Grading Pre-Inspection
|
12/7/2020
|
Not Ready for Inspection
|
OSVALDO PARAMO
|
|
Pre-Inspection
|
12/7/2020
|
Approved
|
OSVALDO PARAMO
|
|
Piling/Pier/Caisson
|
12/23/2020
|
Partial Approval
|
OSVALDO PARAMO
|
|
Deputy Reinf. Concrete
|
12/29/2020
|
Partial Approval
|
OSVALDO PARAMO
|
|
Deputy Reinf. Concrete
|
1/13/2021
|
Partial Approval
|
OSVALDO PARAMO
|
|
Piling/Pier/Caisson
|
1/14/2021
|
Partial Approval
|
OSVALDO PARAMO
|
|
Deputy Reinf. Concrete
|
1/19/2021
|
Partial Approval
|
OSVALDO PARAMO
|
|
Deputy Reinf. Concrete
|
1/20/2021
|
Partial Approval
|
OSVALDO PARAMO
|
|
Piling/Pier/Caisson
|
1/21/2021
|
Partial Approval
|
OSVALDO PARAMO
|
|
Deputy Reinf. Concrete
|
2/3/2021
|
Partial Approval
|
OSVALDO PARAMO
|
|
Excavation/Setback/Form/Re-Bar
|
2/4/2021
|
Not Ready for Inspection
|
OSVALDO PARAMO
|
|
Excavation/Setback/Form/Re-Bar
|
2/18/2021
|
Partial Approval
|
OSVALDO PARAMO
|
|
Deputy Reinf. Concrete
|
3/4/2021
|
Partial Approval
|
OSVALDO PARAMO
|
|
Excavation/Setback/Form/Re-Bar
|
3/4/2021
|
Partial Inspection
|
OSVALDO PARAMO
|
|
Excavation/Setback/Form/Re-Bar
|
3/19/2021
|
Partial Approval
|
OSVALDO PARAMO
|
|
Excavation/Setback/Form/Re-Bar
|
3/22/2021
|
Not Ready for Inspection
|
OSVALDO PARAMO
|
|
Excavation/Setback/Form/Re-Bar
|
3/25/2021
|
Partial Approval
|
OSVALDO PARAMO
|
|
Deputy Reinf. Concrete
|
3/26/2021
|
Partial Approval
|
OSVALDO PARAMO
|
|
Masonry Wall/Backfill
|
4/10/2021
|
Partial Approval
|
JOHN HAYES
|
|
Footing/Foundation/Slab
|
6/10/2021
|
Not Ready for Inspection
|
OSVALDO PARAMO
|
|
Deputy Reinf. Concrete
|
6/16/2021
|
Approved
|
ALFREDO BALANDRA
|
|
Footing/Foundation/Slab
|
6/17/2021
|
Partial Approval
|
OSVALDO PARAMO
|
|
Excavation/Setback/Form/Re-Bar
|
7/12/2021
|
Not Ready for Inspection
|
OSVALDO PARAMO
|
|
Excavation/Setback/Form/Re-Bar
|
7/13/2021
|
Partial Inspection
|
OSVALDO PARAMO
|
|
Deputy Drilled-In Anchors
|
7/19/2021
|
Partial Approval
|
OSVALDO PARAMO
|
|
Excavation/Setback/Form/Re-Bar
|
7/19/2021
|
Not Ready for Inspection
|
OSVALDO PARAMO
|
|
Excavation/Setback/Form/Re-Bar
|
7/20/2021
|
Partial Approval
|
OSVALDO PARAMO
|
|
Deputy Reinf. Concrete
|
7/29/2021
|
Conditional Approval
|
THOMAS LOGRASSO
|
|
Excavation/Setback/Form/Re-Bar
|
9/21/2021
|
Partial Approval
|
OSVALDO PARAMO
|
|
Excavation/Setback/Form/Re-Bar
|
10/13/2021
|
Not Ready for Inspection
|
OSVALDO PARAMO
|
|
Deputy Reinf. Concrete
|
10/21/2021
|
Partial Approval
|
OSVALDO PARAMO
|
|
Underground Mechanical
|
11/1/2021
|
Not Ready for Inspection
|
OSVALDO PARAMO
|
|
Underground Mechanical
|
11/2/2021
|
Not Ready for Inspection
|
OSVALDO PARAMO
|
|
PLUMBING-Rough
|
11/4/2021
|
Partial Approval
|
OSVALDO PARAMO
|
|
ELECTRICAL-Rough
|
11/8/2021
|
Partial Approval
|
ARTHUR SARGSYAN
|
|
Footing/Foundation/Slab
|
11/8/2021
|
Partial Approval
|
ARTHUR SARGSYAN
|
|
Excavation/Setback/Form/Re-Bar
|
12/6/2021
|
Partial Approval
|
OSVALDO PARAMO
