2128 S ORANGE DR 90016

Certificate Information: 2128 S ORANGE DR 90016

Application / Permit
19010-10000-05239
Plan Check / Job No.
B19LA24803
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED 2 STORY ACCESSORY DWELLING UNIT PER AB 494 AND SB 229 WITH AN ATTACHED 2-CAR GARAGE.
Permit Issued
Issued on 2/18/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 8/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/21/2019 APPLICANT
Assigned to Plan Check Engineer 11/26/2019 MICHAEL LOPEZ
Corrections Issued 12/4/2019 MICHAEL LOPEZ
Quality Review Completed 12/7/2019 STANLEY RAAP
Green Plans Picked Up 12/11/2019 APPLICANT
Building Plans Picked Up 12/12/2019 APPLICANT
Plan Check Approved 2/11/2020 MICHAEL LOPEZ
Issued 2/18/2020 LADBS
CofO in Progress 8/15/2023 STUART CHAPMAN
Permit Finaled 8/15/2023 DEROLD HAUFF
CofO Issued 8/15/2023 DEROLD HAUFF
Permit Finaled 8/15/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/20/2019 ELAINE LEI
CPC Cleared 12/20/2019 JASON CHAN
Eng Process Fee Ord 176,300 Cleared 12/20/2019 ELAINE LEI
Sewer availability Cleared 12/20/2019 ELAINE LEI
Hydrant and Access approval Cleared 12/23/2019 JEREMY CARTER
Green Code Cleared 1/2/2020 VIVIAN LAO
Low Impact Development Cleared 2/6/2020 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 2/11/2020 EMIL KYUPELYAN

Contact Information

Contractor Owner-Builder       ,
Engineer Kim,, Taewon; Lic. No.: C80632 28000 S WESTERN AVE UNIT 209      SAN PEDRO, CA 90732

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/2/2020 Corrections Issued BOB DUNN
Excavation/Setback/Form/Re-Bar 3/4/2020 Corrections Issued EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 3/18/2020 Approved DAVID CHAN
Footing/Foundation/Slab 3/18/2020 Approved DAVID CHAN
BUILDING-Rough-Frame 4/13/2020 Partial Approval STUART CHAPMAN
Green Building Rough 4/13/2020 Not Ready for Inspection STUART CHAPMAN
Verify Sprinkler Sign Off 4/13/2020 Not Ready for Inspection STUART CHAPMAN
Underground Mechanical 4/28/2020 Partial Approval STUART CHAPMAN
PLUMBING-Rough 5/6/2020 Approved STUART CHAPMAN
BUILDING-Rough-Frame 5/28/2020 Conditional Approval STUART CHAPMAN
ELECTRICAL-Rough 5/28/2020 Approved STUART CHAPMAN
Insulation 6/4/2020 Not Ready for Inspection SABAS ALONSO
Insulation 6/9/2020 Approved THOMAS LOGRASSO
Drywall Nailing 6/11/2020 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 6/16/2020 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 7/20/2020 Approved STUART CHAPMAN
ELECTRICAL-Final 7/20/2020 Approved STUART CHAPMAN
Final 7/20/2020 Corrections Issued STUART CHAPMAN
Green Building Final 7/20/2020 Approved STUART CHAPMAN
Green Building Rough 7/20/2020 Approved STUART CHAPMAN
HVAC-Final 7/20/2020 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Final 7/20/2020 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 7/20/2020 SGSOV Approved STUART CHAPMAN
Service/Power Release 7/20/2020 Approved STUART CHAPMAN
Smoke Detectors 7/20/2020 Approved STUART CHAPMAN
Verify Sprinkler Sign Off 7/20/2020 Approved STUART CHAPMAN
Final 7/30/2020 Conditional Approval STUART CHAPMAN
Service/Power Release 8/18/2020 Approved STUART CHAPMAN
Special/Order Compliance 8/8/2023 Corrections Issued JOSH MEISTER
Final 8/15/2023 OK to Issue CofO STUART CHAPMAN