4250 N NAVAJO ST 91602

Certificate Information: 4250 N NAVAJO ST 91602

Application / Permit
19010-10000-05306
Plan Check / Job No.
B19LA25129
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Miscellaneous Bldg/Structure
Work Description
NEW COSNTRUCTION OF PATIO COVER AT BBQ AREA
Permit Issued
Issued on 1/21/2021
Issuing Office
Current Status
Issued on 1/21/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/26/2019 APPLICANT
Assigned to Plan Check Engineer 12/20/2019 AUNG SOE
Corrections Issued 12/26/2019 MIGUEL JIMENEZ
Quality Review Completed 1/7/2020 BILL STUTSMAN
Building Plans Picked Up 1/13/2020 APPLICANT
Applicant returned to address corrections 5/11/2020 AUNG SOE
Applicant returned to address corrections 10/19/2020 AUNG SOE
Plan Check Approved 10/21/2020 AUNG SOE
Issued 1/21/2021 APPLICANT

Permit Application Clearance Information

ZI Cleared 1/30/2020 ANNA VIDAL
Eng Process Fee Ord 176,300 Cleared 7/17/2020 LEE GUILBEAUX
Low Impact Development Cleared 9/23/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 10/1/2020 ADRIAN CASTRO

Contact Information

Architect Neubert,, Aaron Douglas; Lic. No.: C29005 3052 BERKELEY CIRCLE      LOS ANGELES, CA 90026
Contractor Picture Build; Lic. No.: 990772-C27 12410 FOOTHILL BLVD STE E      SYLMAR, CA 91342
Engineer Phillips,, Craig Richard; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/9/2021 Corrections Issued ARAM AVEDISIAN
Footing/Foundation/Slab 3/15/2021 No Access for Inspection THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 3/18/2021 Corrections Issued THOMAS FINNILA
Deputy Reinf. Concrete 3/19/2021 Conditional Approval THOMAS FINNILA
Piling/Pier/Caisson 3/24/2021 Partial Approval THOMAS FINNILA
Deputy Reinf. Concrete 3/31/2021 Conditional Approval THOMAS FINNILA
Structural Steel Frame 4/30/2021 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 5/24/2021 Conditional Approval THOMAS FINNILA
Wood Frame 6/1/2021 Approved THOMAS FINNILA
Wood Frame 6/15/2021 Approved THOMAS FINNILA
Footing/Foundation/Slab 7/29/2021 Approved ARAM AVEDISIAN