|
|
Special/Order Compliance
|
2/2/2022
|
Approved
|
MICHAEL LEWIS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/4/2022
|
Corrections Issued
|
OSVALDO PARAMO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/9/2022
|
Approved
|
OSVALDO PARAMO
|
|
Green Building Rough
|
6/9/2022
|
Not Ready for Inspection
|
OSVALDO PARAMO
|
|
Verify Sprinkler Sign Off
|
6/9/2022
|
Not Ready for Inspection
|
OSVALDO PARAMO
|
|
PLUMBING-Rough
|
6/14/2022
|
Approved
|
OSVALDO PARAMO
|
|
ELECTRICAL-Rough
|
7/28/2022
|
Not Ready for Inspection
|
OSVALDO PARAMO
|
|
HVAC-Rough
|
7/28/2022
|
Approved
|
OSVALDO PARAMO
|
|
ELECTRICAL-Rough
|
8/2/2022
|
Partial Approval
|
OSVALDO PARAMO
|
|
HVAC-Rough
|
8/2/2022
|
Approved
|
OSVALDO PARAMO
|
|
BUILDING-Rough-Frame
|
8/5/2022
|
Approved
|
OSVALDO PARAMO
|
|
Green Building Rough
|
8/5/2022
|
Approved
|
OSVALDO PARAMO
|
|
Verify Sprinkler Sign Off
|
8/5/2022
|
Approved
|
OSVALDO PARAMO
|
|
Insulation
|
8/16/2022
|
Approved
|
OSVALDO PARAMO
|
|
ELECTRICAL-Rough
|
9/1/2022
|
Approved
|
OSVALDO PARAMO
|
|
Interior/Exterior Lathing
|
9/7/2022
|
Partial Approval
|
OSVALDO PARAMO
|
|
Interior/Exterior Lathing
|
9/12/2022
|
Partial Approval
|
OSVALDO PARAMO
|
|
Drywall Nailing
|
9/20/2022
|
Not Ready for Inspection
|
OSVALDO PARAMO
|
|
Interior/Exterior Lathing
|
9/21/2022
|
Approved
|
OSVALDO PARAMO
|
|
Drywall Nailing
|
9/26/2022
|
Approved
|
OSVALDO PARAMO
|
|
Sewer
|
12/7/2022
|
Approved
|
OSVALDO PARAMO
|
|
Underground Mechanical
|
12/7/2022
|
Approved
|
OSVALDO PARAMO
|
|
Service/Power Release
|
1/23/2023
|
Not Ready for Inspection
|
OSVALDO PARAMO
|
|
Gas Test
|
1/24/2023
|
Approved
|
ALIZAH MAYAGOITIA
|
|
SGSOV-Seismic Gas S/O Valve
|
1/24/2023
|
SGSOV Approved
|
ALIZAH MAYAGOITIA
|
|
PLUMBING-Final
|
1/27/2023
|
Approved
|
SCOTT FINNILA
|
|
ELECTRICAL-Final
|
1/30/2023
|
Corrections Issued
|
OSVALDO PARAMO
|
|
ELECTRICAL-Final
|
2/7/2023
|
Partial Approval
|
OSVALDO PARAMO
|
|
HVAC-Final
|
2/7/2023
|
Partial Approval
|
OSVALDO PARAMO
|
|
ELECTRICAL-Final
|
2/17/2023
|
Approved
|
OSVALDO PARAMO
|
|
Grounding or Bonding
|
3/29/2023
|
Partial Inspection
|
OSVALDO PARAMO
|
|
Excavation/Setback/Form/Re-Bar
|
4/3/2023
|
Approved
|
OSVALDO PARAMO
|
|
Grounding or Bonding
|
4/3/2023
|
Approved
|
OSVALDO PARAMO
|
|
HVAC-Final
|
4/24/2023
|
Corrections Issued
|
ALIZAH MAYAGOITIA
|
|
Final
|
5/1/2023
|
Corrections Issued
|
OSVALDO PARAMO
|
|
Footing/Foundation/Slab
|
5/1/2023
|
Approved
|
OSVALDO PARAMO
|
|
Green Building Final
|
5/1/2023
|
Approved
|
OSVALDO PARAMO
|
|
HVAC-Final
|
5/1/2023
|
Approved
|
OSVALDO PARAMO
|
|
Service/Power Release
|
5/1/2023
|
Not Ready for Inspection
|
OSVALDO PARAMO
|
|
Smoke Detectors
|
5/1/2023
|
Approved
|
OSVALDO PARAMO
|
|
Final
|
6/27/2023
|
Corrections Issued
|
OSVALDO PARAMO
|
|
Service/Power Release
|
6/27/2023
|
Approved
|
OSVALDO PARAMO
|
|
Final
|
7/5/2023
|
OK to Issue CofO
|
OSVALDO PARAMO
|