456-458 N MUSEUM DR 90065

Certificate Information: 456-458 N MUSEUM DR 90065

Application / Permit
19010-10000-05080
Plan Check / Job No.
B19LA24174
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) SINGLE FAMILY DWELLING, ACCESSORY DWELLING UNIT PER AB 494 & SB 229 ON 1ST FLOOR, & GARAGE ON BASEMENT LEVEL
Permit Issued
Issued on 10/13/2020
Issuing Office
Current Status
CofO Issued on 8/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/13/2019 APPLICANT
Assigned to Plan Check Engineer 11/22/2019 LAMAR DAVIS
Corrections Issued 11/26/2019 LAMAR DAVIS
Quality Review Completed 12/10/2019 HERNAN ARREOLA
Building Plans Picked Up 12/10/2019 APPLICANT
Applicant returned to address corrections 12/16/2019 LAMAR DAVIS
Applicant returned to address corrections 3/3/2020 LAMAR DAVIS
Green Plans Picked Up 4/17/2020 APPLICANT
Plan Check Approved 4/29/2020 LAMAR DAVIS
Issued 10/13/2020 APPLICANT
CofO in Progress 7/19/2023 OSVALDO PARAMO
CofO in Progress 7/19/2023 OSVALDO PARAMO
Permit Finaled 8/7/2023 DEROLD HAUFF
CofO Issued 8/7/2023 DEROLD HAUFF
Permit Finaled 8/7/2023 DEROLD HAUFF

Permit Application Clearance Information

GPI Written Notices Cleared 11/27/2019 ALEXANDER HELFER
Grading Pre-Inspection Cleared 11/27/2019 ALEXANDER HELFER
Address approval Cleared 1/16/2020 JUAN ASHTON
Eng Process Fee Ord 176,300 Cleared 1/16/2020 JUAN ASHTON
BHO/Hillside ordinance Cleared 2/4/2020 THAN WIN
BHO/Hillside ordinance Cleared 2/4/2020 THAN WIN
Trees in Parkway Cleared 2/4/2020 JOHN KIM
BHO/Hillside ordinance Cleared 2/6/2020 JUAN ASHTON
Hydrant and Access approval Cleared 2/6/2020 JEREMY CARTER
Permit Cleared 2/6/2020 JUAN ASHTON
Sewer availability Cleared 2/6/2020 JUAN ASHTON
Low Impact Development Cleared 2/12/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 2/12/2020 THOMAS LANG
Green Code Cleared 2/18/2020 DONALD CRICHLOW
Excavation more than 5-ft deep Cleared 2/19/2020 CALOSHA APPROVED
Miscellaneous Cleared 2/19/2020 LAMAR DAVIS
Miscellaneous Cleared 2/25/2020 TERRI OSBORNE
Specific Plan Cleared 2/25/2020 TERRI OSBORNE

Contact Information

Architect Gonzalez,, David; Lic. No.: C34529 1719 MADISON AVENUE      PASADENA, CA 91104
Contractor B M Construction Llc; Lic. No.: 1066119-B 568 MT WASHINGTON DRIVE      LOS ANGELES, CA 90065
Engineer De, Leon, Cynthia Aguilar; Lic. No.: C31604 8061 SAN MATEO CIR      BUENA PARK, CA 90620
Engineer Irvine,, Jon Alan; Lic. No.: GE2891 145 N SIERRA MADRE BLVD STE 1      PASADENA, CA 91107
Engineer Le,, Thang Huu; Lic. No.: C63174 507 MAGELLAN RD      ARCADIA, CA 91007
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007
Geologist Irvine,, Jon A; Lic. No.: EG1691 819 W HERITAGE OAK CT      ALTADENA, CA 91001

