- Application / Permit
- 19010-10000-05224
- Plan Check / Job No.
- B19LA24762
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- PROPOSED 25'-9" x 41'-0" DETACHED ACCESSORY LIVING QUARTER.
- Permit Issued
- Issued on 8/6/2020
- Issuing Office
- Current Status
- CofO Issued on 6/15/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/21/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/26/2019 | MICHAEL LOPEZ |
| Corrections Issued | 12/4/2019 | MICHAEL LOPEZ |
| Quality Review Completed | 12/7/2019 | STANLEY RAAP |
| Building Plans Picked Up | 12/18/2019 | APPLICANT |
| Applicant returned to address corrections | 1/22/2020 | MICHAEL LOPEZ |
| Green Plans Picked Up | 7/7/2020 | APPLICANT |
| Applicant returned to address corrections | 7/23/2020 | MICHAEL LOPEZ |
| Plan Check Approved | 8/6/2020 | MICHAEL LOPEZ |
| Issued | 8/6/2020 | APPLICANT |
| CofO in Progress | 5/29/2021 | ANTHONY MCDOWALL |
| Permit Finaled | 6/15/2021 | VINCENT COTTON |
| CofO Issued | 6/15/2021 | VINCENT COTTON |
| Permit Finaled | 6/15/2021 | VINCENT COTTON |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 1/8/2020 | THOMAS LANG |
| BHO/Hillside ordinance | Cleared | 1/8/2020 | THOMAS LANG |
| BHO/Hillside ordinance | Cleared | 1/8/2020 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 1/8/2020 | THOMAS LANG |
| Sewer availability | Cleared | 1/8/2020 | THOMAS LANG |
| ZA Case | Cleared | 1/8/2020 | TERRI OSBORNE |
| ZA Case | Cleared | 1/8/2020 | TERRI OSBORNE |
| Green Code | Cleared | 1/28/2020 | COLIN LOREDO |
| Low Impact Development | Cleared | 1/29/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 1/29/2020 | EMIL KYUPELYAN |
| Miscellaneous | Cleared | 8/5/2020 | NIKTA MOUSAVI |
| GPI Written Notices | Cleared | 8/6/2020 | VASIL MIHALEV |
| Grading Pre-Inspection | Cleared | 8/6/2020 | VASIL MIHALEV |
Contact Information
| Contractor | Vanceco Inc; Lic. No.: 812260-B | 8335 SUNSET BLVD #400 WEST HOLLYWOOD, CA 90069 |
| Engineer | Irvine,, Jon Alan; Lic. No.: GE2891 | 145 N SIERRA MADRE BLVD STE 1 PASADENA, CA 91107 |
| Engineer | Labib,, Youhanna T; Lic. No.: S4549 | 319 MAIN STREET EL SEGUNDO, CA 90245 |
| Geologist | Irvine,, Jon A; Lic. No.: EG1691 | 819 W HERITAGE OAK CT ALTADENA, CA 91001 |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 8/10/2020 | Corrections Issued | ANTHONY MCDOWALL |
| Piling/Pier/Caisson | 8/12/2020 | Partial Approval | ANTHONY MCDOWALL |
| Piling/Pier/Caisson | 8/19/2020 | Partial Approval | ANTHONY MCDOWALL |
| Footing/Foundation/Slab | 9/1/2020 | Partial Approval | ANTHONY MCDOWALL |
| Footing/Foundation/Slab | 9/11/2020 | Partial Approval | ANTHONY MCDOWALL |
| Underground Mechanical | 9/11/2020 | Partial Approval | ANTHONY MCDOWALL |
| Footing/Foundation/Slab | 9/22/2020 | Partial Approval | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2020 | Partial Approval | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2020 | Approved | ANTHONY MCDOWALL |
| Underground Mechanical | 11/2/2020 | Partial Approval | ANTHONY MCDOWALL |
| Underground Mechanical | 12/3/2020 | Partial Approval | ANTHONY MCDOWALL |
| BUILDING-Rough-Frame | 12/21/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| Green Building Rough | 12/21/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Rough | 12/21/2020 | Corrections Issued | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 12/21/2020 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 12/22/2020 | Corrections Issued | CARLOS MATAMOROS |
| Green Building Rough | 12/22/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 1/5/2021 | Approved | ANTHONY MCDOWALL |
| HVAC-Rough | 1/5/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| PLUMBING-Rough | 1/8/2021 | Corrections Issued | ANTHONY MCDOWALL |
| HVAC-Rough | 1/12/2021 | Approved | ANTHONY MCDOWALL |
| PLUMBING-Rough | 1/12/2021 | Corrections Issued | ANTHONY MCDOWALL |
| Interior/Exterior Lathing | 1/20/2021 | Approved | ANTHONY MCDOWALL |
| PLUMBING-Rough | 1/20/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Interior/Exterior Lathing | 1/25/2021 | Approved | ANTHONY MCDOWALL |
| BUILDING-Rough-Frame | 1/26/2021 | Approved | ANTHONY MCDOWALL |
| ELECTRICAL-Rough | 1/26/2021 | Approved | ANTHONY MCDOWALL |
| Green Building Rough | 1/26/2021 | Approved | ANTHONY MCDOWALL |
| PLUMBING-Rough | 1/26/2021 | Approved | ANTHONY MCDOWALL |
| Insulation | 2/4/2021 | Approved | ANTHONY MCDOWALL |
| Drywall Nailing | 2/10/2021 | Approved | ANTHONY MCDOWALL |
| ELECTRICAL-Final | 3/19/2021 | Corrections Issued | ANTHONY MCDOWALL |
| ELECTRICAL-Final | 3/24/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Special/Order Compliance | 3/24/2021 | Partial Approval | MATT KELLERMAN |
| ELECTRICAL-Final | 3/25/2021 | Approved | ANTHONY MCDOWALL |
| HVAC-Final | 3/25/2021 | Approved | ANTHONY MCDOWALL |
| PLUMBING-Final | 3/25/2021 | Approved | ANTHONY MCDOWALL |
| Final | 4/7/2021 | Corrections Issued | ANTHONY MCDOWALL |
| Footing/Foundation/Slab | 4/7/2021 | Approved | ANTHONY MCDOWALL |
| Green Building Final | 4/7/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| SGSOV-Seismic Gas S/O Valve | 4/7/2021 | SGSOV Approved | ANTHONY MCDOWALL |
| Service/Power Release | 4/7/2021 | Approved | ANTHONY MCDOWALL |
| Smoke Detectors | 4/7/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Final | 4/15/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Green Building Final | 4/15/2021 | Corrections Issued | ANTHONY MCDOWALL |
| Smoke Detectors | 4/15/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Final | 4/20/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Green Building Final | 4/20/2021 | Approved | ANTHONY MCDOWALL |
| Smoke Detectors | 4/20/2021 | Approved | ANTHONY MCDOWALL |
| Final | 4/26/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Final | 5/12/2021 | Partial Approval | ANTHONY MCDOWALL |
| Final | 5/24/2021 | OK to Issue CofO | ANTHONY MCDOWALL |