546 W 111TH PL 90044
Certificate Information: 546 W 111TH PL 90044
- Application / Permit
- 19010-10000-05141
- Plan Check / Job No.
- B19LA24378
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2 STORY ADU PER AB 494 & SB 229.
- Permit Issued
- Issued on 4/15/2021
- Issuing Office
- Current Status
- CofO Issued on 2/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/15/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/22/2019 | STARR CHEN |
| Corrections Issued | 12/10/2019 | STARR CHEN |
| Quality Review Completed | 12/13/2019 | JASON HEALEY |
| Green Plans Picked Up | 12/19/2019 | APPLICANT |
| Building Plans Picked Up | 12/20/2019 | APPLICANT |
| Plan Check Approved | 3/26/2021 | STARR CHEN |
| Issued | 4/15/2021 | APPLICANT |
| CofO in Progress | 1/25/2023 | JAMES CHAVEZ |
| CofO Issued | 2/6/2023 | ANSON MAGLASANG |
| Permit Finaled | 2/6/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 5/29/2020 | CECILIO NAVARRO |
| Hydrant and Access approval | Cleared | 6/2/2020 | GEORGE SUCHAND |
| Eng Process Fee Ord 176,300 | Cleared | 7/10/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 7/10/2020 | CECILIO NAVARRO |
| Low Impact Development | Cleared | 2/4/2021 | MARTIN FRAGOSO |
| Green Code | Cleared | 3/16/2021 | KHEDER ALRAZAA |
| Roof/Waste drainage to street | Cleared | 3/18/2021 | ROSA SILVA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/14/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 11/12/2021 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 11/12/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Footing/Foundation/Slab | 11/19/2021 | Approved | EUGENE CASSIDY |
| Underground Mechanical | 11/19/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Rough | 12/8/2021 | Corrections Issued | JOHN KLARIN |
| Underground Mechanical | 12/8/2021 | Corrections Issued | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2021 | Partial Approval | EUGENE CASSIDY |
| PLUMBING-Rough | 12/13/2021 | Partial Approval | EUGENE CASSIDY |
| Sewer | 12/13/2021 | Approved | EUGENE CASSIDY |
| Underground Mechanical | 12/13/2021 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 12/16/2021 | Partial Approval | EUGENE CASSIDY |
| Green Building Rough | 12/16/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Insulation | 12/16/2021 | Partial Approval | EUGENE CASSIDY |
| Verify Sprinkler Sign Off | 12/16/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Wood Frame | 12/23/2021 | Partial Approval | ANSON MAGLASANG |
| Wood Frame | 1/27/2022 | Partial Approval | EUGENE CASSIDY |
| Wood Frame | 2/17/2022 | Corrections Issued | ANSON MAGLASANG |
| ELECTRICAL-Rough | 3/7/2022 | Not Ready for Inspection | JOHN KLARIN |
| Wood Frame | 3/7/2022 | Partial Approval | JOHN KLARIN |
| ELECTRICAL-Rough | 4/5/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 4/5/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Wood Frame | 4/5/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 4/8/2022 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 4/8/2022 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 5/2/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2022 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 5/2/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 5/2/2022 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 5/6/2022 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 5/6/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Rough | 5/6/2022 | Approved | ALIZAH MAYAGOITIA |
| Shower Pan | 5/6/2022 | Approved | ALIZAH MAYAGOITIA |
| Wood Frame | 5/6/2022 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 5/11/2022 | Conditional Approval | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 5/11/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Drywall Nailing | 5/18/2022 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 5/18/2022 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 5/18/2022 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 5/18/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 7/13/2022 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 11/1/2022 | Not Ready for Inspection | JOHN KLARIN |
| Final | 11/1/2022 | Corrections Issued | JOHN KLARIN |
| Gas Test | 11/1/2022 | Not Ready for Inspection | JOHN KLARIN |
| Green Building Final | 11/1/2022 | Not Ready for Inspection | JOHN KLARIN |
| HVAC-Final | 11/1/2022 | Not Ready for Inspection | JOHN KLARIN |
| PLUMBING-Final | 11/1/2022 | Not Ready for Inspection | JOHN KLARIN |
| ELECTRICAL-Final | 11/9/2022 | Corrections Issued | JOHN KLARIN |
| ELECTRICAL-Final | 11/9/2022 | Not Ready for Inspection | JOHN KLARIN |
| Final | 11/9/2022 | Corrections Issued | JOHN KLARIN |
| Gas Test | 11/9/2022 | Approved | JOHN KLARIN |
| Green Building Final | 11/9/2022 | Corrections Issued | JOHN KLARIN |
| HVAC-Final | 11/9/2022 | Approved | JOHN KLARIN |
| PLUMBING-Final | 11/9/2022 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 11/9/2022 | SGSOV Approved | JOHN KLARIN |
| Service/Power Release | 11/9/2022 | Not Ready for Inspection | JOHN KLARIN |
| Smoke Detectors | 11/9/2022 | Corrections Issued | JOHN KLARIN |
| ELECTRICAL-Final | 11/29/2022 | Not Ready for Inspection | JOHN KLARIN |
| Final | 11/29/2022 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 11/29/2022 | Not Ready for Inspection | JOHN KLARIN |
| Service/Power Release | 11/29/2022 | Not Ready for Inspection | JOHN KLARIN |
| Smoke Detectors | 11/29/2022 | Not Ready for Inspection | JOHN KLARIN |
| ELECTRICAL-Final | 12/14/2022 | No Access for Inspection | JAMES CHAVEZ |
| Final | 12/14/2022 | No Access for Inspection | JAMES CHAVEZ |
| Green Building Final | 12/14/2022 | No Access for Inspection | JAMES CHAVEZ |
| Service/Power Release | 12/14/2022 | No Access for Inspection | JAMES CHAVEZ |
| Smoke Detectors | 12/14/2022 | No Access for Inspection | JAMES CHAVEZ |
| ELECTRICAL-Final | 12/21/2022 | Approved | JAMES CHAVEZ |
| Service/Power Release | 12/21/2022 | Approved | JAMES CHAVEZ |
| Final | 1/5/2023 | OK to Issue CofO | JAMES CHAVEZ |
| Green Building Final | 1/5/2023 | Approved | JAMES CHAVEZ |
| Smoke Detectors | 1/5/2023 | Approved | JAMES CHAVEZ |