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Grading Pre-Inspection 12/7/2020 Not Ready for Inspection OSVALDO PARAMO
Pre-Inspection 12/7/2020 Approved OSVALDO PARAMO
Piling/Pier/Caisson 12/23/2020 Partial Approval OSVALDO PARAMO
Deputy Reinf. Concrete 12/29/2020 Partial Approval OSVALDO PARAMO
Deputy Reinf. Concrete 1/13/2021 Partial Approval OSVALDO PARAMO
Piling/Pier/Caisson 1/14/2021 Partial Approval OSVALDO PARAMO
Deputy Reinf. Concrete 1/19/2021 Partial Approval OSVALDO PARAMO
Deputy Reinf. Concrete 1/20/2021 Partial Approval OSVALDO PARAMO
Piling/Pier/Caisson 1/21/2021 Partial Approval OSVALDO PARAMO
Deputy Reinf. Concrete 2/3/2021 Partial Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 2/4/2021 Not Ready for Inspection OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 2/18/2021 Partial Approval OSVALDO PARAMO
Deputy Reinf. Concrete 3/4/2021 Partial Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 3/4/2021 Partial Inspection OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 3/19/2021 Partial Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 3/22/2021 Not Ready for Inspection OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 3/25/2021 Partial Approval OSVALDO PARAMO
Deputy Reinf. Concrete 3/26/2021 Partial Approval OSVALDO PARAMO
Masonry Wall/Backfill 4/10/2021 Partial Approval JOHN HAYES
Footing/Foundation/Slab 6/10/2021 Not Ready for Inspection OSVALDO PARAMO
Deputy Reinf. Concrete 6/16/2021 Approved ALFREDO BALANDRA
Footing/Foundation/Slab 6/17/2021 Partial Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 7/12/2021 Not Ready for Inspection OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 7/13/2021 Partial Inspection OSVALDO PARAMO
Deputy Drilled-In Anchors 7/19/2021 Partial Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 7/19/2021 Not Ready for Inspection OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 7/20/2021 Partial Approval OSVALDO PARAMO
Deputy Reinf. Concrete 7/29/2021 Conditional Approval THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 9/21/2021 Partial Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 10/13/2021 Not Ready for Inspection OSVALDO PARAMO
Deputy Reinf. Concrete 10/21/2021 Partial Approval OSVALDO PARAMO
Underground Mechanical 11/1/2021 Not Ready for Inspection OSVALDO PARAMO
Underground Mechanical 11/2/2021 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Rough 11/4/2021 Partial Approval OSVALDO PARAMO
ELECTRICAL-Rough 11/8/2021 Partial Approval ARTHUR SARGSYAN
Footing/Foundation/Slab 11/8/2021 Partial Approval ARTHUR SARGSYAN
Excavation/Setback/Form/Re-Bar 12/6/2021 Partial Approval OSVALDO PARAMO
Special/Order Compliance 2/2/2022 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 3/4/2022 Corrections Issued OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 6/9/2022 Approved OSVALDO PARAMO
Green Building Rough 6/9/2022 Not Ready for Inspection OSVALDO PARAMO
Verify Sprinkler Sign Off 6/9/2022 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Rough 6/14/2022 Approved OSVALDO PARAMO
ELECTRICAL-Rough 7/28/2022 Not Ready for Inspection OSVALDO PARAMO
HVAC-Rough 7/28/2022 Approved OSVALDO PARAMO
ELECTRICAL-Rough 8/2/2022 Partial Approval OSVALDO PARAMO
HVAC-Rough 8/2/2022 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 8/5/2022 Approved OSVALDO PARAMO
Green Building Rough 8/5/2022 Approved OSVALDO PARAMO
Verify Sprinkler Sign Off 8/5/2022 Approved OSVALDO PARAMO
Insulation 8/16/2022 Approved OSVALDO PARAMO
ELECTRICAL-Rough 9/1/2022 Approved OSVALDO PARAMO
Interior/Exterior Lathing 9/7/2022 Partial Approval OSVALDO PARAMO
Interior/Exterior Lathing 9/12/2022 Partial Approval OSVALDO PARAMO
Drywall Nailing 9/20/2022 Not Ready for Inspection OSVALDO PARAMO
Interior/Exterior Lathing 9/21/2022 Approved OSVALDO PARAMO
Drywall Nailing 9/26/2022 Approved OSVALDO PARAMO
Sewer 12/7/2022 Approved OSVALDO PARAMO
Underground Mechanical 12/7/2022 Approved OSVALDO PARAMO
Service/Power Release 1/23/2023 Not Ready for Inspection OSVALDO PARAMO
Gas Test 1/24/2023 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 1/24/2023 SGSOV Approved ALIZAH MAYAGOITIA
PLUMBING-Final 1/27/2023 Approved SCOTT FINNILA
ELECTRICAL-Final 1/30/2023 Corrections Issued OSVALDO PARAMO
ELECTRICAL-Final 2/7/2023 Partial Approval OSVALDO PARAMO
HVAC-Final 2/7/2023 Partial Approval OSVALDO PARAMO
ELECTRICAL-Final 2/17/2023 Approved OSVALDO PARAMO
Grounding or Bonding 3/29/2023 Partial Inspection OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 4/3/2023 Approved OSVALDO PARAMO
Grounding or Bonding 4/3/2023 Approved OSVALDO PARAMO
HVAC-Final 4/24/2023 Corrections Issued ALIZAH MAYAGOITIA
Final 5/1/2023 Corrections Issued OSVALDO PARAMO
Footing/Foundation/Slab 5/1/2023 Approved OSVALDO PARAMO
Green Building Final 5/1/2023 Approved OSVALDO PARAMO
HVAC-Final 5/1/2023 Approved OSVALDO PARAMO
Service/Power Release 5/1/2023 Not Ready for Inspection OSVALDO PARAMO
Smoke Detectors 5/1/2023 Approved OSVALDO PARAMO
Final 6/27/2023 Corrections Issued OSVALDO PARAMO
Service/Power Release 6/27/2023 Approved OSVALDO PARAMO
Final 7/5/2023 OK to Issue CofO OSVALDO PARAMO