1845-1847 S VINEYARD AVE 90019

Certificate Information: 1845-1847 S VINEYARD AVE 90019

Application / Permit
19010-10000-05326
Plan Check / Job No.
B19LA25185
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW (2) STORY DUPLEX (REAR) 1,672.08 SQFT 2 OF 2
Permit Issued
Issued on 7/17/2020
Issuing Office
Current Status
CofO Issued on 8/13/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/26/2019 APPLICANT
Green Plans Picked Up 12/4/2019 APPLICANT
Assigned to Plan Check Engineer 12/5/2019 TSE MING HUANG
Corrections Issued 12/20/2019 TSE MING HUANG
Quality Review Completed 12/28/2019 STANLEY RAAP
Building Plans Picked Up 1/6/2020 APPLICANT
Plan Check Approved 2/11/2020 TSE MING HUANG
Issued 7/17/2020 APPLICANT
CofO in Progress 7/21/2021 STUART CHAPMAN
Permit Finaled 8/13/2021 DEROLD HAUFF
CofO Issued 8/13/2021 DEROLD HAUFF
Permit Finaled 8/13/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/23/2019 JAMES MORALEZ
Eng Process Fee Ord 176,300 Cleared 12/23/2019 JAMES MORALEZ
Green Code Cleared 12/23/2019 DONALD CRICHLOW
Highway dedication Cleared 12/23/2019 JAMES MORALEZ
Permit Cleared 12/23/2019 JAMES MORALEZ
Sewer availability Cleared 12/23/2019 JAMES MORALEZ
Hydrant and Access approval Cleared 1/6/2020 JOHN CONNEALLY
Low Impact Development Cleared 1/29/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 1/29/2020 JUAN ASHTON
Frnt yard landscape/Water mgmt Cleared 2/4/2020 ANNA VIDAL
Prkng lot landscape/Water mgmt Cleared 2/4/2020 ANNA VIDAL

Contact Information

Contractor Owner-Builder       ,
Engineer Pinzon,, Eduardo A; Lic. No.: C74869 821 W SPRUCE ST      WEST COVINA, CA 91790

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/3/2020 Partial Approval STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 8/20/2020 Approved STUART CHAPMAN
Footing/Foundation/Slab 8/20/2020 Approved STUART CHAPMAN
METHANE-Barrier 8/20/2020 Approved STUART CHAPMAN
METHANE-Subgrade 8/20/2020 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 9/10/2020 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 9/18/2020 Partial Approval STUART CHAPMAN
PLUMBING-Rough 10/2/2020 Approved STUART CHAPMAN
Drywall Nailing 10/5/2020 Not Ready for Inspection STUART CHAPMAN
ELECTRICAL-Rough 10/5/2020 Approved STUART CHAPMAN
Drywall Nailing 10/8/2020 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 10/15/2020 Corrections Issued STUART CHAPMAN
Green Building Rough 10/15/2020 Not Ready for Inspection STUART CHAPMAN
METHANE-Rough 10/15/2020 Approved STUART CHAPMAN
Verify Sprinkler Sign Off 10/15/2020 Not Ready for Inspection STUART CHAPMAN
HVAC-Rough 10/21/2020 Not Ready for Inspection STUART CHAPMAN
Rough-Elec/Plmb/HVAC 10/21/2020 Not Ready for Inspection STUART CHAPMAN
Shower Pan 10/21/2020 Approved STUART CHAPMAN
HVAC-Rough 10/22/2020 Conditional Approval STUART CHAPMAN
BUILDING-Rough-Frame 10/27/2020 Not Ready for Inspection STUART CHAPMAN
Green Building Rough 10/27/2020 Approved STUART CHAPMAN
Verify Sprinkler Sign Off 10/27/2020 Not Ready for Inspection STUART CHAPMAN
Wood Frame 10/27/2020 Approved STUART CHAPMAN
Insulation 11/5/2020 Partial Approval STUART CHAPMAN
Interior/Exterior Lathing 11/5/2020 Partial Approval STUART CHAPMAN
Insulation 11/12/2020 Not Ready for Inspection STUART CHAPMAN
Interior/Exterior Lathing 11/12/2020 Approved STUART CHAPMAN
Insulation 11/16/2020 Not Ready for Inspection STUART CHAPMAN
BUILDING-Rough-Frame 11/24/2020 Approved STUART CHAPMAN
Insulation 11/24/2020 Approved STUART CHAPMAN
Verify Sprinkler Sign Off 11/24/2020 Approved STUART CHAPMAN
Drywall Nailing 11/30/2020 Approved STUART CHAPMAN
Underground Mechanical 1/21/2021 Approved STUART CHAPMAN
ELECTRICAL-Final 2/23/2021 Corrections Issued STUART CHAPMAN
HVAC-Final 2/23/2021 Approved STUART CHAPMAN
PLUMBING-Final 2/23/2021 Approved STUART CHAPMAN
ELECTRICAL-Final 3/2/2021 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 6/9/2021 SGSOV Not Ready KATHRYN BUTTERWORTH
Final 7/16/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Green Building Final 7/16/2021 Approved KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 7/16/2021 SGSOV Not Ready KATHRYN BUTTERWORTH
Service/Power Release 7/16/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Smoke Detectors 7/16/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 7/20/2021 SGSOV Not Ready KATHRYN BUTTERWORTH
Final 7/21/2021 OK to Issue CofO STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 7/21/2021 SGSOV Approved STUART CHAPMAN
Service/Power Release 7/21/2021 Approved STUART CHAPMAN
Smoke Detectors 7/21/2021 Approved STUART CHAPMAN