1437 N MCCOLLUM ST 90026

Certificate Information: 1437 N MCCOLLUM ST 90026

Application / Permit
19010-10000-05313
Plan Check / Job No.
B19LA25141
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EXISTING ONE STORY GARAGE TO BE CONVERTED TO ADU, ADD 2ND STORY WITH NEW PREFAB STAIRS TO (E) ONE STORY GARAGE.
Permit Issued
Issued on 6/1/2020
Issuing Office
Current Status
CofO Issued on 2/23/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/26/2019 APPLICANT
Assigned to Plan Check Engineer 12/5/2019 TSE MING HUANG
Corrections Issued 12/13/2019 TSE MING HUANG
Green Plans Picked Up 12/17/2019 APPLICANT
Quality Review Completed 12/28/2019 STANLEY RAAP
Building Plans Picked Up 1/7/2020 APPLICANT
Applicant returned to address corrections 2/25/2020 TSE MING HUANG
Plan Check Approved 5/27/2020 TSE MING HUANG
Issued 6/1/2020 APPLICANT
CofO in Progress 2/23/2026 HAMIK HARTOUNIAN
Permit Finaled 2/23/2026 DEROLD HAUFF
CofO Issued 2/23/2026 DEROLD HAUFF
Permit Finaled 2/23/2026 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/22/2020 EMIL KYUPELYAN
Grading Pre-Inspection Cleared 1/22/2020 BARTON HOLMES
Sewer availability Cleared 1/22/2020 EMIL KYUPELYAN
Green Code Cleared 2/5/2020 NEGAR NEJAD
Hydrant and Access approval Cleared 2/5/2020 JEREMY CARTER
Low Impact Development Cleared 2/7/2020 AMMAR ELTAWIL
Address approval Cleared 2/10/2020 EMIL KYUPELYAN
Roof/Waste drainage to street Cleared 2/10/2020 EMIL KYUPELYAN

Contact Information

Contractor Oko Builders Inc; Lic. No.: 1063539-B 369 S DOHENY DR SUITE 116      BEVERLY HILLS, CA 90211
Engineer Song,, Zhenyu Michael; Lic. No.: S5266 12540 DESTINO ST      CERRITOS, CA 90703

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/12/2020 Approved MATTHEW NUCKOLLS
Floor/Roof Diaphrgm/Shear Wall 6/12/2020 Partial Approval MATTHEW NUCKOLLS
Deputy Drilled-In Anchors 6/15/2020 Conditional Approval THOMAS LOGRASSO
ELECTRICAL-Rough 6/26/2020 Approved ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 6/26/2020 Approved ROBERT VORHIS
HVAC-Rough 6/26/2020 Corrections Issued ROBERT VORHIS
PLUMBING-Rough 6/26/2020 Approved ROBERT VORHIS
BUILDING-Rough-Frame 7/7/2020 Approved SCOTT FINNILA
Green Building Rough 7/7/2020 Approved SCOTT FINNILA
Sewer 7/7/2020 Approved SCOTT FINNILA
Shower Pan 7/7/2020 Approved SCOTT FINNILA
Insulation 7/14/2020 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 7/17/2020 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 7/17/2020 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Final 2/1/2021 Corrections Issued OSVALDO PARAMO
Final 2/1/2021 Not Ready for Inspection OSVALDO PARAMO
Footing/Foundation/Slab 2/1/2021 Approved OSVALDO PARAMO
Gas Test 2/1/2021 Approved OSVALDO PARAMO
Green Building Final 2/1/2021 Not Ready for Inspection OSVALDO PARAMO
HVAC-Final 2/1/2021 Corrections Issued OSVALDO PARAMO
PLUMBING-Final 2/1/2021 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 2/1/2021 SGSOV Approved OSVALDO PARAMO
Smoke Detectors 2/1/2021 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Final 2/26/2021 Not Ready for Inspection ROBERT VORHIS
Final 2/26/2021 Not Ready for Inspection ROBERT VORHIS
Green Building Final 2/26/2021 Approved ROBERT VORHIS
HVAC-Final 2/26/2021 Approved ROBERT VORHIS
Smoke Detectors 2/26/2021 Approved ROBERT VORHIS
ELECTRICAL-Final 3/8/2021 Approved KATHRYN BUTTERWORTH
Final 3/8/2021 Partial Approval KATHRYN BUTTERWORTH
Final 6/26/2024 Partial Approval HAMIK HARTOUNIAN
Final 2/20/2026 OK to Issue CofO HAMIK HARTOUNIAN