3025 S WALTON AVE 90007

Certificate Information: 3025 S WALTON AVE 90007

Application / Permit
19010-10000-05147
Plan Check / Job No.
B19LA24438
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 3 STORY SINGLE FAMILY DWELLING (FRONT)
Permit Issued
Issued on 4/10/2020
Issuing Office
Metro
Current Status
CofO Issued on 4/15/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/15/2019 APPLICANT
Assigned to Plan Check Engineer 12/5/2019 FERNANDO FLORES
Corrections Issued 12/12/2019 FERNANDO FLORES
Green Plans Picked Up 12/20/2019 APPLICANT
Quality Review Completed 12/27/2019 ARMEN JIVALAGIAN
Building Plans Picked Up 1/2/2020 APPLICANT
Applicant returned to address corrections 1/13/2020 FERNANDO FLORES
Applicant returned to address corrections 1/21/2020 FERNANDO FLORES
Plan Check Approved 3/4/2020 FERNANDO FLORES
Issued 4/10/2020 LADBS
CofO in Progress 3/23/2021 KATHRYN BUTTERWORTH
Permit Finaled 4/15/2021 DEROLD HAUFF
CofO Issued 4/15/2021 DEROLD HAUFF
Permit Finaled 4/15/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/21/2020 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 1/21/2020 EMIL KYUPELYAN
Permit Cleared 1/21/2020 EMIL KYUPELYAN
Sewer availability Cleared 1/21/2020 EMIL KYUPELYAN
Green Code Cleared 1/30/2020 FERNANDO FLORES
Hydrant and Access approval Cleared 1/30/2020 GEORGE SUCHAND
Trees in Parkway Cleared 2/5/2020 JOHN KIM
Frnt yard landscape/Water mgmt Cleared 3/3/2020 RUBEN VASQUEZ
Low Impact Development Cleared 3/4/2020 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 3/4/2020 ELAINE LEI

Contact Information

Architect Yung,, Paul H; Lic. No.: C28869 5558 VALERIO TRAIL      SAN DIEGO, CA 92130
Contractor Soft Story Pros; Lic. No.: 1032036-B P O BOX 35351      LOS ANGELES, CA 90035
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/27/2020 Partial Approval KATHRYN BUTTERWORTH
Footing/Foundation/Slab 4/27/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
METHANE-Barrier 4/27/2020 Approved KATHRYN BUTTERWORTH
METHANE-Subgrade 4/27/2020 Approved KATHRYN BUTTERWORTH
Underground Mechanical 4/27/2020 Partial Approval KATHRYN BUTTERWORTH
Footing/Foundation/Slab 4/29/2020 Approved KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 5/8/2020 Corrections Issued KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 5/11/2020 Partial Approval KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 5/19/2020 Partial Approval KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 5/29/2020 Partial Approval KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 6/11/2020 Not Ready for Inspection JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 7/17/2020 Conditional Approval DAVID CHAN
Floor/Roof Diaphrgm/Shear Wall 8/13/2020 Corrections Issued KATHRYN BUTTERWORTH
HVAC-Rough 8/17/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
PLUMBING-Rough 8/17/2020 Corrections Issued KATHRYN BUTTERWORTH
ELECTRICAL-Rough 8/19/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
HVAC-Rough 8/19/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
PLUMBING-Rough 8/19/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 8/28/2020 Partial Approval KATHRYN BUTTERWORTH
ELECTRICAL-Rough 8/28/2020 Approved KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 8/28/2020 Partial Approval KATHRYN BUTTERWORTH
Green Building Rough 8/28/2020 Approved KATHRYN BUTTERWORTH
HVAC-Rough 8/28/2020 Approved KATHRYN BUTTERWORTH
METHANE-Rough 8/28/2020 Approved KATHRYN BUTTERWORTH
PLUMBING-Rough 8/28/2020 Approved KATHRYN BUTTERWORTH
Verify Sprinkler Sign Off 8/28/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
Wood Frame 8/28/2020 Partial Approval KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 9/1/2020 Approved KATHRYN BUTTERWORTH
Insulation 9/1/2020 Corrections Issued KATHRYN BUTTERWORTH
Verify Sprinkler Sign Off 9/1/2020 Approved KATHRYN BUTTERWORTH
Drywall Nailing 9/14/2020 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 9/14/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
Interior/Exterior Lathing 9/18/2020 Partial Approval STUART CHAPMAN
Sewer 12/1/2020 Approved DAVID FEILER
Final 3/4/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Green Building Final 3/4/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 3/4/2021 SGSOV Approved KATHRYN BUTTERWORTH
Service/Power Release 3/4/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Smoke Detectors 3/4/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 3/11/2021 OK to Issue CofO KATHRYN BUTTERWORTH
Green Building Final 3/11/2021 Approved KATHRYN BUTTERWORTH
Service/Power Release 3/11/2021 Approved KATHRYN BUTTERWORTH
Smoke Detectors 3/11/2021 Approved KATHRYN BUTTERWORTH