1016 N RIDGEWOOD PL 90038

Certificate Information: 1016 N RIDGEWOOD PL 90038

Application / Permit
19010-10000-05336
Plan Check / Job No.
B19LA25204
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 32' X 31' 3" ONE STORY, TYPE V ADU PER AB 494 AND SB 229.
Permit Issued
Issued on 3/20/2020
Issuing Office
Metro
Current Status
CofO Issued on 11/25/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/26/2019 APPLICANT
Assigned to Plan Check Engineer 12/10/2019 CRYSTEL MAALOUF
Corrections Issued 12/12/2019 CRYSTEL MAALOUF
Quality Review Completed 12/12/2019 JASON HEALEY
Building Plans Picked Up 12/24/2019 APPLICANT
Green Plans Picked Up 1/9/2020 APPLICANT
Applicant returned to address corrections 3/3/2020 CRYSTEL MAALOUF
Plan Check Approved 3/11/2020 CRYSTEL MAALOUF
Issued 3/20/2020 LADBS
CofO in Progress 11/16/2020 CHRIS CHRISTENSEN
Permit Finaled 11/25/2020 DEROLD HAUFF
CofO Issued 11/25/2020 DEROLD HAUFF
Permit Finaled 11/25/2020 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/9/2020 THOMAS LANG
Construction near power lines Cleared 1/9/2020 TORI CHEN
Eng Process Fee Ord 176,300 Cleared 1/9/2020 THOMAS LANG
Sewer availability Cleared 1/9/2020 THOMAS LANG
Green Code Cleared 2/5/2020 VIVIAN LAO
Hydrant and Access approval Cleared 2/20/2020 GEORGE SUCHAND
Low Impact Development Cleared 2/20/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 2/20/2020 THOMAS LANG

Contact Information

Contractor S M Development Company Inc; Lic. No.: 450270-B 12208 PEORIA STREET      SUN VALLEY, CA 91352
Engineer Li,, Dacheng David; Lic. No.: C58075 3129 S HACIENDA BL STE 524      HACIENDA HEIGHTS, CA 91745

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 3/25/2020 Not Ready for Inspection JOSEPH MCGARRY
PLUMBING-Rough 3/25/2020 Partial Approval JOSEPH MCGARRY
Verify Sprinkler Sign Off 3/25/2020 Not Ready for Inspection JOSEPH MCGARRY
Footing/Foundation/Slab 4/13/2020 Not Ready for Inspection ARTHUR SARGSYAN
Excavation/Setback/Form/Re-Bar 4/15/2020 Approved RAUL BARAJAS
BUILDING-Rough-Frame 5/28/2020 Not Ready for Inspection ARTHUR SARGSYAN
ELECTRICAL-Rough 5/28/2020 Approved ARTHUR SARGSYAN
Green Building Rough 5/28/2020 Approved ARTHUR SARGSYAN
HVAC-Rough 5/28/2020 Approved ARTHUR SARGSYAN
PLUMBING-Rough 5/28/2020 Approved ARTHUR SARGSYAN
Verify Sprinkler Sign Off 5/28/2020 Not Ready for Inspection ARTHUR SARGSYAN
Wood Frame 5/28/2020 Not Ready for Inspection ARTHUR SARGSYAN
ELECTRICAL-Rough 6/2/2020 Approved ARTHUR SARGSYAN
HVAC-Rough 6/2/2020 Approved ARTHUR SARGSYAN
PLUMBING-Rough 6/2/2020 Approved ARTHUR SARGSYAN
Insulation 6/18/2020 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 6/18/2020 Partial Approval CHRIS CHRISTENSEN
Drywall Nailing 6/24/2020 Approved ARTHUR SARGSYAN
Underground Mechanical 7/7/2020 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 10/19/2020 Approved JOSEPH MCGARRY
Final 10/19/2020 Corrections Issued JOSEPH MCGARRY
Footing/Foundation/Slab 10/19/2020 Approved JOSEPH MCGARRY
Green Building Final 10/19/2020 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 10/19/2020 SGSOV Approved JOSEPH MCGARRY
Service/Power Release 10/19/2020 Not Required JOSEPH MCGARRY
Smoke Detectors 10/19/2020 Approved JOSEPH MCGARRY
Verify Sprinkler Sign Off 10/19/2020 Approved JOSEPH MCGARRY
ELECTRICAL-Final 11/16/2020 Approved CHRIS CHRISTENSEN
Final 11/16/2020 OK to Issue CofO CHRIS CHRISTENSEN
Green Building Final 11/16/2020 Approved CHRIS CHRISTENSEN
HVAC-Final 11/16/2020 Approved CHRIS CHRISTENSEN
PLUMBING-Final 11/16/2020 Approved CHRIS CHRISTENSEN