8470 W FRANKLIN AVE 90069
Certificate Information: 8470 W FRANKLIN AVE 90069
- Application / Permit
- 19010-10000-05371
- Plan Check / Job No.
- B19LA25358
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY SFD WITH BASEMENT, ROOF DECK, AND ATTACHED GARAGE
- Permit Issued
- Issued on 8/3/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/2/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/19/2019 | CATHERINE CHEN |
| Green Plans Picked Up | 1/27/2020 | APPLICANT |
| Corrections Issued | 1/29/2020 | CATHERINE CHEN |
| Quality Review Completed | 2/3/2020 | MINYE PAK |
| Building Plans Picked Up | 2/10/2020 | APPLICANT |
| Applicant returned to address corrections | 10/2/2020 | CATHERINE CHEN |
| Applicant returned to address corrections | 10/30/2020 | CATHERINE CHEN |
| Applicant returned to address corrections | 11/2/2020 | CATHERINE CHEN |
| Applicant returned to address corrections | 2/8/2021 | CATHERINE CHEN |
| Applicant returned to address corrections | 2/18/2021 | CATHERINE CHEN |
| Applicant returned to address corrections | 2/22/2021 | CATHERINE CHEN |
| Applicant returned to address corrections | 12/10/2021 | CATHERINE CHEN |
| Applicant returned to address corrections | 12/15/2021 | CATHERINE CHEN |
| Applicant returned to address corrections | 12/17/2021 | CATHERINE CHEN |
| Applicant returned to address corrections | 12/27/2021 | CATHERINE CHEN |
| Applicant returned to address corrections | 12/28/2021 | CATHERINE CHEN |
| Applicant returned to address corrections | 1/25/2022 | CATHERINE CHEN |
| Plan Check Approved | 5/18/2022 | SINA KHOSRAVI |
| Issued | 8/3/2022 | APPLICANT |
| CofO in Progress | 9/2/2025 | ROY SPAULDING |
| Permit Finaled | 9/4/2025 | DEROLD HAUFF |
| CofO Issued | 9/4/2025 | DEROLD HAUFF |
| Permit Finaled | 9/4/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 2/19/2020 | MARKOS PEREZ-BRAN |
| BHO/Hillside ordinance | Cleared | 2/19/2020 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/19/2020 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 2/19/2020 | MARKOS PEREZ-BRAN |
| ZI | Cleared | 2/19/2020 | VINCENT QUITORIANO |
| Address approval | Cleared | 8/24/2020 | ELENA LOPEZ |
| BHO/Hillside ordinance | Cleared | 8/25/2020 | ELENA LOPEZ |
| Permit | Cleared | 8/26/2020 | ELENA LOPEZ |
| Work Adjacent to Public Way | Cleared | 1/4/2021 | ARMEN SARKISIAN |
| Hydrant and Access approval | Cleared | 2/12/2021 | KURT CORRAL |
| Low Impact Development | Cleared | 10/29/2021 | TA ANH |
| Stormwater Pollution Mitigatn | Cleared | 10/29/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 11/1/2021 | STEVE MELGAR |
| Excavation more than 5-ft deep | Cleared | 12/15/2021 | CALOSHA APPROVED |
| Grading Pre-Inspection | Cleared | 12/15/2021 | CATHERINE CHEN |
| Green Code | Cleared | 5/18/2022 | NEGAR NEJAD |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mahn,, Jonathan Edward; Lic. No.: C60293 | 12848 FOOTHILL BLVD SYLMAR, CA 91381 |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 25531 PRADO DELAS BELLOTAS CALABASAS, CA 91302 |
| Geologist | Triebold,, Mark John; Lic. No.: EG1796 | 6906 QUITO COURT CAMARILLO, CA 93012 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Grading | 8/18/2022 | Conditional Approval | RAUL BARAJAS |
| Deputy Grading | 8/19/2022 | Conditional Approval | RAUL BARAJAS |
| Deputy Grading | 8/22/2022 | Conditional Approval | RAUL BARAJAS |
| Deputy Grading | 8/23/2022 | Conditional Approval | RAUL BARAJAS |
| Deputy Grading | 8/24/2022 | Conditional Approval | RYAN SALAZAR |
| Piling/Pier/Caisson | 8/26/2022 | Corrections Issued | RAUL BARAJAS |
| Piling/Pier/Caisson | 8/31/2022 | Partial Approval | RAUL BARAJAS |
| Special/Order Compliance | 8/31/2022 | Approved | JOAQUIN GREENOUGH |
| Deputy Reinf. Concrete | 9/2/2022 | Conditional Approval | RAUL BARAJAS |
| Piling/Pier/Caisson | 9/9/2022 | Partial Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 9/13/2022 | Conditional Approval | RAUL BARAJAS |
| Piling/Pier/Caisson | 10/12/2022 | Partial Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 10/19/2022 | Conditional Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 11/17/2022 | Conditional Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 11/29/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Deputy Reinf. Concrete | 12/7/2022 | Conditional Approval | RAUL BARAJAS |
