NEW 2 STORY ADU PER AB 494 & SB 229.
Permit Issued
Issued on 4/15/2021
Issuing Office
Current Status
CofO Issued on 2/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/15/2019 APPLICANT
Assigned to Plan Check Engineer 11/22/2019 STARR CHEN
Corrections Issued 12/10/2019 STARR CHEN
Quality Review Completed 12/13/2019 JASON HEALEY
Green Plans Picked Up 12/19/2019 APPLICANT
Building Plans Picked Up 12/20/2019 APPLICANT
Plan Check Approved 3/26/2021 STARR CHEN
Issued 4/15/2021 APPLICANT
CofO in Progress 1/25/2023 JAMES CHAVEZ
CofO Issued 2/6/2023 ANSON MAGLASANG
Permit Finaled 2/6/2023 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 5/29/2020 CECILIO NAVARRO
Hydrant and Access approval Cleared 6/2/2020 GEORGE SUCHAND
Eng Process Fee Ord 176,300 Cleared 7/10/2020 CECILIO NAVARRO
Sewer availability Cleared 7/10/2020 CECILIO NAVARRO
Low Impact Development Cleared 2/4/2021 MARTIN FRAGOSO
Green Code Cleared 3/16/2021 KHEDER ALRAZAA
Roof/Waste drainage to street Cleared 3/18/2021 ROSA SILVA

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/14/2021 Not Ready for Inspection EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 11/12/2021 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 11/12/2021 Not Ready for Inspection EUGENE CASSIDY
Footing/Foundation/Slab 11/19/2021 Approved EUGENE CASSIDY
Underground Mechanical 11/19/2021 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Rough 12/8/2021 Corrections Issued JOHN KLARIN
Underground Mechanical 12/8/2021 Corrections Issued JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 12/13/2021 Partial Approval EUGENE CASSIDY
PLUMBING-Rough 12/13/2021 Partial Approval EUGENE CASSIDY
Sewer 12/13/2021 Approved EUGENE CASSIDY
Underground Mechanical 12/13/2021 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 12/16/2021 Partial Approval EUGENE CASSIDY
Green Building Rough 12/16/2021 Not Ready for Inspection EUGENE CASSIDY
Insulation 12/16/2021 Partial Approval EUGENE CASSIDY
Verify Sprinkler Sign Off 12/16/2021 Not Ready for Inspection EUGENE CASSIDY
Wood Frame 12/23/2021 Partial Approval ANSON MAGLASANG
Wood Frame 1/27/2022 Partial Approval EUGENE CASSIDY
Wood Frame 2/17/2022 Corrections Issued ANSON MAGLASANG
ELECTRICAL-Rough 3/7/2022 Not Ready for Inspection JOHN KLARIN
Wood Frame 3/7/2022 Partial Approval JOHN KLARIN
ELECTRICAL-Rough 4/5/2022 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Rough 4/5/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Wood Frame 4/5/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
ELECTRICAL-Rough 4/8/2022 Approved JOHN KLARIN
PLUMBING-Rough 4/8/2022 Approved JOHN KLARIN
BUILDING-Rough-Frame 5/2/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 5/2/2022 Approved ALIZAH MAYAGOITIA
Green Building Rough 5/2/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 5/2/2022 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 5/6/2022 Approved ALIZAH MAYAGOITIA
Green Building Rough 5/6/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
HVAC-Rough 5/6/2022 Approved ALIZAH MAYAGOITIA
Shower Pan 5/6/2022 Approved ALIZAH MAYAGOITIA
Wood Frame 5/6/2022 Approved ALIZAH MAYAGOITIA
Insulation 5/11/2022 Conditional Approval ALIZAH MAYAGOITIA
Interior/Exterior Lathing 5/11/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Drywall Nailing 5/18/2022 Approved ALIZAH MAYAGOITIA
Green Building Rough 5/18/2022 Approved ALIZAH MAYAGOITIA
Insulation 5/18/2022 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 5/18/2022 Partial Approval ALIZAH MAYAGOITIA
Interior/Exterior Lathing 7/13/2022 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 11/1/2022 Not Ready for Inspection JOHN KLARIN
Final 11/1/2022 Corrections Issued JOHN KLARIN
Gas Test 11/1/2022 Not Ready for Inspection JOHN KLARIN
Green Building Final 11/1/2022 Not Ready for Inspection JOHN KLARIN
HVAC-Final 11/1/2022 Not Ready for Inspection JOHN KLARIN
PLUMBING-Final 11/1/2022 Not Ready for Inspection JOHN KLARIN
ELECTRICAL-Final 11/9/2022 Corrections Issued JOHN KLARIN
ELECTRICAL-Final 11/9/2022 Not Ready for Inspection JOHN KLARIN
Final 11/9/2022 Corrections Issued JOHN KLARIN
Gas Test 11/9/2022 Approved JOHN KLARIN
Green Building Final 11/9/2022 Corrections Issued JOHN KLARIN
HVAC-Final 11/9/2022 Approved JOHN KLARIN
PLUMBING-Final 11/9/2022 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 11/9/2022 SGSOV Approved JOHN KLARIN
Service/Power Release 11/9/2022 Not Ready for Inspection JOHN KLARIN
Smoke Detectors 11/9/2022 Corrections Issued JOHN KLARIN
ELECTRICAL-Final 11/29/2022 Not Ready for Inspection JOHN KLARIN
Final 11/29/2022 Corrections Issued JOHN KLARIN
Green Building Final 11/29/2022 Not Ready for Inspection JOHN KLARIN
Service/Power Release 11/29/2022 Not Ready for Inspection JOHN KLARIN
Smoke Detectors 11/29/2022 Not Ready for Inspection JOHN KLARIN
ELECTRICAL-Final 12/14/2022 No Access for Inspection JAMES CHAVEZ
Final 12/14/2022 No Access for Inspection JAMES CHAVEZ
Green Building Final 12/14/2022 No Access for Inspection JAMES CHAVEZ
Service/Power Release 12/14/2022 No Access for Inspection JAMES CHAVEZ
Smoke Detectors 12/14/2022 No Access for Inspection JAMES CHAVEZ
ELECTRICAL-Final 12/21/2022 Approved JAMES CHAVEZ
Service/Power Release 12/21/2022 Approved JAMES CHAVEZ
Final 1/5/2023 OK to Issue CofO JAMES CHAVEZ
Green Building Final 1/5/2023 Approved JAMES CHAVEZ
Smoke Detectors 1/5/2023 Approved JAMES CHAVEZ