169 W VERNON AVE 90037

Certificate Information: 169 W VERNON AVE 90037

Application / Permit
19010-10000-04968
Plan Check / Job No.
B19LA23740
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) DETACHED ACCESSORY DWELLING UNIT PER AB 494 and SB 229 PER WFPP
Permit Issued
Issued on 1/22/2020
Issuing Office
South Los Angeles
Current Status
CofO Issued on 9/23/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/6/2019 APPLICANT
Assigned to Plan Check Engineer 11/14/2019 ARSALAN SHABESTARI
Corrections Issued 11/18/2019 ARSALAN SHABESTARI
Green Plans Picked Up 11/19/2019 APPLICANT
Quality Review Completed 11/23/2019 YOUNG KIM
Building Plans Picked Up 12/3/2019 APPLICANT
Plan Check Approved 1/21/2020 ARSALAN SHABESTARI
Issued 1/22/2020 LADBS
CofO in Progress 8/18/2020 ROBERT MCDOWELL
Permit Finaled 9/23/2020 DEROLD HAUFF
CofO Issued 9/23/2020 DEROLD HAUFF
Permit Finaled 9/23/2020 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/4/2019 EMIL KYUPELYAN
Community Plan Implem. Overlay Cleared 12/4/2019 RICHARD REASER
Eng Process Fee Ord 176,300 Cleared 12/4/2019 THOMAS LANG
Sewer availability Cleared 12/4/2019 THOMAS LANG
Low Impact Development Cleared 1/16/2020 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 1/16/2020 JUAN ASHTON
Green Code Cleared 1/17/2020 VIVIAN LAO
ZI Cleared 1/21/2020 GISELLE CORELLA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 1/27/2020 Approved JOAQUIN GREENOUGH
Footing/Foundation/Slab 1/29/2020 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 2/3/2020 Approved JOAQUIN GREENOUGH
Sewer 2/6/2020 Approved COREY HUPP
Floor/Roof Diaphrgm/Shear Wall 2/24/2020 Partial Approval JOAQUIN GREENOUGH
BUILDING-Rough-Frame 2/26/2020 Approved JOAQUIN GREENOUGH
ELECTRICAL-Rough 2/26/2020 Approved JOAQUIN GREENOUGH
Green Building Rough 2/26/2020 Approved JOAQUIN GREENOUGH
HVAC-Rough 2/26/2020 Approved JOAQUIN GREENOUGH
PLUMBING-Rough 2/26/2020 Approved JOAQUIN GREENOUGH
Verify Sprinkler Sign Off 2/26/2020 Approved JOAQUIN GREENOUGH
Insulation 3/2/2020 Approved JOAQUIN GREENOUGH
Drywall Nailing 3/5/2020 Approved JOAQUIN GREENOUGH
PLUMBING-Final 3/20/2020 Approved JOAQUIN GREENOUGH
Final 4/16/2020 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 4/16/2020 Partial Approval ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 4/16/2020 SGSOV Not Ready ALEJANDRO DE ARTOLA
Service/Power Release 4/16/2020 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 4/16/2020 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 5/8/2020 Approved ROBERT MCDOWELL
Final 5/8/2020 Conditional Approval ROBERT MCDOWELL
Green Building Final 5/8/2020 Approved ROBERT MCDOWELL
HVAC-Final 5/8/2020 Approved ROBERT MCDOWELL
SGSOV-Seismic Gas S/O Valve 5/8/2020 SGSOV Approved ROBERT MCDOWELL
Final 8/18/2020 OK to Issue CofO ROBERT MCDOWELL