| Piling/Pier/Caisson | 12/14/2022 | Partial Approval | STUART CHAPMAN |
| Underground Mechanical | 1/17/2023 | Approved | JEFFREY MEAD |
| Footing/Foundation/Slab | 1/24/2023 | Partial Approval | STUART CHAPMAN |
| Deputy Reinf. Concrete | 1/25/2023 | Approved | STUART CHAPMAN |
| Deputy Reinf. Concrete | 2/6/2023 | Conditional Approval | STUART CHAPMAN |
| Reinforced Masonry Frame | 3/2/2023 | Partial Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 3/3/2023 | Conditional Approval | RAUL BARAJAS |
| Deputy Steel/Welding | 3/3/2023 | Approved | STUART CHAPMAN |
| Reinforced Concrete Frame | 3/3/2023 | Partial Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2023 | Partial Approval | STUART CHAPMAN |
| Deputy Steel/Welding | 4/21/2023 | Conditional Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2023 | Partial Approval | RAUL BARAJAS |
| Deputy Wood Construction | 2/12/2024 | Conditional Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 2/13/2024 | Corrections Issued | RAUL BARAJAS |
| BUILDING-Rough-Frame | 2/16/2024 | Corrections Issued | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2024 | Partial Approval | RAUL BARAJAS |
| HVAC-Rough | 3/20/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Final | 3/21/2024 | Corrections Issued | RAUL BARAJAS |
| ELECTRICAL-Rough | 3/21/2024 | Conditional Approval | RAUL BARAJAS |
| HVAC-Rough | 3/21/2024 | Partial Approval | RAUL BARAJAS |
| Interior/Exterior Lathing | 3/28/2024 | Partial Inspection | RAUL BARAJAS |
| PLUMBING-Rough | 3/28/2024 | Corrections Issued | RAUL BARAJAS |
| Insulation | 6/10/2024 | Approved | RAUL BARAJAS |
| Drywall Nailing | 8/27/2024 | Approved | RAUL BARAJAS |
| Drywall Nailing | 9/5/2024 | Approved | RAUL BARAJAS |
| Shower Pan | 9/5/2024 | Approved | RAUL BARAJAS |
| Shower Pan | 9/6/2024 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 9/13/2024 | Approved | RAUL BARAJAS |
| ELECTRICAL-Final | 3/19/2025 | Partial Approval | ROY SPAULDING |
| HVAC-Final | 3/19/2025 | Corrections Issued | ROY SPAULDING |
| PLUMBING-Final | 3/19/2025 | Partial Approval | ROY SPAULDING |
| BUILDING-Rough-Frame | 4/1/2025 | Approved | ROY SPAULDING |
| ELECTRICAL-Final | 4/1/2025 | Not Ready for Inspection | ROY SPAULDING |
| Final | 4/1/2025 | Not Ready for Inspection | ROY SPAULDING |
| Footing/Foundation/Slab | 4/1/2025 | Approved | ROY SPAULDING |
| Green Building Final | 4/1/2025 | Approved | ROY SPAULDING |
| Green Building Rough | 4/1/2025 | Approved | ROY SPAULDING |
| HVAC-Final | 4/1/2025 | Not Ready for Inspection | ROY SPAULDING |
| PLUMBING-Final | 4/1/2025 | Not Ready for Inspection | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 4/1/2025 | SGSOV Not Ready | ROY SPAULDING |
| Service/Power Release | 4/1/2025 | Not Ready for Inspection | ROY SPAULDING |
| Smoke Detectors | 4/1/2025 | Approved | ROY SPAULDING |
| Verify Sprinkler Sign Off | 4/1/2025 | Approved | ROY SPAULDING |
| ELECTRICAL-Final | 4/4/2025 | Not Ready for Inspection | ROY SPAULDING |
| Final | 4/4/2025 | Corrections Issued | ROY SPAULDING |
| HVAC-Final | 4/4/2025 | Not Ready for Inspection | ROY SPAULDING |
| PLUMBING-Final | 4/4/2025 | Not Ready for Inspection | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 4/4/2025 | SGSOV Not Ready | ROY SPAULDING |
| Service/Power Release | 4/4/2025 | Not Ready for Inspection | ROY SPAULDING |
| ELECTRICAL-Final | 4/10/2025 | Approved | ROY SPAULDING |
| Final | 4/10/2025 | Corrections Issued | ROY SPAULDING |
| HVAC-Final | 4/10/2025 | Approved | ROY SPAULDING |
| PLUMBING-Final | 4/10/2025 | Approved | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 4/10/2025 | SGSOV Not Ready | ROY SPAULDING |
| Service/Power Release | 4/10/2025 | Not Ready for Inspection | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 7/30/2025 | SGSOV Not Ready | BRIAN SULLIVAN |
| Final | 8/25/2025 | Not Ready for Inspection | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 8/25/2025 | SGSOV Approved | ROY SPAULDING |
| Service/Power Release | 8/25/2025 | Approved | ROY SPAULDING |
| Final | 8/26/2025 | Conditional Approval | ROY SPAULDING |
| Final | 8/29/2025 | OK to Issue CofO | ROY SPAULDING |