3793 S DENKER AVE 90018

Certificate Information: 3793 S DENKER AVE 90018

Application / Permit
19010-10000-05061
Plan Check / Job No.
B19LA24107
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2 STORY ADU WITH ATTACHED 2 CAR GARAGE (1200 SF MAX PER ORDINANCE)
Permit Issued
Issued on 8/11/2021
Issuing Office
Current Status
CofO Issued on 10/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/12/2019 APPLICANT
Assigned to Plan Check Engineer 11/22/2019 SARAH ABOULHOSN
Corrections Issued 12/5/2019 SARAH ABOULHOSN
Quality Review Completed 12/10/2019 JASON HEALEY
Building Plans Picked Up 12/12/2019 APPLICANT
Green Plans Picked Up 12/16/2019 APPLICANT
Applicant returned to address corrections 1/13/2020 AUNG SOE
Applicant returned to address corrections 8/27/2020 AUNG SOE
Applicant returned to address corrections 9/2/2020 AUNG SOE
Plan Check Approved 9/3/2020 AUNG SOE
Issued 8/11/2021 APPLICANT
CofO in Progress 9/23/2022 SABAS ALONSO
Permit Finaled 10/1/2022 DEROLD HAUFF
CofO Issued 10/1/2022 DEROLD HAUFF
Permit Finaled 10/1/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/17/2019 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 12/17/2019 EMIL KYUPELYAN
Green Code Cleared 1/3/2020 VIVIAN LAO
Sewer availability Cleared 1/3/2020 ERIK BEASLEY
Low Impact Development Cleared 1/7/2020 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 1/7/2020 ELAINE LEI
Stormwater Pollution Mitigatn Cleared 1/7/2020 ORVAL HERNANDEZ-MARCIAL

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/22/2021 Corrections Issued SHAVONNE ESPINOZA
Excavation/Setback/Form/Re-Bar 11/30/2021 Corrections Issued SABAS ALONSO
Underground Mechanical 11/30/2021 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 12/10/2021 Conditional Approval SABAS ALONSO
Underground Mechanical 12/10/2021 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 12/27/2021 Partial Approval SABAS ALONSO
Green Building Rough 12/27/2021 Not Ready for Inspection SABAS ALONSO
Verify Sprinkler Sign Off 12/27/2021 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 1/20/2022 Not Ready for Inspection SABAS ALONSO
HVAC-Rough 1/20/2022 Not Ready for Inspection SABAS ALONSO
PLUMBING-Rough 1/20/2022 Partial Inspection SABAS ALONSO
Underground Mechanical 1/20/2022 Partial Inspection SABAS ALONSO
BUILDING-Rough-Frame 1/27/2022 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 1/27/2022 Corrections Issued SABAS ALONSO
Green Building Rough 1/27/2022 Not Ready for Inspection SABAS ALONSO
HVAC-Rough 1/27/2022 Not Ready for Inspection SABAS ALONSO
PLUMBING-Rough 1/27/2022 Approved SABAS ALONSO
Verify Sprinkler Sign Off 1/27/2022 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 2/1/2022 Approved SABAS ALONSO
HVAC-Rough 2/1/2022 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 2/4/2022 Not Ready for Inspection SABAS ALONSO
Green Building Rough 2/4/2022 Approved SABAS ALONSO
HVAC-Rough 2/4/2022 Not Ready for Inspection SABAS ALONSO
Verify Sprinkler Sign Off 2/4/2022 Approved SABAS ALONSO
BUILDING-Rough-Frame 2/9/2022 Approved SABAS ALONSO
HVAC-Rough 2/9/2022 Not Ready for Inspection SABAS ALONSO
Insulation 2/14/2022 Corrections Issued SABAS ALONSO
Interior/Exterior Lathing 2/14/2022 Partial Approval SABAS ALONSO
HVAC-Rough 2/18/2022 Approved ALIZAH MAYAGOITIA
Insulation 2/18/2022 Approved ALIZAH MAYAGOITIA
Drywall Nailing 2/24/2022 Approved HORACE FULTZ
Interior/Exterior Lathing 3/4/2022 Approved SABAS ALONSO
ELECTRICAL-Final 4/6/2022 Corrections Issued SABAS ALONSO
Gas Test 4/6/2022 Not Ready for Inspection SABAS ALONSO
PLUMBING-Final 4/6/2022 Approved SABAS ALONSO
ELECTRICAL-Final 5/5/2022 Partial Approval HORACE FULTZ
Gas Test 5/5/2022 Approved HORACE FULTZ
Final 5/10/2022 Not Ready for Inspection SABAS ALONSO
Footing/Foundation/Slab 5/10/2022 Approved SABAS ALONSO
Green Building Final 5/10/2022 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 5/10/2022 SGSOV Not Ready SABAS ALONSO
Service/Power Release 5/10/2022 Approved SABAS ALONSO
Smoke Detectors 5/10/2022 Not Ready for Inspection SABAS ALONSO
HVAC-Final 5/12/2022 Corrections Issued SABAS ALONSO
Final 5/19/2022 No Access for Inspection SABAS ALONSO
PLUMBING-Final 5/19/2022 No Access for Inspection SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 5/19/2022 SGSOV Not Ready SABAS ALONSO
Smoke Detectors 5/19/2022 No Access for Inspection SABAS ALONSO
Final 5/27/2022 Corrections Issued SABAS ALONSO
HVAC-Final 5/27/2022 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 5/27/2022 SGSOV Approved SABAS ALONSO
Smoke Detectors 5/27/2022 Approved SABAS ALONSO
Final 9/23/2022 OK to Issue CofO SABAS ALONSO