1448-1450 W 80TH ST 90047

Certificate Information: 1448-1450 W 80TH ST 90047

Application / Permit
19010-10000-05384
Plan Check / Job No.
B19LA25440
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2 STORY DUPLEX WITH ATTACHED 3 CAR GARAGE
Permit Issued
Issued on 1/31/2020
Issuing Office
Metro
Current Status
CofO Issued on 10/20/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/3/2019 APPLICANT
Green Plans Picked Up 12/10/2019 APPLICANT
Assigned to Plan Check Engineer 12/12/2019 SERGIO GUTIERREZ
Corrections Issued 12/17/2019 SERGIO GUTIERREZ
Quality Review Completed 12/30/2019 KESETE HAREGOT
Building Plans Picked Up 1/6/2020 APPLICANT
Plan Check Approved 1/23/2020 SERGIO GUTIERREZ
Issued 1/31/2020 LADBS
CofO in Progress 10/17/2020 ALEJANDRO DE ARTOLA
Permit Finaled 10/20/2020 DEROLD HAUFF
CofO Issued 10/20/2020 DEROLD HAUFF
Permit Finaled 10/20/2020 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/8/2020 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 1/8/2020 EMIL KYUPELYAN
Highway dedication Cleared 1/8/2020 EMIL KYUPELYAN
Sewer availability Cleared 1/8/2020 EMIL KYUPELYAN
Hydrant and Access approval Cleared 1/9/2020 GEORGE SUCHAND
Frnt yard landscape/Water mgmt Cleared 1/14/2020 SARAHI ORTEGA
Low Impact Development Cleared 1/16/2020 ORVAL HERNANDEZ-MARCI
Green Code Cleared 1/17/2020 COLIN LOREDO
Roof/Waste drainage to street Cleared 1/23/2020 CELINA MORENO

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/17/2020 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 5/4/2020 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 5/4/2020 Approved ALEJANDRO DE ARTOLA
Insulation 5/5/2020 Partial Approval BRIAN CHRISTIAN
Floor/Roof Diaphrgm/Shear Wall 5/6/2020 Partial Approval BRIAN CHRISTIAN
Floor/Roof Diaphrgm/Shear Wall 5/21/2020 Partial Approval BRIAN CHRISTIAN
Floor/Roof Diaphrgm/Shear Wall 6/18/2020 Partial Approval BRIAN CHRISTIAN
Floor/Roof Diaphrgm/Shear Wall 7/8/2020 Partial Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 7/15/2020 Approved FREDDIE RIVERA
ELECTRICAL-Rough 7/15/2020 Partial Approval FREDDIE RIVERA
Green Building Rough 7/15/2020 Approved FREDDIE RIVERA
HVAC-Rough 7/15/2020 Corrections Issued FREDDIE RIVERA
PLUMBING-Rough 7/15/2020 Approved FREDDIE RIVERA
Verify Sprinkler Sign Off 7/15/2020 Approved FREDDIE RIVERA
Insulation 7/16/2020 Corrections Issued SABAS ALONSO
Drywall Nailing 7/31/2020 Approved SABAS ALONSO
Interior/Exterior Lathing 7/31/2020 Approved SABAS ALONSO
ELECTRICAL-Final 10/16/2020 Approved ALEJANDRO DE ARTOLA
Final 10/16/2020 OK to Issue CofO ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 10/16/2020 Approved ALEJANDRO DE ARTOLA
Green Building Final 10/16/2020 Approved ALEJANDRO DE ARTOLA
HVAC-Final 10/16/2020 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 10/16/2020 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 10/16/2020 SGSOV Approved ALEJANDRO DE ARTOLA
Service/Power Release 10/16/2020 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 10/16/2020 Approved ALEJANDRO DE ARTOLA