2955 S MIDVALE AVE 90064
Certificate Information: 2955 S MIDVALE AVE 90064
- Application / Permit
- 19010-10000-05193
- Plan Check / Job No.
- B19LA24550
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 78SQ.FT ADDITION TO (E) GARAGE, AND NEW 1158SQ.FT ATTACHED ACCESSORY DWELLING UNIT PER AB494 AND AB229. [(N) 2ND-STORY ADU OVER (E) ONE-CAR GARAGE.]
- Permit Issued
- Issued on 2/7/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 7/1/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/18/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/26/2019 | RAHEL BEYENE |
| Corrections Issued | 12/2/2019 | RAHEL BEYENE |
| Quality Review Completed | 12/7/2019 | STANLEY RAAP |
| Building Plans Picked Up | 12/13/2019 | APPLICANT |
| Green Plans Picked Up | 12/16/2019 | APPLICANT |
| Applicant returned to address corrections | 1/16/2020 | RAHEL BEYENE |
| Plan Check Approved | 1/17/2020 | RAHEL BEYENE |
| Issued | 2/7/2020 | LADBS |
| CofO in Progress | 6/17/2021 | EVAN COOPER |
| CofO in Progress | 6/23/2021 | EVAN COOPER |
| Permit Finaled | 7/1/2021 | KENNETH NAGLE |
| CofO Issued | 7/1/2021 | KENNETH NAGLE |
| Permit Finaled | 7/1/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Construction near power lines | Cleared | 1/7/2020 | WALTER RAMIREZ |
| Miscellaneous | Cleared | 1/7/2020 | ANNA VIDAL |
| Miscellaneous | Cleared | 1/7/2020 | ANNA VIDAL |
| Grading Pre-Inspection | Cleared | 1/14/2020 | PATRICK MISCHLICH |
| Address approval | Cleared | 1/16/2020 | ELENA LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/16/2020 | ELENA LOPEZ |
| GPI Written Notices | Cleared | 1/16/2020 | RAHEL BEYENE |
| Green Code | Cleared | 1/16/2020 | KHEDER ALRAZAA |
| Hydrant and Access approval | Cleared | 1/16/2020 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 1/16/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 1/16/2020 | ELENA LOPEZ |
| Sewer availability | Cleared | 1/16/2020 | ELENA LOPEZ |
Contact Information
| Contractor | Kravitz Oded General Contractor Inc; Lic. No.: 1009679-B | 3246 VETERAN AVE LOS ANGELES, CA 90034 |
| Engineer | Cohanfard,, Albert; Lic. No.: C45408 | 910 S BEDFORD ST 304 LOS ANGELES, CA 90035 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/9/2020 | Conditional Approval | KEVIN BEAULIEU |
| Floor/Roof Diaphrgm/Shear Wall | 4/27/2020 | Partial Approval | TIM CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2020 | No Access for Inspection | KENNETH NAGLE |
| HVAC-Rough | 6/3/2020 | No Access for Inspection | KENNETH NAGLE |
| PLUMBING-Rough | 6/3/2020 | No Access for Inspection | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2020 | Not Ready for Inspection | JUSTIN CURTIS |
| HVAC-Rough | 6/17/2020 | Not Ready for Inspection | JUSTIN CURTIS |
| PLUMBING-Rough | 6/17/2020 | Not Ready for Inspection | JUSTIN CURTIS |
| ELECTRICAL-Rough | 6/26/2020 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2020 | Partial Approval | KEVIN SARGSYAN |
| HVAC-Rough | 6/26/2020 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 6/26/2020 | Corrections Issued | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 6/29/2020 | Not Ready for Inspection | JUSTIN CURTIS |
| Green Building Rough | 6/29/2020 | Not Ready for Inspection | JUSTIN CURTIS |
| MERV13>=Rough | 6/29/2020 | Not Ready for Inspection | JUSTIN CURTIS |
| PLUMBING-Rough | 6/29/2020 | Approved | JUSTIN CURTIS |
| BUILDING-Rough-Frame | 7/8/2020 | Partial Approval | JUSTIN CURTIS |
| Green Building Rough | 7/8/2020 | Not Ready for Inspection | JUSTIN CURTIS |
| Interior/Exterior Lathing | 7/8/2020 | Approved | JUSTIN CURTIS |
| MERV13>=Rough | 7/8/2020 | Not Ready for Inspection | JUSTIN CURTIS |
| Shower Pan | 7/8/2020 | Approved | JUSTIN CURTIS |
| Insulation | 7/10/2020 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 7/15/2020 | Not Ready for Inspection | JUSTIN CURTIS |
| Green Building Rough | 7/15/2020 | Not Ready for Inspection | JUSTIN CURTIS |
| Interior/Exterior Lathing | 7/15/2020 | Not Ready for Inspection | JUSTIN CURTIS |
| Drywall Nailing | 7/17/2020 | Partial Approval | JUSTIN CURTIS |
| ELECTRICAL-Final | 11/19/2020 | Corrections Issued | RICHARD ROBLES |
| Service/Power Release | 11/19/2020 | Not Ready for Inspection | RICHARD ROBLES |
| Service/Power Release | 12/1/2020 | Approved | RICHARD ROBLES |
| SGSOV-Seismic Gas S/O Valve | 3/26/2021 | SGSOV Not Ready | EVAN COOPER |
| BUILDING-Rough-Frame | 4/22/2021 | Approved | EVAN COOPER |
| Drywall Nailing | 4/22/2021 | Approved | EVAN COOPER |
| Final | 4/22/2021 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 4/22/2021 | Approved | EVAN COOPER |
| Green Building Final | 4/22/2021 | Not Ready for Inspection | EVAN COOPER |
| Green Building Rough | 4/22/2021 | Approved | EVAN COOPER |
| MERV13>=Final | 4/22/2021 | Not Ready for Inspection | EVAN COOPER |
| MERV13>=Rough | 4/22/2021 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 4/22/2021 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 4/22/2021 | Approved | EVAN COOPER |
| Final | 5/19/2021 | Not Ready for Inspection | EVAN COOPER |
| Green Building Final | 5/19/2021 | Not Ready for Inspection | EVAN COOPER |
| MERV13>=Final | 5/19/2021 | Not Ready for Inspection | EVAN COOPER |
| Final | 6/8/2021 | Conditional Approval | EVAN COOPER |
| Green Building Final | 6/8/2021 | Approved | EVAN COOPER |
| MERV13>=Final | 6/8/2021 | Approved | EVAN COOPER |
| Final | 6/23/2021 | OK to Issue CofO | EVAN COOPER |