169 W VERNON AVE 90037
Certificate Information: 169 W VERNON AVE 90037
- Application / Permit
- 19010-10000-04968
- Plan Check / Job No.
- B19LA23740
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) DETACHED ACCESSORY DWELLING UNIT PER AB 494 and SB 229 PER WFPP
- Permit Issued
- Issued on 1/22/2020
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 9/23/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/6/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/14/2019 | ARSALAN SHABESTARI |
| Corrections Issued | 11/18/2019 | ARSALAN SHABESTARI |
| Green Plans Picked Up | 11/19/2019 | APPLICANT |
| Quality Review Completed | 11/23/2019 | YOUNG KIM |
| Building Plans Picked Up | 12/3/2019 | APPLICANT |
| Plan Check Approved | 1/21/2020 | ARSALAN SHABESTARI |
| Issued | 1/22/2020 | LADBS |
| CofO in Progress | 8/18/2020 | ROBERT MCDOWELL |
| Permit Finaled | 9/23/2020 | DEROLD HAUFF |
| CofO Issued | 9/23/2020 | DEROLD HAUFF |
| Permit Finaled | 9/23/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/4/2019 | EMIL KYUPELYAN |
| Community Plan Implem. Overlay | Cleared | 12/4/2019 | RICHARD REASER |
| Eng Process Fee Ord 176,300 | Cleared | 12/4/2019 | THOMAS LANG |
| Sewer availability | Cleared | 12/4/2019 | THOMAS LANG |
| Low Impact Development | Cleared | 1/16/2020 | ORVAL HERNANDEZ-MARCIAL |
| Roof/Waste drainage to street | Cleared | 1/16/2020 | JUAN ASHTON |
| Green Code | Cleared | 1/17/2020 | VIVIAN LAO |
| ZI | Cleared | 1/21/2020 | GISELLE CORELLA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 1/27/2020 | Approved | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 1/29/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 2/3/2020 | Approved | JOAQUIN GREENOUGH |
| Sewer | 2/6/2020 | Approved | COREY HUPP |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2020 | Partial Approval | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 2/26/2020 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 2/26/2020 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 2/26/2020 | Approved | JOAQUIN GREENOUGH |
| HVAC-Rough | 2/26/2020 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 2/26/2020 | Approved | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 2/26/2020 | Approved | JOAQUIN GREENOUGH |
| Insulation | 3/2/2020 | Approved | JOAQUIN GREENOUGH |
| Drywall Nailing | 3/5/2020 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Final | 3/20/2020 | Approved | JOAQUIN GREENOUGH |
| Final | 4/16/2020 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 4/16/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 4/16/2020 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Service/Power Release | 4/16/2020 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 4/16/2020 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 5/8/2020 | Approved | ROBERT MCDOWELL |
| Final | 5/8/2020 | Conditional Approval | ROBERT MCDOWELL |
| Green Building Final | 5/8/2020 | Approved | ROBERT MCDOWELL |
| HVAC-Final | 5/8/2020 | Approved | ROBERT MCDOWELL |
| SGSOV-Seismic Gas S/O Valve | 5/8/2020 | SGSOV Approved | ROBERT MCDOWELL |
| Final | 8/18/2020 | OK to Issue CofO | ROBERT MCDOWELL |