/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/2/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/3/2019 | APPLICANT |
| Green Plans Picked Up | 12/10/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/12/2019 | SERGIO GUTIERREZ |
| Corrections Issued | 12/17/2019 | SERGIO GUTIERREZ |
| Quality Review Completed | 12/30/2019 | KESETE HAREGOT |
| Building Plans Picked Up | 1/6/2020 | APPLICANT |
| Plan Check Approved | 3/3/2020 | SERGIO GUTIERREZ |
| Issued | 3/16/2020 | LADBS |
| CofO in Progress | 11/16/2020 | ANSON MAGLASANG |
| No Progress | 11/20/2020 | ANSON MAGLASANG |
| CofO in Progress | 11/20/2020 | ANSON MAGLASANG |
| CofO in Progress | 12/1/2020 | ANSON MAGLASANG |
| Permit Finaled | 12/2/2020 | DEROLD HAUFF |
| CofO Issued | 12/2/2020 | DEROLD HAUFF |
| Permit Finaled | 12/2/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/13/2020 | EMIL KYUPELYAN |
| Eng Process Fee Ord 176,300 | Cleared | 1/13/2020 | EMIL KYUPELYAN |
| Hydrant and Access approval | Cleared | 1/13/2020 | JOHN CONNEALLY |
| Sewer availability | Cleared | 1/13/2020 | EMIL KYUPELYAN |
| Green Code | Cleared | 2/12/2020 | COLIN LOREDO |
| Low Impact Development | Cleared | 2/12/2020 | ORVAL HERNANDEZ-MARCIAL |
| Roof/Waste drainage to street | Cleared | 2/12/2020 | JEANETTE VONG |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/15/2020 | Approved | EUGENE CASSIDY |
| METHANE-Barrier | 5/15/2020 | Approved | EUGENE CASSIDY |
| METHANE-Subgrade | 5/15/2020 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2020 | Partial Approval | EUGENE CASSIDY |
| Underground Mechanical | 5/26/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 5/27/2020 | Partial Approval | EUGENE CASSIDY |
| Insulation | 5/27/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Underground Mechanical | 5/27/2020 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2020 | Partial Approval | BRIAN CHRISTIAN |
| Insulation | 5/28/2020 | Partial Approval | BRIAN CHRISTIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2020 | Partial Approval | EUGENE CASSIDY |
| Deputy Wood Construction | 6/24/2020 | Conditional Approval | BRIAN CHRISTIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2020 | No Access for Inspection | BRIAN CHRISTIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2020 | Approved | BRIAN CHRISTIAN |
| BUILDING-Rough-Frame | 7/28/2020 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 7/28/2020 | Approved | EUGENE CASSIDY |
| Green Building Rough | 7/28/2020 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 7/28/2020 | Conditional Approval | EUGENE CASSIDY |
| MERV13>=Rough | 7/28/2020 | Approved | EUGENE CASSIDY |
| METHANE-Rough | 7/28/2020 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 7/28/2020 | Approved | EUGENE CASSIDY |
| Rough-Elec/Plmb/HVAC | 7/28/2020 | Conditional Approval | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 7/28/2020 | Approved | EUGENE CASSIDY |
| Insulation | 7/31/2020 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 8/10/2020 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 8/10/2020 | Corrections Issued | EUGENE CASSIDY |
| Interior/Exterior Lathing | 8/11/2020 | Corrections Issued | EUGENE CASSIDY |
| Interior/Exterior Lathing | 8/12/2020 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 10/13/2020 | Approved | EUGENE CASSIDY |
| Final | 10/13/2020 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 10/13/2020 | Approved | EUGENE CASSIDY |
| HVAC-Final | 10/13/2020 | Approved | EUGENE CASSIDY |
| MERV13>=Final | 10/13/2020 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 10/13/2020 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 10/13/2020 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 10/13/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 10/13/2020 | Approved | EUGENE CASSIDY |
| Final | 10/30/2020 | Corrections Issued | EUGENE CASSIDY |
| Service/Power Release | 10/30/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 11/12/2020 | OK to Issue CofO | EUGENE CASSIDY |
| Service/Power Release | 11/12/2020 | Approved | EUGENE CASSIDY |